Expected Completion Date
October 2025
Status Updated
March, 2025
SL. No | Name of the work | Progress details |
01 | Foundation work | Footing casting 100% completed, Mat casting 100% completed, retaining wall 100% completed, Basement roof 100% completed. |
02 | Super Structure work | 97% Completed. (G.F 100%, 1st Floor Roof Slab -100%, 2nd Floor Roof Slab -100%, 3rd Floor Roof Slab -100%, 4th Floor Roof Slab -100% completed. 5th floor roof slab 100% completed), 6th floor roof slab 100% completed, 8th floor slab 100% completed. |
03 | Block Work | 25% Completed. (Common) |
04 | Electrical conducting work | 5% Completed. |
05 | Door frame fitting work | Not Yet Started. |
06 | Sanitary & plumbing line work | Not Yet Started. |
07 | In side Plastering work | Not Yet Started. |
08 | Electrical cable wiring work | Not Yet Started. |
09 | Wall tiles work | Not Yet Started. |
10 | Common sanitary & Plumbing line work | Not Yet Started. |
11 | Outside plastering work | Not Yet Started. |
12 | Floor tiles/Marble work | Not Yet Started. |
13 | L.C.C work | Not Yet Started. |
14 | Grill & Railing work | Not Yet Started. |
15 | Inside paint & Polishing work | Not Yet Started. |
16 | Switch -Socket fitting work | Not Yet Started. |
17 | Outside paint work | Not Yet Started. |
18 | Door shutter work | Not Yet Started. |
19 | Aluminum/Glazing work | Not Yet Started. |
20 | Tiles Pointing work & Marble finishing work | Not Yet Started. |
21 | Commode – Basin fitting work and C.P fittings work | Not Yet Started. |
22 | Lift/Generator /Substation /Solar work | Not Yet Started. |
23 | Boundary wall /Ground floor development work | Not Yet Started. |
24 | Roof top finishing work | Not Yet Started. |
25 | Roof top Gardening work | Not Yet Started. |