bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

Silvi

Gulshan, Dhaka
Expected Completion Date June 2026
Status Updated April, 2026
Back to all projects
Silvi

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work Footing casting 100% completed, Mat casting 100% completed, retaining wall 100% completed, Basement roof 100% completed.
02 Super Structure work 100% Completed. (G.F 100%, 1st Floor Roof Slab -100%, 2nd Floor Roof Slab -100%, 3rd Floor Roof Slab -100%, 4th Floor Roof Slab -100% completed. 5th floor roof slab 100% completed), 6th floor roof slab 100% completed, 7th floor roof slab 100% completed, 8th floor slab 100% completed.
03 Partition Wall Work 100% Completed.
04 Electrical conducting work 90% Completed.
05 Door frame fitting work 98% completed.
06 Sanitary & plumbing line work 90% completed.
07 In side Plastering work 92% completed.
08 Electrical cable wiring work 80% completed.
09 Wall tiles work 80% completed.
10 Common sanitary & Plumbing line work 87% Completed.
11 Outside plastering work 95% Completed.
12 Floor tiles/Marble work 70% completed.
13 L.C.C work Not Yet Started.
14 Grill & Railing work 50% completed.
15 Inside paint & Polishing work Not Yet Started.
16 Switch -Socket fitting work Not Yet Started.
17 Outside paint work Not Yet Started.
18 Door shutter work Not Yet Started.
19 Aluminum/Glazing work Not Yet Started.
20 Tiles Pointing work & Marble finishing work Not Yet Started.
21 Commode – Basin fitting work and C.P fittings work Not Yet Started.
22 Lift/Generator /Substation /Solar work Not Yet Started.
23 Boundary wall /Ground floor development work Not Yet Started.
24 Roof top finishing work Not Yet Started.
25 Roof top Gardening work Construction work 90%