Completion Date
January 2026
Status Updated
September, 2024
SL. No | Name of the work | Progress details |
01 | Foundation work | Footing casting 100% completed, Mat casting 100% completed, retaining wall 100% completed, Basement roof 100% completed. |
02 | Super Structure work | 50% Completed. (5th floor roof slab casting completed). |
03 | Block Work | 20% Completed. |
04 | Electrical conducting work | 5% Completed. |
05 | Door frame fitting work | |
06 | Sanitary & plumbing line work | |
07 | In side Plastering work | |
08 | Electrical cable wiring work | |
09 | Wall tiles work | |
10 | Common sanitary & Plumbing line work | |
11 | Outside plastering work | |
12 | Floor tiles/Marble work | |
13 | L.C.C work | |
14 | Grill & Railing work | |
15 | Inside paint & Polishing work | |
16 | Switch -Socket fitting work | |
17 | Outside paint work | |
18 | Door shutter work | |
19 | Aluminum/Glazing work | |
20 | Tiles Pointing work & Marble finishing work | |
21 | Commode – Basin fitting work and C.P fittings work | |
22 | Lift/Generator /Substation /Solar work | |
23 | Boundary wall /Ground floor development work | |
24 | Roof top finishing work | |
25 | Roof top Gardening work |