The Palms

Aftabnagar, Dhaka

Completion Date

September 2024

Status Updated

March, 2024

SL. No Name of the work Location Progress details (November)
01 Foundation work   100% completed.
02 Super Structure work   100%
03 Block Work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

04 Electrical conduiting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

 

05 Door frame fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

06 Sanitary & plumbing line work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

 

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

07 In side Plastering work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

 

08 Electrical cable wiring work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

 

 90% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

90% Complete d

 

09 Wall tiles work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

85% Completed

85% Completed

85% Completed

85% Completed

85% Completed

85% Completed

85% Completed

85% Completed

70% Completed

 

10 Common sanitary & Plumbing line work   30%Completed

 

11 Outside plastering work   85% Completed
12 Floor tiles/Marble work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

75% Completed

75% Completed

75Completed

75% Completed

75% Completed

75% Completed

75% Completed

75% Completed

50% Completed

 

13 L.C.C work    
14 Grill & Railing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

10% Completed

20%  Completed

20% Completed

20% Completed

20%  Completed

40% Completed

40% Completed

40% Completed

40% Completed

 

 

15 Inside paint & Polishing work    
16 Switch -Socket fitting work    
17 Outside paint work    
18 Door shutter work    
19 Aluminum work    
20 Tiles Pointing work & Marble finishing work    
21 Commode – Basin fitting work and C.P fittings work    
22 Lift/Generator /Substation /Solar work    
23 Boundary wall /Ground floor development work   50% Completed
24 Roof top finishing work   50%Completed
25 Roof top Gardening work G.F Garden work    