Spring Field

Bashundhara R/A, Dhaka

Expected Completion Date

August 2025

Status Updated

December, 2024

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% Complete  
02 Super Structure work 9th Floor Column Work is on Progress.  
03 Block Work Apartment A1

Apartment A2

Apartment A3

Apartment A4

Apartment A5

Apartment A6

Apartment A7

 

75% Complete

95% Complete

98% Complete

95% Complete

95% Complete

85% Complete

45% Complete

 
04 Electrical conduiting work Apartment A1

Apartment A2

Apartment A3

Apartment A4

Apartment A5

Apartment A6

Apartment A7

 

55% Complete

80% Complete

95% Complete

95% Complete

90% Complete

70% Complete

20% Complete

 

 
05 Door frame fitting work Apartment A3

Apartment A4

Apartment A5

 

100% Complete

90% Complete

90% Complete

 

 

 
06 Sanitary & plumbing line  work      
07 In side Plastering work Ground floor

Apartment A1

Apartment A2

Apartment A3

 

Apartment A4

 

Apartment A5

 

Apartment A6

Apartment A7

 

Ceiling 80% Complete

Ceiling 90% Complete

Ceiling 100% Complete

Ceiling 100% & Inside wall 90%

Ceiling 100% & Inside wall 90%

Ceiling100% & Inside wall 80%

Ceiling 100% Complete

Ceiling 100% Complete

 

 

 

 

 

 

08 Electrical cable wiring work      
09 Wall tiles  work      
10 Common sanitary & Plumbing line work      
11 Outside plastering work      
12 Floor tiles/Marble work      
13 L.C.C work      
14 Grill & Railing work      
15 Inside paint & Polishing work      
16 Switch -Socket fitting work      
17 Outside paint work      
18 Door shutter work      
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode – Basin fitting work and C.P fittings work      
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work      
24 Roof top finishing work      
25 Roof top Gardening work G.F Garden work      