Expected Completion Date
July 2024
Status Updated
July, 2024
| SL. No | Name of the work | Progress details |
| 01 | Foundation work | Foundation work 100% complete.
|
| 02 | Super Structure work | Ground floor to Roof top column casting 100% complete.
|
| 03 | Block Work | First floor to 9th floor blocks 100% complete.
Ground floor block work 100% complete.
|
| 04 | Electrical conduite work | 1st floor to 9th floor conduit work 100% Complete. |
| 05 | Door frame fitting work | 1st floor to 9th floor 100% door frame fitting Complete.
|
| 06 | Sanitary & plumbingline work | 1st floor to 9th floor 100% complete.
|
| 07 | In side Plastering work | 1st floor to 9th floor plaster 100% complete. |
| 08 | Electrical cable wiring work | 1st floor to 9th floor cable wiring 100% complete. |
| 09 | Wall tiles work | 1st floor to 9th floor 100% complete
|
| 10 | Common sanitary & Plumbing line work | 100% complete. |
| 11 | Outside plastering work | 1st floor to 9th floor plaster 100% complete. |
| 12 | Floor tiles/Marble work | 1st floor to 9th floor 100% complete.
|
| – | L.C.C work | L.C.C work 100% complete. |
| 14 | Grill & Railing work | 1st floor to 9th floor 100% complete.
|
| 15 | Inside paint & Polishing work | 1st floor to 9th floor 100% complete.
|
| 16 | Switch -Socket fitting work | 1st floor to 2nd floor 100% complete.
|
| 17 | Outside paint work | 1st floor to 9th floor outside paint work 100% complete.
|
| 18 | Door shutter work | 1st floor to 9th floor door shutter work 100% complete
|
| 19 | Aluminum/Glazing work | 1st floor to 9th floor aluminum work 100% complete
|
| 20 | Tiles Pointing work & Marble finishing work | 1st floor to 9th floor pointing work 100% complete.
|
| 21 | Commode – Basin fitting work and C.P fittings work | 1st floor to 9th floor pointing work 100% complete |
| 22 | Lift/Generator /Substation /Solar work | Lift/Generator /Substation /Solar work 100% complete. |
| 23 | Boundary wall /Ground floor development work | Ground Floor development work 100% complete.
False Celling development work 100 % complete.
|
| 24 | Roof top finishing work | Roof top finishing work 100% complete. |
| 25 | Roof top Gardening work | Roof top gardening work 100% complete. |