Expected Completion Date
September 2025
Status Updated
September, 2025
| SL. No | Name of the work | Progress details |
| Foundation work | 100% Completed | |
| Super Structure work | 100% completed | |
| Block work | A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%, A-8=100%, B-8=100%, A-9=100%, B-9=100% | |
| Electrical conduit work | A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,
A-8=100%, B-8=100%, A-9=100%, B-9=100%, |
|
| Door frame fitting work | A-2=100%, B-2=100%, A-3=100%, B-3=100%,A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,
A-8=100%, B-8=100%, A-9=100%, B-9=100%, |
|
| Sanitary & plumbing line work | A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,
A-8=100%, B-8=100%, A-9=100%, B-9=100%, |
|
| In side Plastering work | A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,
A-8=100%, B-8=100%, A-9=100%, B-9=100%, |
|
| Electrical cable wiring work | A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,
A-8=100%, B-8=100%, A-9=100%, B-9=100%, |
|
| Wall tiles work | A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,
A-8=100%, B-8=100%, A-9=100%, B-9=100%, |
|
| Common sanitary & Plumbing line work | 90% | |
| Outside plastering work | 01. North side = 100%,
02. South side = 100%, 03. East Side = 100%, 04. West Side = 100%. |
|
| Floor tiles/Marble work Flat | 100% | |
| L.C.C work | 100% | |
| Grill & Railing work | 100% | |
| Inside paint & Polishing work | 100% | |
| Switch -Socket fitting work | 95% | |
| Aluminum/Glazing work | 95% | |
| Outside paint work | 60% | |
| Door shutter work | 100% | |
| Tiles Pointing work & Marble finishing work | 40% | |
| Commode – Basin fitting work and C.P fittings work | 60% | |
| Lift/Generator /Substation /Solar work | 100% | |
| Boundary wall /Ground floor development work | 80% | |
| Roof top finishing work | 90% | |
| Roof top Gardening work | 60% |