The Destination

Dhanmondi, Dhaka

Expected Completion Date

December 2024

Status Updated

November, 2024

SL. No Name of the work Progress details
01 Foundation work 100%
02 Super Structure work G.F- 100%, 1st floor-100%, 2nd floor-100%, 3rd floor 100%,4th-Floor -100%, 5th Floor-100%, 6th floor 100%,7th floor 100%, 8th floor 100%, 9th floor 100%, 10 th floor 100%, 11th floor 100%, Roof top 100%.
03 Block Work  1st Floor100 %, A2-100%, B2-100%, A3-100%, B3-100%, A4-100%, B4-100%, A5-100%, B5-100%, A6-100%, B6-100%, A7-100%, B7-100%, A8-100%, B8-100%, A9-100%, B9-100%, A10-100%, B10-100%, A11-100%, B11-100%,
04 Electrical conducting work G.F- 95%, 1st floor-95%, 2nd floor 100%,3rd Floor-100%, 4th Floor 100%, 5th floor 100%, 6th floor 100%, 7th floor 100%, 8th floor 100%, 9th floor 100%, 10th floor 100%, 11th floor100%, Roof Top 90% completed.
05 Door frame fitting work Flat-B2 100%, A2- 100%, B3-100%, A3-100%, B4-100%, A4-100%, B5-100%, A5-100%, B6-100%, A6-100%, A7-100%, B7-100%, A8-100%, B8-100%, A9-100%, B9-100%, A10-100%B10-100% , A11-100% B11-100% Mezzanine Floor 100%
06 Sanitary & plumbing line work (AC drain water line, verandah vertical line) 2nd floor 100%, 3rd floor 100%, 4th floor100%, 5th floor 100%, 6th floor 100%, 7th floor 100%, 8th floor 100%, 9th floor 100%, 10th Floor 100% ,11thfloor 100% , Roof Top 90%.
07 In side Plastering work G.F 90% ,1st Floor ceiling plaster 100%, 2nd floor 100%, 3rd floor 100%, 4th floor 100%,5th 100% ,6th floor 100%, 7th floor 100%,8th floor 100%, 9th floor 100%,10th floor 100%, 11th floor 100%

Wall plaster: A2-100%, B2-100%, A3-100%, B3-100%, A4-100%, B4-100%, A5-100%, B5-100%, A6-100%, B6-100%, A7-100%, B7-100%, A8-100%, B8-100%, A9-100%, B9-100%, A10-100%, B10-100%, A11-100%, B11-100% , Roof Top 95% .

08 Electrical cable wiring work G.F-90% , 1st Floor-90% , A2-100%,B2-100%,A3-100%,B3-100%, A4-100%, B4-100%, A5-100%, B5-100%, A6-100%, B6-100%, A7-100%,B7-100%, A8-100%, B8-100%,A9-100%, B9-100%,A10-100% , B10-100%,  A11-100%, B11 -100% ,Roof Top 90% .
09 Wall tiles work G.F-95%, 1st Floor-100%, A2-100%, B2-100%, A3-100%, B3-100%, A4-100%, B4-100%, A5-100%, B5-100%, A6 -100%, B6-100%, A7-100%, B7-100%, B8-100%, A8-100%, A9-100%, B9-100%, A10- 100%, B10-100%, A11-100%, B11-100%, Roof Top-80%
     
10 Common sanitary & Plumbing line work G.F-80% ,1st Floor- 90% , Roof Top-90%.
11 Outside plastering work South side 100%, North side 100%, West side 100%
12 Floor tiles/Marble work  G.F- 90%, 1st Floor- 98%, Flat-A2-100%, B2-100% , A3-100% ,  B3 -100%, A5 -100%, B5 -100%, A6-100%, B6 -100%, A7-100%, B7-100%,A8-100% ,B8-100%,B9-100%,  A9-100% A-10 -100% , B-10 -100% , A11-100%, B11-100%, Roof Top 90%
13 L.C.C work 100%
14 Grill & Railing work 100%
15 Inside paint & Polishing work A11-100% ,B11-90% , A9-100%, B9-100%, A8-100%, B8-100%,A7-100%, B7-100%, A6-90%, B6-100%, A5-100%, B5-60%, A4-100%, B4-70%, A3-100%, B3-100%,A2-60%,  B2-100%
16 Switch -Socket fitting work A11-100%,  B11-100%, A10-70%,B10-70%,  A9-100%, B9-100%, A8-100%, B8-100%,A7-100%, B7-100%,A6-100%, B6-100%, A5-100%, B5-100%, A4-100%, B4-100%,A3-100%, B3-100%, A2-100%, B2-100%
17 Outside paint work 70%
18 Door shutter work A11-100%, A9-100%, B9-100% , A8-100%, B8-100%, A7-90%, B7-90%, A6-100%, A4-100%, B4-100%,  A5-100%, B5-90%, A3-100%,  B3-100% ,A2-60%, B2-100%
19 Aluminum/Glazing work A11-100% , A9-100%, B9-100%, A8-100%, B8- 100%, A7-100%, B7-100%, A6-100%, B6-90%, A5-100%, B5-80% ,A4-100%, B4-100%, A3-100%, B3-100%, A2-70%, B2-100%
20 Tiles Pointing work & Marble finishing work A11-100%, A9-100%, B9-100%, A8-100%,A7-100%, B7-100%, B8-100%, A6-100%, B6-90%, A3-100%, B3-100%, B2-100%,
21 Commode – Basin fitting work and C.P fittings work A11-100%,B11-50% A10-40% B10-40% A9-100%, B9- 100%,A8- 100%B8-100%,A7-100%, B7-100%,A6-100% B6-100%, A5-100%, B5-90%, A4-100%B4-100%, A3-100%,B3-100%A2-90%, B2-100%.

 

22 Lift/Generator /Substation /Solar work 90%
23 Boundary wall /Ground floor development work 98%
24 Roof top finishing work 90%
25 Roof top Gardening work 60%