Get in touch

img

bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

The Lighthouse

Bashundhara R/A, Dhaka
Expected Completion Date February 2028
Status Updated April, 2026
Back to all projects
The Lighthouse

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work 100% Completed
02 Super Structure work 78% Completed
03 Block work 45% Completed
04 Electrical  conduit  work 40% Completed
05 Door frame fitting work N/A
06 Sanitary & plumbing line  work N/A
07 In side Plastering work N/A
08 Electrical cable wiring work N/A
09 Wall tiles  work N/A
10 Common sanitary & Plumbing line work 2%
11 Outside plastering work N/A
12 Floor tiles/Marble work N/A
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum/Glazing work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work 42% Completed
24 Roof top finishing work N/A
25 Roof top Gardening work N/A

 

Contact Call WhatsApp