The Millennial

Bhatara, Dhaka

Expected Completion Date

December 2025

Status Updated

July, 2025

SL. No Name of the work Progress details
1 Foundation work 100% completed
2 Basement work 100 % completed
3 Super Structure work 100 % completed (Tower-1, Tower-2, Tower-3)
4 Block Work Tower -01, All apartments of tower: 1 (A1 to A8) total 08 apartments nos are 100% completed.

Tower -02, All apartments of tower: 2 total 55 nos apartments are 100% completed.

 

Tower -03, All apartments of tower: 3 total 51 nos apartments are 100% completed

 

5 Electrical conduiting work Over all apartments 100 % completed. Common Area 90 % Completed
6 Door frame fitting work Over all 100 % completed
7 Sanitary & plumbing line work Internal wiring 100% completed.
8 Inside Plastering work Overall 100%
9 Electrical cable wiring work 100 % apartments completed.
10 Wall tiles work Wall tile: Tower -1, 100% T-2: 100%. T-3: 98% complete.
11 Common sanitary & Plumbing line work Overall, 50% completed.
12 Outside plastering work Tower -1 completed. Tower-2= 100% T-3 =

100%

13 Floor tiles/Marble work Tower- 1, 100 % Complete. Tower-2, = 100% complete. Tower: 3 50 apartments completed.
14 L.C.C work Tower- 1 Completed, Tower -2, 100% Completed, Tower -3, 100% Completed.
15 Grill & Railing work Apartments of Tower- 1 = 100 % completed, Tower-2 = 100% completed, Tower-3 = 98% completed.
16 Inside paint & Polishing work Tower-1, 1st and 2nd code work =100% complete. Tower-2, 1st code 11th floor completed. Tower-3, 1st code 10 apartment completed.
17 Switch -Socket fitting work Tower-1 completed.
18 Outside paint work Tower-1 Putty Work Completed.
19 Door shutter work Tower -1 completed. tower: 2, 10 apartments completed.
20 Aluminum work Tower-1: 100 % completed, Tower: 2, 80% completed.
21 Tiles Pointing work & Marble finishing work NYS
22 Commode – Basin fitting work and C.P fittings work NYS
23 Lift/Generator /Substation /Solar work NYS
24 Boundary wall /Ground floor development work 60 % completed (Boundary wall 90% completed, Plaster due.)
25 Roof top finishing work Tower: 1 tile work: 95% competed. Tower-2:  80 % completed. Tower: 3, 50% completed.
26 Roof top Gardening work G.F Garden work NYS
27 Land escape /Logo work NYS