Spring Field

Bashundhara R/A, Dhaka

Completion Date

April 2025

Status Updated

March, 2024

SL. No Name of the work Progress details
01 Foundation work 100% Complete
02 Super Structure work Upto 3rd floor roof slab casting Completed & 4th floor roof slab & beam shuttering work ongoing.
03 Block Work  
04 Electrical conduiting work  
05 Door frame fitting work  
06 Sanitary & plumbing line  work  
07 In side Plastering work A2 – 80% celing plaster completed
08 Electrical cable wiring work  
09 Wall tiles  work  
10 Common sanitary & Plumbing line work  
11 Outside plastering work  
12 Floor tiles/Marble work  
13 L.C.C work  
14 Grill & Railing work  
15 Inside paint & Polishing work  
16 Switch -Socket fitting work  
17 Outside paint work  
18 Door shutter work  
19 Aluminum work  
20 Tiles Pointing work & Marble finishing work  
21 Commode – Basin fitting work and C.P fittings work  
22 Lift/Generator /Substation /Solar work  
23 Boundary wall /Ground floor development work  
24 Roof top finishing work  
25 Roof top Gardening work G.F Garden work  

16604