The Laurels

Uttara, Dhaka

Expected Completion Date

February 2026

Status Updated

March, 2026

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work 100% completed
  Electrical conduit work 99% completed
  Door frame fitting work 100%completed
  Sanitary & plumbing line work 98%completed
  In side Plastering work 98% completed
  Electrical cable wiring work 99%
  Wall tiles work 99%
  Common sanitary & Plumbing line work 99%
  Outside plastering work 100%
  Floor tiles/Marble work 100%
  L.C.C work 100%
  Grill & Railing work 100%
  Inside paint & Polishing work 90%
  Switch -Socket fitting work 90%
  Outside paint work 85%
  Outside Conmix Plaster 99%
  Aluminum/Glazing work 95%
  Tiles Pointing work & Marble finishing work 90%
  Commode – Basin fitting work and C.P fittings work 70%
  Lift/Generator /Substation /Solar work 95%
  Boundary wall /Ground floor development work 100%
  Roof top finishing work 90%
  Roof top Gardening work 90%