The Laurels

Uttara, Dhaka

Expected Completion Date

February 2026

Status Updated

September, 2025

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 99% completed
  Block work 99% completed
  Electrical  conduit work 99% completed
  Door frame fitting work 100%completed
  Sanitary & plumbing line  work 90%completed
  In side Plastering work 98% completed
  Electrical cable wiring work 90%
  Wall tiles  work 90%
  Common sanitary & Plumbing line work 60%
  Outside plastering work 90%
  Floor tiles/Marble work 85%
  L.C.C work N/A
  Grill & Railing work 80%
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Outside Conmix Plaster 70%
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work 50%
  Boundary wall /Ground floor development work N/A
  Roof top finishing work 40%
  Roof top Gardening work 10%