Silver Creek

Banani, Dhaka
Expected Completion Date July 2024
Status Updated July, 2024
Back to all projects
Silver Creek

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work Foundation work 100% complete.

 

02 Super Structure work Ground floor to Roof top column casting 100% complete.

 

03 Block Work First floor to 9th floor blocks 100% complete.

Ground floor block work 100% complete.

 

04 Electrical conduite work 1st floor to 9th floor conduit work 100% Complete.
05 Door frame fitting work 1st floor to 9th floor 100% door frame fitting Complete.

 

06 Sanitary & plumbingline work 1st floor to 9th floor 100% complete.

 

 

07 In side Plastering work 1st floor to 9th floor plaster 100% complete.
08 Electrical cable wiring work 1st floor to 9th floor cable wiring 100% complete.
09 Wall tiles work 1st floor to 9th floor 100% complete

 

 

10 Common sanitary & Plumbing line work 100% complete.
11 Outside plastering work 1st floor to 9th floor plaster 100% complete.
12 Floor tiles/Marble work 1st floor to 9th floor 100% complete.

 

L.C.C work L.C.C work 100% complete.
14 Grill & Railing work 1st floor to 9th floor 100% complete.

 

 

15 Inside paint & Polishing work 1st floor to 9th floor 100% complete.

 

 

16 Switch -Socket fitting work 1st floor to 2nd floor 100% complete.

 

 

17 Outside paint work 1st floor to 9th floor outside paint work 100% complete.

 

18 Door shutter work 1st floor to 9th floor door shutter work 100% complete

 

19 Aluminum/Glazing work 1st floor to 9th floor aluminum work 100% complete

 

20 Tiles Pointing work & Marble finishing work 1st floor to 9th floor pointing work 100% complete.

 

 

21 Commode – Basin fitting work and C.P fittings work 1st floor to 9th floor pointing work 100% complete
22 Lift/Generator /Substation /Solar work Lift/Generator /Substation /Solar work 100% complete.
23 Boundary wall /Ground floor development work Ground Floor development work 100% complete.

False Celling development work 100 % complete.

 

24 Roof top finishing work Roof top finishing work 100% complete.
25 Roof top Gardening work Roof top gardening work 100% complete.