Silvi

Gulshan, Dhaka

Expected Completion Date

January 2026

Status Updated

November, 2024

SL. No Name of the work Progress details
01 Foundation work Footing casting 100% completed, Mat casting 100% completed, retaining wall 100% completed, Basement roof 100% completed.
02 Super Structure work 70 % Completed. (G.F 100%, 1st Floor Roof Slab -100%, 2nd Floor Roof Slab -100%, 3rd Floor Roof Slab -100%, 4th Floor Roof Slab -100% completed. 5th floor roof slab 100% completed), 6th floor roof slab 100% completed)
03 Block Work 25% Completed. (Common)
04 Electrical conducting work 5% Completed.
05 Door frame fitting work  
06 Sanitary & plumbing line work  
07 In side Plastering work  
08 Electrical cable wiring work  
09 Wall tiles work  
10 Common sanitary & Plumbing line work  
11 Outside plastering work  
12 Floor tiles/Marble work  
13 L.C.C work  
14 Grill & Railing work  
15 Inside paint & Polishing work  
16 Switch -Socket fitting work  
17 Outside paint work  
18 Door shutter work  
19 Aluminum/Glazing work  
20 Tiles Pointing work & Marble finishing work  
21 Commode – Basin fitting work and C.P fittings work  
22 Lift/Generator /Substation /Solar work  
23 Boundary wall /Ground floor development work  
24 Roof top finishing work  
25 Roof top Gardening work  

 

16604