The Boulevard

Bashundhara R/A, Dhaka

Expected Completion Date

April 2025

Status Updated

March, 2025

S/N Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 98% completed
  Block work A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%.
  Electrical  conduit work A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%.
  Door frame fitting work A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%.
  Sanitary & plumbing line  work A-1=85%,A-2=85%A-3=85%, A-4=85%,A-5=85% ,A-6 =85%,A-7=85%,A-8=85%.
  In side Plastering work A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%.
  Electrical cable wiring work A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%.
  Wall tiles  work 90%
  Common sanitary & Plumbing line work 75%
  Outside plastering work 98%
  Floor tiles/Marble work A-1=95%,A-2=98%A-3=95%, A-4=98%, A-5=98% ,A-6 =98%,A-7=98%,A-8=98%.
  L.C.C work 100%
  Grill & Railing work 75%
  Inside paint & Polishing work 50%
  Switch -Socket fitting work N/A
  Outside paint work 20%
  Door shutter work 30%
  Aluminum/Glazing work 55%
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work 50%
  Boundary wall /Ground floor development work 70%
  Roof top finishing work N/A
  Roof top Gardening work N/A

 