The Retreat

Bashundhara R/A, Dhaka
Expected Completion Date August 2025
Status Updated August, 2025
Back to all projects
The Retreat

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work 100% Complete
  Electrical  conduit work 100% Complete
  Door frame fitting work 100% Complete
  Sanitary & plumbing line  work 100%  Complete
  In side Plastering work 100% Complete
  Electrical cable wiring work 100% Complete
  Wall tiles  work 100% Complete
  Common sanitary & Plumbing line work 100% Complete
  Outside plastering work 100% Complete
  Floor tiles/Marble work 100% Complete
  L.C.C work 100% Complete
  Grill & Railing work 100% Complete
  Inside paint & Polishing work 99%
  Switch -Socket fitting work 100%
  Outside paint work 100%
  Door shutter work 100% Complete
  Aluminum/Glazing work 100% Complete
  Tiles Pointing work & Marble finishing work 100%
  Commode – Basin fitting work and C.P fittings work 100%

 

 

 

  Lift/Generator /Substation /Solar work 100%
  Boundary wall /Ground floor development work 100%
  Roof top finishing work 100%
  Roof top Gardening work 99%