Completion Date
May 2025
Status Updated
March, 2024
SL. No | Name of the work | Progress details |
01 | Foundation work | 100% Complete |
02 | Super Structure work | 6th floor roof slab & beam shuttering work Ongoing |
03 | Block Work | A1 -60% Complete
A2- 35% Complete |
04 | Electrical conduting work | 1st & 2nd floor done |
05 | Door frame fitting work | N/A |
06 | Sanitary & plumbing line work | N/A |
07 | In side Plastering work | A1 Celling Plaster Complete
A2 Celling Plaster Complete A3 Celling Plaster Complete A4 Celling Plaster Complete |
08 | Electrical cable wiring work | |
09 | Wall tiles work | |
10 | Common sanitary & Plumbing line work | |
11 | Outside plastering work | |
12 | Floor tiles/Marble work | |
13 | L.C.C work | |
14 | Grill & Railing work | |
15 | Inside paint & Polishing work | |
16 | Switch -Socket fitting work | |
17 | Outside paint work | |
18 | Door shutter work | |
19 | Aluminum work | |
20 | Tiles Pointing work & Marble finishing work | |
21 | Commode – Basin fitting work and C.P fittings work | |
22 | Lift/Generator /Substation /Solar work | |
23 | Boundary wall /Ground floor development work | |
24 | Roof top finishing work | |
25 | Roof top Gardening work G.F Garden work |