South Serenity

Bashundhara R/A, Dhaka
Expected Completion Date March 2028
Status Updated April, 2026
Back to all projects
South Serenity

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed  
02 Super Structure work   60% completed  
03 Block Work Ground floor 115mm CSB

1st floor

2nd Floor

3rd Floor

4th floor

5th floor

6th floor

7th floor

8th floor

 

20% Complete

 

10% Complete

5% Complete

0% Complete

0% Complete

0% Complete

0% Complete

0% Complete

0% Complete

 

 

 

 

 
04 Electrical conduiting work      
05 Door frame fitting work      
06 Sanitary & plumbing line work      
07 In side Plastering work      
08 Electrical cable wiring work      
09 Wall tiles work      
10 Common sanitary & Plumbing line work      
11 Outside plastering work      
12 Floor tiles/Marble work      
13 L.C.C work      
14 Grill & Railing work      
15 Inside paint & Polishing work      
16 Switch -Socket fitting work      
17 Outside paint work      
18 Door shutter work      
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode-Basin fitting work and CP fittings work      
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work GF 40 % Complete  
24 Roof top finishing work      
25 Roof top Gardening work G.F Garden work      

 