The Peak

ECB Circle, Dhaka

Completion Date

August 2027

Status Updated

September, 2024

SL. No Name of the work Progress details
1 Foundation work 100% Completed
2 Super Structure work 26% Completed
3 Block work N/A
4 Electrical conduit work 15% Completed
5 Door frame fitting work N/A
6 Sanitary & plumbing line work 3%Completed
7 In side Plastering work 5% Complete
8 Electrical cable wiring work 12% Complete
9 Wall tiles work N/A
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work N/A
12 Floor tiles/Marble work N/A
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum/Glazing work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work N/A
25 Roof top Gardening work N/A