The Santorini

Bashundhara R/A, Dhaka

Expected Completion Date

July 2025

Status Updated

February, 2025

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%, A-8=100%, B-8=100%, A-9=100%, B-9=100%
  Electrical  conduit work A-2=90%, B-2=90%, A-3=90%, B-3=90%,    A-4=90%, B-4=90%, A-5=90%, B-5=90%, A-6=90%, B-6=90%, A-7=90%, B-7=90%,

A-8=90%, B-8=90%, A-9=90%, B-9=90%,

  Door frame fitting work A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,

A-8=100%, B-8=100%, A-9=100%, B-9=100%,

  Sanitary & plumbing line  work A-2=85%, B-2=85%, A-3=85%, B-3=85%,    A-4=85%, B-4=85%, A-5=85%, B-5=85%, A-6=85%, B-6=85%, A-7=85%, B-7=85%, A-8=85%, B-8=85%, A-9=85%, B-9=85%
  In side Plastering work A-2=99%, B-2=99% A-3=99%, B-3=99%,    A-4=99%, B-4=99%, A-5=99%, B-5=99%, A-6=99%, B-6=99%, A-7=99%, B-7=99%,

A-8=99%, B-8=99%, A-9=99%, B-9=99%,

  Electrical cable wiring work A-2=90%, B-2=90%, A-3=90%, B-3=90%,    A-4=90%, B-4=90%, A-5=90%, B-5=90%, A-6=90%, B-6=90%, A-7=90%, B-7=90%, A-8=90%, B-8=90%, A-9=90%, B-9=90%
  Wall tiles  work A-2=50%, B-2=50%, A-3=70%, B-3=50%,    A-4=67%, B-4=67%, A-5=67%, B-5=67%, A-6=67%, B-6=67%, A-7=67%, B-7=67%, A-8=67%, B-8=67%, A-9=67%, B-9=67%
  Common sanitary & Plumbing line work 30%
  Outside plastering work 01. North side = 100%,

02. South side = 100%,

03. East Side = 100%,

04. West Side = 100%.

  Floor tiles/Marble work 70%
  L.C.C work 20%
  Grill & Railing work 65%
  Inside paint & Polishing work 1%
  Switch -Socket fitting work N/A
  Aluminum/Glazing work N/A
  Outside paint work N/A
  Door shutter work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work 25%
  Roof top finishing work 35%
  Roof top Gardening work 80%

 