The Mulberry

Bashundhara R/A, Dhaka

Completion Date

September 2025

Status Updated

September, 2024

SL. No Name of the work Progress details (september) Progress details ()
01 Foundation work 100% Complete  
02 Super Structure work 10th floor Slab  Casting Work Complete  
03 Block Work A1 Block Work 100% Complete

A2 Block Work 100% complete

A3 Block Work 100% complete

A4 Block Work 100% complete

A5 Block Work 100% Complete

A6 Block Work 100% Complete

A7 Block Work up to 7’ Hight Complete

 
04 Electrical conduting work A1 Conduit Work Complete

A2 Conduit Work Complete

A3 Conduit Work Complete

A4 Conduit Work Complete

A5 Conduit Work Complete

A5 Conduit Work Complete

A6 Conduit Work Complete

A7 Conduit Work Complete

 

 
05 Door frame fitting work A2 Door frame fitting Work 70%Complete

A3 Door frame fitting Work 70% Complete

A4 Door frame fitting Work 70% Complete

A5 Door frame fitting Work 70% Complete

 

 
06 Sanitary & plumbing line  work N/A  
07 In side Plastering work A1 Celling Plaster Complete

A2 Celling Plaster Complete

A3 Celling Plaster Complete

A4 Celling Plaster Complete

A5 Celling Plaster Complete

A6 Celling Plaster Complete

A7 Celling Plaster Complete

A8Celling Plaster Complete

Comon Space ( Stair Celing Plaster 2nd to 5th floor)

 
08 Electrical cable wiring work    
09 Wall tiles  work    
10 Common sanitary & Plumbing line work    
11 Outside plastering work    
12 Floor tiles/Marble work    
13 L.C.C work    
14 Grill & Railing work    
15 Inside paint & Polishing work    
16 Switch -Socket fitting work    
17 Outside paint work    
18 Door shutter work    
19 Aluminum work    
20 Tiles Pointing work & Marble finishing work    
21 Commode – Basin fitting work and C.P fittings work    
22 Lift/Generator /Substation /Solar work    
23 Boundary wall /Ground floor development work    
24 Roof top finishing work    
25 Roof top Gardening work G.F Garden work    