The Mulberry

Bashundhara R/A, Dhaka

Expected Completion Date

September 2025

Status Updated

November, 2024

SL. No Name of the work Progress details Remarks
01 Foundation work 100% Complete  
02 Super Structure work 10th floor Slab  Casting Work Complete  
03 Block Work A1 Block Work up to Full H Complete

A2 Block Work up to Full Hight complete

A3 Block Work up to Full Hight complete

A4 Block Work up to Full Hight complete

A5 Block Work up to Full Hight Complete

A6 Block Work up to Full Hight Complete

A7 Block Work up to Full Hight Complete

A8 Block Work up to 90% Complete

A9 Block Work up to 40 % Complete

 

 
04 Electrical conduting work A1 Conduit Work Complete

A2 Conduit Work Complete

A3 Conduit Work Complete

A4 Conduit Work Complete

A5 Conduit Work Complete

A5 Conduit Work Complete

A6 Conduit Work Complete

A7 Conduit Work Complete

A8 Conduit Work Complete

A8 Conduit Work Complete 70%

 
05 Door frame fitting work A2 Door frame fitting Work 70%Complete

A3 Door frame fitting Work100% Complete

A4 Door frame fitting Work 100% Complete

A5 Door frame fitting Work 100% Complete

A6 Door frame fitting Work 100% Complete

A7 Door frame fitting Work 100% Complete

 

 
06 Sanitary & plumbing line  work Duckting work 60%  work done  
07 In side Plastering work A1 Celling Plaster Complete

A2 Celling Plaster Complete

A3 Celling & Inner wall Plaster Complete

A4 Celling Plaster Complete

A5 Celling Plaster Complete

A6 Celling Plaster Complete

A7 Celling Plaster Complete

A8 Celling Plaster Complete

Comon Space ( Stair Celing All floor) done

 
08 Electrical cable wiring work N/A  
09 Wall tiles  work N/A  
10 Common sanitary & Plumbing line work N/A  
11 Outside plastering work N/A  
12 Floor tiles/Marble work N/A  
13 L.C.C work N/A  
14 Grill & Railing work N/A  
15 Inside paint & Polishing work N/A  
16 Switch -Socket fitting work N/A  
17 Outside paint work N/A  
18 Door shutter work N/A  
19 Aluminum work N/A  
20 Tiles Pointing work & Marble finishing work N/A  
21 Commode – Basin fitting work and C.P fittings work N/A  
22 Lift/Generator /Substation /Solar work N/A  
23 Boundary wall /Ground floor development work N/A  
24 Roof top finishing work N/A  
25 Roof top Gardening work G.F Garden work N/A  

16604