The Mulberry

Bashundhara R/A, Dhaka

Completion Date

May 2025

Status Updated

March, 2024

SL. No Name of the work Progress details
01 Foundation work 100% Complete
02 Super Structure work 6th floor roof slab & beam shuttering work Ongoing
03 Block Work A1 -60% Complete

A2- 35% Complete

04 Electrical conduting work 1st & 2nd floor done
05 Door frame fitting work N/A
06 Sanitary & plumbing line  work N/A
07 In side Plastering work A1 Celling Plaster Complete

A2 Celling Plaster Complete

A3 Celling Plaster Complete

A4 Celling Plaster Complete

08 Electrical cable wiring work  
09 Wall tiles  work  
10 Common sanitary & Plumbing line work  
11 Outside plastering work  
12 Floor tiles/Marble work  
13 L.C.C work  
14 Grill & Railing work  
15 Inside paint & Polishing work  
16 Switch -Socket fitting work  
17 Outside paint work  
18 Door shutter work  
19 Aluminum work  
20 Tiles Pointing work & Marble finishing work  
21 Commode – Basin fitting work and C.P fittings work  
22 Lift/Generator /Substation /Solar work  
23 Boundary wall /Ground floor development work  
24 Roof top finishing work  
25 Roof top Gardening work G.F Garden work  