The Madison

Uttara, Dhaka

Expected Completion Date

July 2026

Status Updated

March, 2026

SL. No Name of the work Progress details
1 Foundation work 100% Completed.
2 Basement work 100% Completed.
3 Super Structure work 100% completed. (T-1- 11th F roof Completed, T-2 – 11th F roof Completed. T-3 – 10F roof Completed, T-4 – 10F Roof Completed)
4 Block Work 99 % completed.
5 Electrical conduiting work 99% Completed.
6 Door frame fitting work 99% Completed.
7 Sanitary & plumbing line work 96% Completed.
8 Inside Plastering work 98% Completed.
9 Electrical cable wiring work 93% Completed.
10 Wall tiles work 94% completed
11 Common sanitary & Plumbing line work 55% completed
12 Outside plastering work 87% Completed.
13 Floor tiles/Marble work 94% completed.
14 L.C.C work 45% Completed.
15 Grill & Railing work 89% completed.
16 Inside paint & Polishing work 44% completed.
17 Switch -Socket fitting work 40% completed.
18 Outside paint work 25% completed.
19 Door shutter work 45% completed.
20 Aluminum work 50% completed.
21 Tiles Pointing work & Marble finishing work 30% completed.
22 Commode – Basin fitting work and C.P fittings work 25% completed.
23 Lift/Generator /Substation /Solar work 40% completed.
24 Boundary wall /Ground floor development work 50% Completed.
25 Roof top finishing work 50% Completed.
26 Roof top Gardening work G.F Garden work 55% completed.
27 Land escape /Logo work Not Yet Started.