Expected Completion Date
August 2025
Status Updated
February, 2025
SL. No | Name of the work | Location | Progress details | Remarks |
01 | Foundation work | 100% Complete | ||
02 | Super Structure work | parapet wall casting 70%
over head tank wall casting, veranda slab casting 70% |
||
03 | Block Work | Apartment A1
Apartment A2 Apartment A3 Apartment A4 Apartment A5 Apartment A6 Apartment A7 Apartment A8 Apartment A9
|
85% Complete
95% Complete 98% Complete 98% Complete 98% Complete 98% Complete 85% Complete 85% complete 80% complete |
|
04 | Electrical conduiting work | Apartment A1
Apartment A2 Apartment A3 Apartment A4 Apartment A5 Apartment A6 Apartment A7 Apartment A8 Apartment A9
|
85% Complete
90% Complete 98% Complete 98% Complete 98% Complete 98% Complete 85% Complete 80% Complete 75% Complete
|
|
05 | Door frame fitting work | Apartment A1
Apartment A2 Apartment A3 Apartment A4 Apartment A5 Apartment A6 Apartment A7
|
100% Complete
100% Complete 100% Complete 95% complete 95% Complete 95% Complete 75% Complete
|
|
06 | Sanitary & plumbing line work | Vertical plumbing line 30%
Vertical ppr line 30% |
||
07 | In side Plastering work | Ground floor
Apartment A1 Apartment A2 Apartment A3 Apartment A4 Apartment A5 Apartment A6 Apartment A7 Apartment A8 Apartment A9 |
Celling 80% Complete
Celling 90% & Inside wall 20% Celling 100% & Inside wall 90% Celling 100% & Inside wall 90% Celling 100% & Inside wall 90% Celling100% & Inside wall 90% Celling 100% & Inside wall 90% Celing 100% & Inside wall 20% Celing 100% Complete Ceiling 100% Complete |
|
08 | Electrical cable wiring work | |||
09 | Wall tiles work | |||
10 | Common sanitary & Plumbing line work | |||
11 | Outside plastering work | |||
12 | Floor tiles/Marble work | |||
13 | L.C.C work | |||
14 | Grill & Railing work | |||
15 | Inside paint & Polishing work | |||
16 | Switch -Socket fitting work | |||
17 | Outside paint work | |||
18 | Door shutter work | |||
19 | Aluminum work | |||
20 | Tiles Pointing work & Marble finishing work | |||
21 | Commode – Basin fitting work and C.P fittings work | |||
22 | Lift/Generator /Substation /Solar work | |||
23 | Boundary wall /Ground floor development work | |||
24 | Roof top finishing work | |||
25 | Roof top Gardening work G.F Garden work |
16604