The Retreat

Bashundhara R/A, Dhaka

Expected Completion Date

March 2025

Status Updated

February, 2025

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work 100% Complete
  Electrical  conduit work  99% Complete
  Door frame fitting work 100% Complete
  Sanitary & plumbing line  work 97%  Complete
  In side Plastering work 99% Complete
  Electrical cable wiring work 95% Complete
  Wall tiles  work 96% Complete
  Common sanitary & Plumbing line work 90% Complete
  Outside plastering work 98% Complete
  Floor tiles/Marble work 95% Complete
  L.C.C work 100% Complete
  Grill & Railing work 95% Complete
  Inside paint & Polishing work 80%
  Switch -Socket fitting work 20%
  Outside paint work 30%
  Door shutter work 90% Complete
  Aluminum/Glazing work 40% Complete
  Tiles Pointing work & Marble finishing work 10%
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work 60%
  Boundary wall /Ground floor development work 70%
  Roof top finishing work 85%
  Roof top Gardening work N/A

16604