Spring Field

Bashundhara R/A, Dhaka

Expected Completion Date

September 2025

Status Updated

September, 2025

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed.  
02 Super Structure work   100% Completed  
03 Block Work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
04 Electrical conduiting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

 
05 Door frame fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
06 Sanitary and plumbing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

80%Complete

80%Complete

80%Complete

80%Complete

80%Complete

80%Complete

80%Complete

80%Complete

80%Complete

 
07 In side Plastering work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

 

95%Complete

95%Complete

95%Complete

95%Complete

95%Complete

95%Complete

95%Complete

95%Complete

95%Complete

 

 
08 Electrical cable wiring work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

 

90%Complete

90%Complete

90%Complete

90%Complete

90%Complete

90%Complete

90%Complete

90%Complete

90%Complete

 

 

 

 

09 Wall tiles work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

85%Complete

85%Complete

90%Complete

95%Complete

95%Complete

95%Complete

95%Complete

40%Complete

90%Complete

 
10 Common sanitary & Plumbing line work    

 

 
11 Outside plastering work   95%Complete

 

 
12 Floor tiles/Marble work   80%Complete

 

 
13 L.C.C work   100%Complete

 

 
14 Grill & Railing work   65%Complete

 

 
15 Inside paint & Polishing work      
16 Switch -Socket fitting work      
17 Outside paint work      
18 Door shutter work      
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode – Basin fitting work and C.P fittings work    

 

 

 
22 Lift/Generator /Substation /Solar work   85%Complete

 

 
23 Boundary wall /Ground floor development work   70%Complete

 

 
24 Roof top finishing work   40%Complete

 

 
25 Roof top Gardening work G.F Garden work      

 

16604