Expected Completion Date July 2026
Status Updated March, 2026
Back to all projects
The Madison

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
1 Foundation work 100% Completed.
2 Basement work 100% Completed.
3 Super Structure work 100% completed. (T-1- 11th F roof Completed, T-2 – 11th F roof Completed. T-3 – 10F roof Completed, T-4 – 10F Roof Completed)
4 Block Work 99 % completed.
5 Electrical conduiting work 99% Completed.
6 Door frame fitting work 99% Completed.
7 Sanitary & plumbing line work 96% Completed.
8 Inside Plastering work 98% Completed.
9 Electrical cable wiring work 93% Completed.
10 Wall tiles work 94% completed
11 Common sanitary & Plumbing line work 55% completed
12 Outside plastering work 87% Completed.
13 Floor tiles/Marble work 94% completed.
14 L.C.C work 45% Completed.
15 Grill & Railing work 89% completed.
16 Inside paint & Polishing work 44% completed.
17 Switch -Socket fitting work 40% completed.
18 Outside paint work 25% completed.
19 Door shutter work 45% completed.
20 Aluminum work 50% completed.
21 Tiles Pointing work & Marble finishing work 30% completed.
22 Commode – Basin fitting work and C.P fittings work 25% completed.
23 Lift/Generator /Substation /Solar work 40% completed.
24 Boundary wall /Ground floor development work 50% Completed.
25 Roof top finishing work 50% Completed.
26 Roof top Gardening work G.F Garden work 55% completed.
27 Land escape /Logo work Not Yet Started.