The Seasons

Bashundhara R/A, Dhaka
Expected Completion Date December 2028
Status Updated April, 2026
Back to all projects
The Seasons

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
  Pile Work 100% Completed
  Sheet Pile Work 100% Completed
  Foundation work 100% Completed
  Super Structure work 15% completed
  Block work 0% Complete
  Electrical  conduit work 0% Complete
  Door frame fitting work 0% Complete
  Sanitary & plumbing line  work 0%  Complete
  In side Plastering work 0% Complete
  Electrical cable wiring work 0% Complete
  Wall tiles  work 0% Complete
  Common sanitary & Plumbing line work 0% Complete
  Outside plastering work 0% Complete
  Floor tiles/Marble work 0% Complete
  L.C.C work 0% Complete
  Grill & Railing work 0% Complete
  Inside paint & Polishing work 0% Complete
  Switch -Socket fitting work 0% Complete
  Outside paint work 0% Complete
  Door shutter work 0% Complete
  Aluminum/Glazing work 0% Complete
  Tiles Pointing work & Marble finishing work 0% Complete
  Commode – Basin fitting work and C.P fittings work 0% Complete

 

 

 

  Lift/Generator /Substation /Solar work 0% Complete
  Boundary wall /Ground floor development work 0% Complete
  Roof top finishing work 0% Complete
  Roof top Gardening work 0% Complete