The Retreat

Block E, Bashundhara R/A

Expected Completion Date

July 2025

Status Updated

May, 2025

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work 100% Complete
  Electrical  conduit work 100% Complete
  Door frame fitting work 100% Complete
  Sanitary & plumbing line  work 99%  Complete
  In side Plastering work 99% Complete
  Electrical cable wiring work 99% Complete
  Wall tiles  work 98% Complete
  Common sanitary & Plumbing line work 98% Complete
  Outside plastering work 98% Complete
  Floor tiles/Marble work 99% Complete
  L.C.C work 100% Complete
  Grill & Railing work 97% Complete
  Inside paint & Polishing work 90%
  Switch -Socket fitting work 95%
  Outside paint work 70%
  Door shutter work 98% Complete
  Aluminum/Glazing work 90% Complete
  Tiles Pointing work & Marble finishing work 90%
  Commode – Basin fitting work and C.P fittings work 90%

 

 

 

  Lift/Generator /Substation /Solar work 99%
  Boundary wall /Ground floor development work 90%
  Roof top finishing work 95%
  Roof top Gardening work 85%