Expected Completion Date
August 2025
Status Updated
August, 2025
| SL. No | Name of the work | Progress details |
| Foundation work | 100% Completed | |
| Super Structure work | 100% completed | |
| Block work | 100% Complete | |
| Electrical conduit work | 100% Complete | |
| Door frame fitting work | 100% Complete | |
| Sanitary & plumbing line work | 100% Complete | |
| In side Plastering work | 100% Complete | |
| Electrical cable wiring work | 100% Complete | |
| Wall tiles work | 100% Complete | |
| Common sanitary & Plumbing line work | 100% Complete | |
| Outside plastering work | 100% Complete | |
| Floor tiles/Marble work | 100% Complete | |
| L.C.C work | 100% Complete | |
| Grill & Railing work | 100% Complete | |
| Inside paint & Polishing work | 99% | |
| Switch -Socket fitting work | 100% | |
| Outside paint work | 100% | |
| Door shutter work | 100% Complete | |
| Aluminum/Glazing work | 100% Complete | |
| Tiles Pointing work & Marble finishing work | 100% | |
| Commode – Basin fitting work and C.P fittings work | 100%
|
|
| Lift/Generator /Substation /Solar work | 100% | |
| Boundary wall /Ground floor development work | 100% | |
| Roof top finishing work | 100% | |
| Roof top Gardening work | 99% |
16604