Expected Completion Date
December 2025
Status Updated
September, 2025
| SL. No | Name of the work | Progress details |
| 1 | Foundation work | 100% completed |
| 2 | Basement work | 100 % completed |
| 3 | Super Structure work | 100 % completed (Tower-1, Tower-2, Tower-3) |
| 4 | Block Work | Tower -01, All apartments of tower: 1 (A1 to A8) total 08 apartments nos are 100% completed.
Tower -02, All apartments of tower: 2 total 55 nos apartments are 100% completed.
Tower -03, All apartments of tower: 3 total 51 nos apartments are 100% completed
|
| 5 | Electrical conduiting work | Over all apartments 100 % completed. Common Area 95% Completed |
| 6 | Door frame fitting work | Over all 100 % completed |
| 7 | Sanitary & plumbing line work | Internal wiring 100% completed. |
| 8 | Inside Plastering work | Overall 100% |
| 9 | Electrical cable wiring work | 100 % apartments completed. |
| 10 | Wall tiles work | Wall tile: Tower -1, 100% T-2: 100%. T-3: 98% complete. |
| 11 | Common sanitary & Plumbing line work | Overall,70% completed. |
| 12 | Outside plastering work | Tower -1 completed. Tower-2= 100% T-3 =
100% |
| 13 | Floor tiles/Marble work | Tower- 1, 100 % Complete. Tower-2, = 100% complete. Tower: 3 51 apartments completed. |
| 14 | L.C.C work | Tower- 1 Completed, Tower -2, 100% Completed, Tower -3, 100% Completed. |
| 15 | Grill & Railing work | Apartments of Tower- 1 = 100 % completed, Tower-2 = 100% completed, Tower-3 = 98% completed. |
| 16 | Inside paint & Polishing work | Tower-1, 1st and 2nd code work =100% complete. Tower-2, 1st code 11th floor completed. Tower-3, 1st code 10 apartment completed. |
| 17 | Switch -Socket fitting work | Tower-1 completed. |
| 18 | Outside paint work | Tower-1 Putty Work Completed. |
| 19 | Door shutter work | Tower -1 completed. tower: 2, 10 apartments completed. |
| 20 | Aluminum work | Tower-1: 100 % completed, Tower: 2, 90% completed. Tower: 3, 40% completed. |
| 21 | Tiles Pointing work & Marble finishing work | Tower-1: 30 % completed, |
| 22 | Commode – Basin fitting work and C.P fittings work | NYS |
| 23 | Lift/Generator /Substation /Solar work | NYS |
| 24 | Boundary wall /Ground floor development work | 80 % completed (Boundary wall 90% completed, Plaster due.) |
| 25 | Roof top finishing work | Tower: 1 tile work: 95% competed. Tower-2: 95 % completed. Tower: 3, 70% completed. |
| 26 | Roof top Gardening work G.F Garden work | NYS |
| 27 | Land escape /Logo work | NYS |