The Madison

Uttara, Dhaka

Expected Completion Date

December 2025

Status Updated

January, 2026

SL. No Name of the work Progress details
1 Foundation work 100% Completed.
2 Basement work 100% Completed.
3 Super Structure work 100% completed. (T-1- 11th F roof Completed, T-2 – 11th F roof Completed. T-3 – 10F roof Completed, T-4 – 10F Roof Completed)
4 Block Work 99 % completed.
5 Electrical conduiting work 99% Completed.
6 Door frame fitting work 99% Completed.
7 Sanitary & plumbing line work 942% Completed.
8 Inside Plastering work 95% Completed.
9 Electrical cable wiring work 88% Completed.
10 Wall tiles work 72% completed
11 Common sanitary & Plumbing line work 76% completed
12 Outside plastering work 80% Completed.
13 Floor tiles/Marble work 75% completed.
14 L.C.C work 40% Completed.
15 Grill & Railing work 86% completed.
16 Inside paint & Polishing work 15% completed.
17 Switch -Socket fitting work 5% completed.
18 Outside paint work 6% completed.
19 Door shutter work 12% completed.
20 Aluminum work 18% completed.
21 Tiles Pointing work & Marble finishing work 20% completed.
22 Commode – Basin fitting work and C.P fittings work 15% completed.
23 Lift/Generator /Substation /Solar work 10% completed.
24 Boundary wall /Ground floor development work 88% Completed.
25 Roof top finishing work 35% Completed.
26 Roof top Gardening work G.F Garden work 15% completed.
27 Land escape /Logo work Not Yet Started.

 