Expected Completion Date
September 2025
Status Updated
December, 2024
SL. No | Name of the work | Progress details | Remarks |
01 | Foundation work | 100% Complete | |
02 | Super Structure work | 10th floor Slab Casting Work Complete | |
03 | Block Work | A1 Block Work up to 80% complete
A2 Block Work up to Full Hight complete A3 Block Work up to Full Hight complete A4 Block Work up to Full Hight complete A5 Block Work up to Full Hight Complete A6 Block Work up to Full Hight Complete A7 Block Work up to Full Hight Complete A8 Block Work up to Full Hight Complete A9 Block Work up to Full Hight Complete
|
|
04 | Electrical conduting work | A1 Conduit Work Complete
A2 Conduit Work Complete A3 Conduit Work Complete A4 Conduit Work Complete A5 Conduit Work Complete A5 Conduit Work Complete A6 Conduit Work Complete A7 Conduit Work Complete A8 Conduit Work Complete A9 Conduit Work Complete
|
|
05 | Door frame fitting work | A2 Door frame fitting Work 70%Complete
A3 Door frame fitting Work100% Complete A4 Door frame fitting Work 100% Complete A5 Door frame fitting Work 100% Complete A6 Door frame fitting Work 100% Complete A7 Door frame fitting Work 100% Complete A7 Door frame fitting Work 100% Complete
|
|
06 | Sanitary & plumbing line work | Duckting work 60% work done | |
07 | In side Plastering work | A1 Celling Plaster Complete
A2 Celling Plaster Complete A3 Celling & Inner wall Plaster Complete A4 Celling & Inner wall Plaster Complete A5 Celling& Inner wall Plaster Complete A6 Celling & Inner wall Plaster Complete A7 Celling & Inner wall Plaster Complete A8 Celling & Inner wall Plaster Complete
Comon Space ( Stair Ceiling All floor) done |
|
08 | Electrical cable wiring work | N/A | |
09 | Wall tiles work | N/A | |
10 | Common sanitary & Plumbing line work | N/A | |
11 | Outside plastering work | West side full complete
North side 40% complete |
|
12 | Floor tiles/Marble work | N/A | |
13 | L.C.C work | N/A | |
14 | Grill & Railing work | N/A | |
15 | Inside paint & Polishing work | N/A | |
16 | Switch -Socket fitting work | N/A | |
17 | Outside paint work | N/A | |
18 | Door shutter work | N/A | |
19 | Aluminum work | N/A | |
20 | Tiles Pointing work & Marble finishing work | N/A | |
21 | Commode – Basin fitting work and C.P fittings work | N/A | |
22 | Lift/Generator /Substation /Solar work | N/A | |
23 | Boundary wall /Ground floor development work | N/A | |
24 | Roof top finishing work | N/A | |
25 | Roof top Gardening work G.F Garden work | N/A |
16604