Expected Completion Date
December 2025
Status Updated
May, 2025
SL. No | Name of the work | Progress details |
1 | Foundation work | 100% Completed. |
2 | Basement work | 100% Completed. |
3 | Super Structure work | 100% completed. (T-1- 11th F roof Completed, T-2 – 11th F roof Completed. T-3 – 10F roof Completed, T-4 – 10F Roof Completed) |
4 | Block Work | 97 % completed. |
5 | Electrical conduiting work | 95% Completed. |
6 | Door frame fitting work | 92% Completed. |
7 | Sanitary & plumbing line work | 81% Completed. |
8 | Inside Plastering work | 89% Completed. |
9 | Electrical cable wiring work | 70% Completed. |
10 | Wall tiles work | 27% completed |
11 | Common sanitary & Plumbing line work | 38% completed |
12 | Outside plastering work | 54% Completed. |
13 | Floor tiles/Marble work | 28% completed. |
14 | L.C.C work | Not Yet Started. |
15 | Grill & Railing work | 42% completed. |
16 | Inside paint & Polishing work | Not Yet Started. |
17 | Switch -Socket fitting work | Not Yet Started. |
18 | Outside paint work | Not Yet Started. |
19 | Door shutter work | Not Yet Started. |
20 | Aluminum work | Not Yet Started. |
21 | Tiles Pointing work & Marble finishing work | Not Yet Started. |
22 | Commode – Basin fitting work and C.P fittings work | Not Yet Started. |
23 | Lift/Generator /Substation /Solar work | Not Yet Started. |
24 | Boundary wall /Ground floor development work | 65% Completed. |
25 | Roof top finishing work | Not Yet Started. |
26 | Roof top Gardening work G.F Garden work | Not Yet Started. |
27 | Land escape /Logo work | Not Yet Started. |