Silvi

Gulshan, Dhaka

Expected Completion Date

October 2025

Status Updated

May, 2025

SL. No Name of the work Progress details
01 Foundation work Footing casting 100% completed, Mat casting 100% completed, retaining wall 100% completed, Basement roof 100% completed.
02 Super Structure work 100% Completed. (G.F 100%, 1st Floor Roof Slab -100%, 2nd Floor Roof Slab -100%, 3rd Floor Roof Slab -100%, 4th Floor Roof Slab -100% completed. 5th floor roof slab 100% completed), 6th floor roof slab 100% completed, 8th floor slab 100% completed.
03 Block Work 30% Completed. (Common)
04 Electrical conducting work 5% Completed.
05 Door frame fitting work Not Yet Started.
06 Sanitary & plumbing line work Not Yet Started.
07 In side Plastering work 10% completed.
08 Electrical cable wiring work Not Yet Started.
09 Wall tiles work Not Yet Started.
10 Common sanitary & Plumbing line work Not Yet Started.
11 Outside plastering work Not Yet Started.
12 Floor tiles/Marble work Not Yet Started.
13 L.C.C work Not Yet Started.
14 Grill & Railing work Not Yet Started.
15 Inside paint & Polishing work Not Yet Started.
16 Switch -Socket fitting work Not Yet Started.
17 Outside paint work Not Yet Started.
18 Door shutter work Not Yet Started.
19 Aluminum/Glazing work Not Yet Started.
20 Tiles Pointing work & Marble finishing work Not Yet Started.
21 Commode – Basin fitting work and C.P fittings work Not Yet Started.
22 Lift/Generator /Substation /Solar work Not Yet Started.
23 Boundary wall /Ground floor development work Not Yet Started.
24 Roof top finishing work Not Yet Started.
25 Roof top Gardening work Not Yet Started.

16604