Expected Completion Date
February 2026
Status Updated
January, 2026
| SL. No | Name of the work | Progress details |
| Foundation work | 100% Completed | |
| Super Structure work | 100% completed | |
| Block work | 100% completed | |
| Electrical conduit work | 99% completed | |
| Door frame fitting work | 100%completed | |
| Sanitary & plumbing line work | 98%completed | |
| In side Plastering work | 98% completed | |
| Electrical cable wiring work | 98% | |
| Wall tiles work | 98% | |
| Common sanitary & Plumbing line work | 95% | |
| Outside plastering work | 98% | |
| Floor tiles/Marble work | 98% | |
| L.C.C work | 100% | |
| Grill & Railing work | 98% | |
| Inside paint & Polishing work | 40% | |
| Switch -Socket fitting work | 10% | |
| Outside paint work | 15% | |
| Outside Conmix Plaster | 98% | |
| Aluminum/Glazing work | 70% | |
| Tiles Pointing work & Marble finishing work | 30% | |
| Commode – Basin fitting work and C.P fittings work | 3% | |
| Lift/Generator /Substation /Solar work | 85% | |
| Boundary wall /Ground floor development work | 70% | |
| Roof top finishing work | 70% | |
| Roof top Gardening work | 70% |