Expected Completion Date
August 2025
Status Updated
May, 2025
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 99% completed | |
Block work | A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%. | |
Electrical conduit work | A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%. | |
Door frame fitting work | A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%. | |
Sanitary & plumbing line work | A-1=87%,A-2=87%A-3=87%, A-4=87%,A-5=87% ,A-6 =87%,A-7=87%,A-8=87%. | |
In side Plastering work | A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%. | |
Electrical cable wiring work | A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%. | |
Wall tiles work | 97% | |
Common sanitary & Plumbing line work | 77% | |
Outside plastering work | 100% | |
Floor tiles/Marble work | A-1=100%,A-2=100%A-3=100%, A-4=100%, A-5=100% ,A-6 =100%,A-7=100%,A-8=100%. | |
L.C.C work | 100% | |
Grill & Railing work | 80% | |
Inside paint & Polishing work | 56% | |
Switch -Socket fitting work | N/A | |
Outside paint work | 30% | |
Door shutter work | 100% | |
Aluminum/Glazing work | 83% | |
Tiles Pointing work & Marble finishing work | N/A | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | 65% | |
Boundary wall /Ground floor development work | 78% | |
Roof top finishing work | N/A | |
Roof top Gardening work | N/A |