Sunny Hill

Mirpur, Dhaka
Expected Completion Date July 2027
Status Updated April, 2026
Back to all projects
Sunny Hill

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
1 Foundation work 100% Completed
2 Super Structure work 97%
3 Block work 80%
4 Electrical conduit work 20%
5 Door frame fitting work N/A
6 Sanitary & plumbing line work 5%
7 In side Plastering work 40%
8 Electrical cable wiring work N/A
9 Wall tiles work N/A
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work N/A
12 Floor tiles/Marble work N/A
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum/Glazing work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work 20%
24 Roof top finishing work N/A
25 Roof top Gardening work N/A