Expected Completion Date
April 2025
Status Updated
December, 2024
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 96% completed | |
Block work | A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%. | |
Electrical conduit work | A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%. | |
Door frame fitting work | A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%. | |
Sanitary & plumbing line work | A-1=70%,A-2=70%A-3=70%, A-4=70%,A-5=70% ,A-6 =70%,A-7=70%,A-8=70%. | |
In side Plastering work | A-1=98%,A-2=98%A-3=98%, A-4=98%,A-5=98% ,A-6 =98%,A-7=98%,A-8=98%. | |
Electrical cable wiring work | A-1=75%,A-2=75%A-3=75%, A-4=75%,A-5=75% ,A-6 =75%,A-7=75%,A-8=75%. | |
Wall tiles work | 60% | |
Common sanitary & Plumbing line work | 15% | |
Outside plastering work | 80% | |
Floor tiles/Marble work | A-1=65%,A-2=70%A-3=70%, A-4=65%, A-5=65% ,A-6 =65%,A-7=65%,A-8=65%. | |
L.C.C work | N/A | |
Grill & Railing work | 50% | |
Inside paint & Polishing work | N/A | |
Switch -Socket fitting work | N/A | |
Outside paint work | N/A | |
Door shutter work | N/A | |
Aluminum/Glazing work | N/A | |
Tiles Pointing work & Marble finishing work | N/A | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | N/A | |
Boundary wall /Ground floor development work | N/A | |
Roof top finishing work | N/A | |
Roof top Gardening work | N/A |
16604