The Santorini

Block K, Bashundhara R/A

Expected Completion Date

September 2025

Status Updated

August, 2025

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%, A-8=100%, B-8=100%, A-9=100%, B-9=100%
  Electrical  conduit work A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,

A-8=100%, B-8=100%, A-9=100%, B-9=100%,

  Door frame fitting work A-2=100%, B-2=100%, A-3=100%, B-3=100%,A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,

A-8=100%, B-8=100%, A-9=100%, B-9=100%,

  Sanitary & plumbing line  work A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,

A-8=100%, B-8=100%, A-9=100%, B-9=100%,

  In side Plastering work A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,

A-8=100%, B-8=100%, A-9=100%, B-9=100%,

  Electrical cable wiring work A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,

A-8=100%, B-8=100%, A-9=100%, B-9=100%,

  Wall tiles  work A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,

A-8=100%, B-8=100%, A-9=100%, B-9=100%,

  Common sanitary & Plumbing line work 80%
  Outside plastering work 01. North side = 100%,

02. South side = 100%,

03. East Side = 100%,

04. West Side = 100%.

  Floor tiles/Marble work 100%
  L.C.C work 100%
  Grill & Railing work 100%
  Inside paint & Polishing work 60%
  Switch -Socket fitting work 85%
  Aluminum/Glazing work 60%
  Outside paint work 45%
  Door shutter work 100%
  Tiles Pointing work & Marble finishing work 60%
  Commode – Basin fitting work and C.P fittings work 60%
  Lift/Generator /Substation /Solar work 90%
  Boundary wall /Ground floor development work 70%
  Roof top finishing work 80%
  Roof top Gardening work 50%