Completion Date
September 2025
Status Updated
September, 2024
SL. No | Name of the work | Progress details (september) | Progress details () |
01 | Foundation work | 100% Complete | |
02 | Super Structure work | 10th floor Slab Casting Work Complete | |
03 | Block Work | A1 Block Work 100% Complete
A2 Block Work 100% complete A3 Block Work 100% complete A4 Block Work 100% complete A5 Block Work 100% Complete A6 Block Work 100% Complete A7 Block Work up to 7’ Hight Complete |
|
04 | Electrical conduting work | A1 Conduit Work Complete
A2 Conduit Work Complete A3 Conduit Work Complete A4 Conduit Work Complete A5 Conduit Work Complete A5 Conduit Work Complete A6 Conduit Work Complete A7 Conduit Work Complete
|
|
05 | Door frame fitting work | A2 Door frame fitting Work 70%Complete
A3 Door frame fitting Work 70% Complete A4 Door frame fitting Work 70% Complete A5 Door frame fitting Work 70% Complete
|
|
06 | Sanitary & plumbing line work | N/A | |
07 | In side Plastering work | A1 Celling Plaster Complete
A2 Celling Plaster Complete A3 Celling Plaster Complete A4 Celling Plaster Complete A5 Celling Plaster Complete A6 Celling Plaster Complete A7 Celling Plaster Complete A8Celling Plaster Complete Comon Space ( Stair Celing Plaster 2nd to 5th floor) |
|
08 | Electrical cable wiring work | ||
09 | Wall tiles work | ||
10 | Common sanitary & Plumbing line work | ||
11 | Outside plastering work | ||
12 | Floor tiles/Marble work | ||
13 | L.C.C work | ||
14 | Grill & Railing work | ||
15 | Inside paint & Polishing work | ||
16 | Switch -Socket fitting work | ||
17 | Outside paint work | ||
18 | Door shutter work | ||
19 | Aluminum work | ||
20 | Tiles Pointing work & Marble finishing work | ||
21 | Commode – Basin fitting work and C.P fittings work | ||
22 | Lift/Generator /Substation /Solar work | ||
23 | Boundary wall /Ground floor development work | ||
24 | Roof top finishing work | ||
25 | Roof top Gardening work G.F Garden work |