Expected Completion Date
March 2025
Status Updated
November, 2024
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 100% completed | |
Block work | 100% Complete | |
Electrical conduit work | 99% Complete | |
Door frame fitting work | 100% Complete | |
Sanitary & plumbing line work | 95% Complete | |
In side Plastering work | 99% Complete | |
Electrical cable wiring work | 90% Complete | |
Wall tiles work | 92% Complete | |
Common sanitary & Plumbing line work | 85% Complete | |
Outside plastering work | 98% Complete | |
Floor tiles/Marble work | 91% Complete | |
L.C.C work | 100% Complete | |
Grill & Railing work | 90% Complete | |
Inside paint & Polishing work | 40% | |
Switch -Socket fitting work | N/A | |
Outside paint work | N/A | |
Door shutter work | 30% Complete | |
Aluminum/Glazing work | 25% Complete | |
Tiles Pointing work & Marble finishing work | N/A | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | 40% | |
Boundary wall /Ground floor development work | 40% | |
Roof top finishing work | 60% | |
Roof top Gardening work | N/A |