South Serenity

Block J, Bashundhara R/A

Expected Completion Date

March 2028

Status Updated

April, 2026

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed  
02 Super Structure work   60% completed  
03 Block Work Ground floor 115mm CSB

1st floor

2nd Floor

3rd Floor

4th floor

5th floor

6th floor

7th floor

8th floor

 

20% Complete

 

10% Complete

5% Complete

0% Complete

0% Complete

0% Complete

0% Complete

0% Complete

0% Complete

 

 

 

 

 
04 Electrical conduiting work      
05 Door frame fitting work      
06 Sanitary & plumbing line work      
07 In side Plastering work      
08 Electrical cable wiring work      
09 Wall tiles work      
10 Common sanitary & Plumbing line work      
11 Outside plastering work      
12 Floor tiles/Marble work      
13 L.C.C work      
14 Grill & Railing work      
15 Inside paint & Polishing work      
16 Switch -Socket fitting work      
17 Outside paint work      
18 Door shutter work      
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode-Basin fitting work and CP fittings work      
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work GF 40 % Complete  
24 Roof top finishing work      
25 Roof top Gardening work G.F Garden work      

 