The Santorini

Bashundhara R/A, Dhaka

Expected Completion Date

July 2025

Status Updated

November, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work A-2=100%, B-2=100%, A-3=100%, B-3=100%,    A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%, A-8=100%, B-8=100%, A-9=100%, B-9=100%
  Electrical  conduit work A-2=90%, B-2=90%, A-3=90%, B-3=90%,    A-4=90%, B-4=90%, A-5=90%, B-5=90%, A-6=90%, B-6=90%, A-7=90%, B-7=90%,

A-8=90%, B-8=90%, A-9=90%, B-9=90%,

  Door frame fitting work A-2=100%, B-2=100%, A-3=100%, B-3=100%,    A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,

A-8=100%, B-8=100%, A-9=100%, B-9=100%,

  Sanitary & plumbing line  work A-2=80%, B-2=80%, A-3=80%, B-3=80%,    A-4=80%, B-4=80%, A-5=80%, B-5=80%, A-6=80%, B-6=80%, A-7=80%, B-7=80%, A-8=80%, B-8=80%, A-9=70%, B-9=70%
  In side Plastering work A-2=98%, B-2=98%, A-3=98%, B-3=98%,    A-4=95%, B-4=98%, A-5=98%, B-5=98%, A-6=98%, B-6=98%, A-7=98%, B-7=98%,

A-8=95%, B-8=95%, A-9=95%, B-9=90%,

  Electrical cable wiring work A-2=00%, B-2=90%, A-3=90%, B-3=90%,    A-4=90%, B-4=90%, A-5=90%, B-5=90%, A-6=90%, B-6=90%, A-7=90%, B-7=90%, A-8=90%, B-8=90%, A-9=00%, B-9=90%
  Wall tiles  work A-2=00%, B-2=00%, A-3=65%, B-3=15%,    A-4=65%, B-4=65%, A-5=65%, B-5=65%, A-6=65%, B-6=65%, A-7=65%, B-7=65%, A-8=65%, B-8=65%, A-9=65%, B-9=65%
  Common sanitary & Plumbing line work N/A
  Outside plastering work 01. North side = 00%,

02. South side = 50%,

03. East Side = 100%,

04. West Side = 100%.

  Floor tiles/Marble work N/A
  L.C.C work N/A
  Grill & Railing work 20%
  Inside paint & Polishing work 1%
  Switch -Socket fitting work N/A
  Aluminum/Glazing work N/A
  Outside paint work N/A
  Door shutter work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work N/A
  Roof top finishing work N/A
  Roof top Gardening work 70%

16604