The Peak

ECB Circle, Dhaka

Completion Date

July 2027

Status Updated

April, 2024

SL. No Name of the work Progress details
Foundation work 100% Completed
Super Structure work 20% completed
Block work N/A
Electrical conduit work N/A
Door frame fitting work N/A
Sanitary & plumbing line work N/A
In side Plastering work N/A
Electrical cable wiring work N/A
Wall tiles work N/A
Common sanitary & Plumbing line work N/A
Outside plastering work N/A
Floor tiles/Marble work N/A
L.C.C work N/A
Grill & Railing work N/A
Inside paint & Polishing work N/A
Switch -Socket fitting work N/A
Outside paint work N/A
Door shutter work N/A
Aluminum/Glazing work N/A
Tiles Pointing work & Marble finishing work N/A
Commode – Basin fitting work and C.P fittings work N/A
Lift/Generator /Substation /Solar work N/A
Boundary wall /Ground floor development work N/A
Roof top finishing work N/A
Roof top Gardening work N/A