Expected Completion Date
September 2025
Status Updated
August, 2025
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 100% completed | |
Block work | A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%, A-8=100%, B-8=100%, A-9=100%, B-9=100% | |
Electrical conduit work | A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,
A-8=100%, B-8=100%, A-9=100%, B-9=100%, |
|
Door frame fitting work | A-2=100%, B-2=100%, A-3=100%, B-3=100%,A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,
A-8=100%, B-8=100%, A-9=100%, B-9=100%, |
|
Sanitary & plumbing line work | A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,
A-8=100%, B-8=100%, A-9=100%, B-9=100%, |
|
In side Plastering work | A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,
A-8=100%, B-8=100%, A-9=100%, B-9=100%, |
|
Electrical cable wiring work | A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,
A-8=100%, B-8=100%, A-9=100%, B-9=100%, |
|
Wall tiles work | A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,
A-8=100%, B-8=100%, A-9=100%, B-9=100%, |
|
Common sanitary & Plumbing line work | 80% | |
Outside plastering work | 01. North side = 100%,
02. South side = 100%, 03. East Side = 100%, 04. West Side = 100%. |
|
Floor tiles/Marble work | 100% | |
L.C.C work | 100% | |
Grill & Railing work | 100% | |
Inside paint & Polishing work | 60% | |
Switch -Socket fitting work | 85% | |
Aluminum/Glazing work | 60% | |
Outside paint work | 45% | |
Door shutter work | 100% | |
Tiles Pointing work & Marble finishing work | 60% | |
Commode – Basin fitting work and C.P fittings work | 60% | |
Lift/Generator /Substation /Solar work | 90% | |
Boundary wall /Ground floor development work | 70% | |
Roof top finishing work | 80% | |
Roof top Gardening work | 50% |