Silvi

Gulshan, Dhaka

Expected Completion Date

October 2025

Status Updated

March, 2025

SL. No Name of the work Progress details
01 Foundation work Footing casting 100% completed, Mat casting 100% completed, retaining wall 100% completed, Basement roof 100% completed.
02 Super Structure work 97% Completed. (G.F 100%, 1st Floor Roof Slab -100%, 2nd Floor Roof Slab -100%, 3rd Floor Roof Slab -100%, 4th Floor Roof Slab -100% completed. 5th floor roof slab 100% completed), 6th floor roof slab 100% completed, 8th floor slab 100% completed.
03 Block Work 25% Completed. (Common)
04 Electrical conducting work 5% Completed.
05 Door frame fitting work Not Yet Started.
06 Sanitary & plumbing line work Not Yet Started.
07 In side Plastering work Not Yet Started.
08 Electrical cable wiring work Not Yet Started.
09 Wall tiles work Not Yet Started.
10 Common sanitary & Plumbing line work Not Yet Started.
11 Outside plastering work Not Yet Started.
12 Floor tiles/Marble work Not Yet Started.
13 L.C.C work Not Yet Started.
14 Grill & Railing work Not Yet Started.
15 Inside paint & Polishing work Not Yet Started.
16 Switch -Socket fitting work Not Yet Started.
17 Outside paint work Not Yet Started.
18 Door shutter work Not Yet Started.
19 Aluminum/Glazing work Not Yet Started.
20 Tiles Pointing work & Marble finishing work Not Yet Started.
21 Commode – Basin fitting work and C.P fittings work Not Yet Started.
22 Lift/Generator /Substation /Solar work Not Yet Started.
23 Boundary wall /Ground floor development work Not Yet Started.
24 Roof top finishing work Not Yet Started.
25 Roof top Gardening work Not Yet Started.

 