The Madison

Uttara, Dhaka

Completion Date

November 2025

Status Updated

March, 2024

SL. No Name of the work Progress details
1 Foundation work 100% Completed.
2 Basement work 100% Completed.
3 Super Structure work 76% completed. (T-1- 5F roof Completed, T-2 – 7F roof Completed. T-3 – 10F roof Completed, T-4 – 9F Roof Completed)
4 Block Work 50 % completed.
5 Electrical conduiting work 48% Completed.
6 Door frame fitting work 40% Completed.
7 Sanitary & plumbing line work 40% Completed.
8 Inside Plastering work 40% Completed.
9 Electrical cable wiring work 10% Completed.
10 Wall tiles work nill
11 Common sanitary & Plumbing line work nill
12 Outside plastering work 10% Completed.
13 Floor tiles/Marble work nill
14 L.C.C work nill
15 Grill & Railing work nill
16 Inside paint & Polishing work nill
17 Switch -Socket fitting work nill
18 Outside paint work nill
19 Door shutter work nill
20 Aluminum work nill
21 Tiles Pointing work & Marble finishing work nill
22 Commode – Basin fitting work and C.P fittings work nill
23 Lift/Generator /Substation /Solar work nill
24 Boundary wall /Ground floor development work 65% Completed.
25 Roof top finishing work nill
26 Roof top Gardening work G.F Garden work nill
27 Land escape /Logo work nill

16604