The Madison

Uttara, Dhaka

Expected Completion Date

December 2025

Status Updated

March, 2025

SL. No Name of the work Progress details
1 Foundation work 100% Completed.
2 Basement work 100% Completed.
3 Super Structure work 99% completed. (T-1- 11th F roof Completed, T-2 – 11th F roof Completed. T-3 – 10F roof Completed, T-4 – 10F Roof Completed)
4 Block Work 95 % completed.
5 Electrical conduiting work 93% Completed.
6 Door frame fitting work 88% Completed.
7 Sanitary & plumbing line work 79% Completed.
8 Inside Plastering work 85% Completed.
9 Electrical cable wiring work 66% Completed.
10 Wall tiles work 25% completed
11 Common sanitary & Plumbing line work 34% completed
12 Outside plastering work 52% Completed.
13 Floor tiles/Marble work Not Yet Started.
14 L.C.C work Not Yet Started.
15 Grill & Railing work 38% (Window Grill)
16 Inside paint & Polishing work Not Yet Started.
17 Switch -Socket fitting work Not Yet Started.
18 Outside paint work Not Yet Started.
19 Door shutter work Not Yet Started.
20 Aluminum work Not Yet Started.
21 Tiles Pointing work & Marble finishing work Not Yet Started.
22 Commode – Basin fitting work and C.P fittings work Not Yet Started.
23 Lift/Generator /Substation /Solar work Not Yet Started.
24 Boundary wall /Ground floor development work 65% Completed.
25 Roof top finishing work Not Yet Started.
26 Roof top Gardening work G.F Garden work Not Yet Started.
27 Land escape /Logo work Not Yet Started.

 