Silvi

Gulshan, Dhaka

Expected Completion Date

March 2026

Status Updated

January, 2026

SL. No Name of the work Progress details
01 Foundation work Footing casting 100% completed, Mat casting 100% completed, retaining wall 100% completed, Basement roof 100% completed.
02 Super Structure work 100% Completed. (G.F 100%, 1st Floor Roof Slab -100%, 2nd Floor Roof Slab -100%, 3rd Floor Roof Slab -100%, 4th Floor Roof Slab -100% completed. 5th floor roof slab 100% completed), 6th floor roof slab 100% completed, 7th floor roof slab 100% completed, 8th floor slab 100% completed.
03 Partition Wall Work 100% Completed.
04 Electrical conducting work 80% Completed.
05 Door frame fitting work 50% completed.
06 Sanitary & plumbing line work 60% completed.
07 In side Plastering work 49% completed.
08 Electrical cable wiring work 20% completed.
09 Wall tiles work 25% completed.
10 Common sanitary & Plumbing line work 70% Completed.
11 Outside plastering work 90% Completed.
12 Floor tiles/Marble work 13% completed.
13 L.C.C work Not Yet Started.
14 Grill & Railing work 25% completed.
15 Inside paint & Polishing work Not Yet Started.
16 Switch -Socket fitting work Not Yet Started.
17 Outside paint work Not Yet Started.
18 Door shutter work Not Yet Started.
19 Aluminum/Glazing work Not Yet Started.
20 Tiles Pointing work & Marble finishing work Not Yet Started.
21 Commode – Basin fitting work and C.P fittings work Not Yet Started.
22 Lift/Generator /Substation /Solar work Not Yet Started.
23 Boundary wall /Ground floor development work Not Yet Started.
24 Roof top finishing work Not Yet Started.
25 Roof top Gardening work Construction work 80%

 