Spring Field

Bashundhara R/A, Dhaka

Expected Completion Date

March 2026

Status Updated

March, 2026

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed.  
02 Super Structure work   100% Completed  
03 Block Work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
04 Electrical conduiting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
05 Door frame fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
06 Sanitary and plumbing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

 

95%Complete

95%Complete

95%Complete

95%Complete

95%Complete

95%Complete

95%Complete

95%Complete

95%Complete

 

 

 

 
07 In side Plastering work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

 

100%Complete

100%Complete

100%Complete

100%Complete

100%Complete

100%Complete

100%Complete

100%Complete

100%Complete

 

 
08 Electrical cable wiring work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

 

100%Complete

100%Complete

100%Complete

100%Complete

100%Complete

100%Complete

100%Complete

100%Complete

100%Complete

 

 

 

 

09 Wall tiles work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

 

99%Complete

99%Complete

100%Complete

100%Complete

100%Complete

100%Complete

100%Complete

99%Complete

100%Complete

 

 
10 Common sanitary & Plumbing line work    

 

 
11 Outside plastering work   99%Complete

 

 
12 Floor tiles/Marble work   98%Complete

 

 
13 L.C.C work   100%Complete

 

 
14 Grill & Railing work   95%Complete

 

 
15 Inside paint & Polishing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

 

70%Complete

70%Complete

70%Complete

70%Complete

70%Complete

70%Complete

70%Complete

70%Complete

70%Complete

 
16 Switch -Socket fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

 

0%Complete

0%Complete

80%Complete

100%Complete

100%Complete

100%Complete

100%Complete

100%Complete

100%Complete

 

 
17 Outside paint work All side 50 %Complete  
18 Door shutter work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

 

85%Complete

80%Complete

100%Complete

95%Complete

95%Complete

95%Complete

100%Complete

50%Complete

100%Complete

 

 
19 Aluminum work All apartment 95%Complete

 

 
20 Tiles Pointing work & Marble finishing work All wall tiles 90%Complete

 

 
21 Commode – Basin fitting work and C.P fittings work   30% complete

 

 

 
22 Lift/Generator /Substation /Solar work   99%Complete

 

 
23 Boundary wall /Ground floor development work   99%Complete

 

 
24 Roof top finishing work   92%Complete

 

 
25 Roof top Gardening work G.F Garden work   90%Complete

 

 