Completion Date
July 2024
Status Updated
July, 2024
SL. No | Name of the work | Progress details |
01 | Foundation work | Foundation work 100% complete.
|
02 | Super Structure work | Ground floor to Roof top column casting 100% complete.
|
03 | Block Work | First floor to 9th floor blocks 100% complete.
Ground floor block work 100% complete.
|
04 | Electrical conduite work | 1st floor to 9th floor conduit work 100% Complete. |
05 | Door frame fitting work | 1st floor to 9th floor 100% door frame fitting Complete.
|
06 | Sanitary & plumbingline work | 1st floor to 9th floor 100% complete.
|
07 | In side Plastering work | 1st floor to 9th floor plaster 100% complete. |
08 | Electrical cable wiring work | 1st floor to 9th floor cable wiring 100% complete. |
09 | Wall tiles work | 1st floor to 9th floor 100% complete
|
10 | Common sanitary & Plumbing line work | 100% complete. |
11 | Outside plastering work | 1st floor to 9th floor plaster 100% complete. |
12 | Floor tiles/Marble work | 1st floor to 9th floor 100% complete.
|
– | L.C.C work | L.C.C work 100% complete. |
14 | Grill & Railing work | 1st floor to 9th floor 100% complete.
|
15 | Inside paint & Polishing work | 1st floor to 9th floor 100% complete.
|
16 | Switch -Socket fitting work | 1st floor to 2nd floor 100% complete.
|
17 | Outside paint work | 1st floor to 9th floor outside paint work 100% complete.
|
18 | Door shutter work | 1st floor to 9th floor door shutter work 100% complete
|
19 | Aluminum/Glazing work | 1st floor to 9th floor aluminum work 100% complete
|
20 | Tiles Pointing work & Marble finishing work | 1st floor to 9th floor pointing work 100% complete.
|
21 | Commode – Basin fitting work and C.P fittings work | 1st floor to 9th floor pointing work 100% complete |
22 | Lift/Generator /Substation /Solar work | Lift/Generator /Substation /Solar work 100% complete. |
23 | Boundary wall /Ground floor development work | Ground Floor development work 100% complete.
False Celling development work 100 % complete.
|
24 | Roof top finishing work | Roof top finishing work 100% complete. |
25 | Roof top Gardening work | Roof top gardening work 100% complete. |