The Boulevard

Bashundhara R/A, Dhaka

Expected Completion Date

April 2025

Status Updated

February, 2025

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 98% completed
  Block work A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%.
  Electrical  conduit work A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%.
  Door frame fitting work A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%.
  Sanitary & plumbing line  work A-1=80%,A-2=80%A-3=80%, A-4=80%,A-5=80% ,A-6 =80%,A-7=80%,A-8=80%.
  In side Plastering work A-1=98%,A-2=98%A-3=98%, A-4=98%,A-5=98% ,A-6 =98%,A-7=98%,A-8=98%.
  Electrical cable wiring work A-1=85%,A-2=85%A-3=85%, A-4=85%,A-5=85% ,A-6 =85%,A-7=85%,A-8=85%.
  Wall tiles  work 80%
  Common sanitary & Plumbing line work 70%
  Outside plastering work 96%
  Floor tiles/Marble work A-1=80%,A-2=80%A-3=80%, A-4=85%, A-5=95% ,A-6 =95%,A-7=95%,A-8=95%.
  L.C.C work 30%
  Grill & Railing work 70%
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work N/A
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work 40%
  Boundary wall /Ground floor development work 50%
  Roof top finishing work N/A
  Roof top Gardening work N/A