Expected Completion Date
September 2025
Status Updated
February, 2025
SL. No | Name of the work | Location | Progress details | Remarks |
01 | Foundation work | 100% completed. | ||
02 | Super Structure work | 100% | ||
03 | Block Work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete |
|
04 | Electrical conduiting work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete
|
|
05 | Door frame fitting work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete |
|
06 | Sanitary & plumbing line work | conseil duct-1
conseil duct-2
|
100% Complete
100% Complete
|
|
07 | In side Plastering work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete
|
|
08 | Electrical cable wiring work |
Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete
|
|
09 | Wall tiles work | Apartment =A9
Apartment =A8 Apartment =A7 Apartment =A4
|
60% Complete
60% Complete 60% Complete 60% Complete |
|
10 | Common sanitary & Plumbing line work | |||
11 | Outside plastering work | West side
North side East side |
full complete
full complete full complete
|
|
12 | Floor tiles/Marble work | Apartment =A9
Apartment =A8 Apartment =A7 Apartment =A4
|
80% Complete
80% Complete 80% Complete 80% Complete |
|
13 | L.C.C work | |||
14 | Grill & Railing work | |||
15 | Inside paint & Polishing work | |||
16 | Switch -Socket fitting work | |||
17 | Outside paint work | |||
18 | Door shutter work | |||
19 | Aluminum work | |||
20 | Tiles Pointing work & Marble finishing work | |||
21 | Commode – Basin fitting work and C.P fittings work | |||
22 | Lift/Generator /Substation /Solar work | |||
23 | Boundary wall /Ground floor development work | Footing casting
Gard room work |
30% complete
On going |
|
24 | Roof top finishing work | Plaster work | 80% complete | |
25 | Roof top Gardening work G.F Garden work |
16604