Spring Field

Bashundhara R/A, Dhaka

Completion Date

April 2025

Status Updated

June, 2024

SL. No Name of the work Progress details (June)
01 Foundation work 100% Complete
02 Super Structure work 5th floor Column work is going on.
03 Block Work A1 – 45%

A2 –  75%

A3 – 75%

04 Electrical conduiting work A1 – 45%

A2 -60%

A3 – 50%

 

05 Door frame fitting work  
06 Sanitary & plumbing line  work  
07 In side Plastering work A1 (ceiling plaster)- 80%

A2 celing plaster 100%

A3 celing plaster 100%

G.F celing plaster 80%

08 Electrical cable wiring work  
09 Wall tiles  work  
10 Common sanitary & Plumbing line work  
11 Outside plastering work  
12 Floor tiles/Marble work  
13 L.C.C work  
14 Grill & Railing work  
15 Inside paint & Polishing work  
16 Switch -Socket fitting work  
17 Outside paint work  
18 Door shutter work  
19 Aluminum work  
20 Tiles Pointing work & Marble finishing work  
21 Commode – Basin fitting work and C.P fittings work  
22 Lift/Generator /Substation /Solar work  
23 Boundary wall /Ground floor development work  
24 Roof top finishing work  
25 Roof top Gardening work G.F Garden work  

 