The Laurels

Uttara, Dhaka

Expected Completion Date

February 2026

Status Updated

October, 2025

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 99% completed
  Block work 99% completed
  Electrical  conduit work 99% completed
  Door frame fitting work 100%completed
  Sanitary & plumbing line  work 95%completed
  In side Plastering work 98% completed
  Electrical cable wiring work 92%
  Wall tiles  work 92%
  Common sanitary & Plumbing line work 70%
  Outside plastering work 92%
  Floor tiles/Marble work 90%
  L.C.C work 10%
  Grill & Railing work 85%
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Outside Conmix Plaster 80%
  Aluminum/Glazing work 10%
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work 60%
  Boundary wall /Ground floor development work 05%
  Roof top finishing work 50%
  Roof top Gardening work 30%

 

16604