The Skyline

Dhanmondi, Dhaka

Expected Completion Date

May 2026

Status Updated

May, 2025

SL. No Name of the work Progress details
01 Shore pile 100%.
  Tie beam 100%
02 Earth cutting 100%
03 Mat casting 100%
04 Supper structure Basement 2 Retaining wall and Roof Slab Casting 100% Complete.

Basement 1 Retaining wall and Roof Slab Casting 100% Complete.

Ground Floor Column and Slab Casting 100% Complete.

1. 1st Floor to 15th floor slab & Column casting 100% complete

2. 1st to 14th floor north & south side fair face wall casting 100%     complete.

3. 1st to 15th floor ceiling plaster 100% complete.

4. 1st to 14th floor block work average 97 % complete.

5. 1st to 14th floor stair Ceiling plaster100 % complete   .

6. 1st to 14th floor False slab & lintel casting average 98% complete

7. 14th,15th floor Up stain & planter box casting 100% complete

8. 1st to 14th floor SDB wall casting 100% complete

 

 

05

 

 

 

Panel work 1st floor to 11th floor panel casting & fitting 95% complete

12th -13th floor panel making average 70% complete & fitting 30% complete.

06 Electrical conducting work 1st to 14th floor vertical riser pipe 100% complete

1st to 14th floor average 80% complete

07 Door frame fitting work  
08 Sanitary & plumbing line work (Ace drain water line, vertical line) 1st to 13th Average 90% complete
09 In side Plastering work Basement -01, Basement-02 Retaining wall plaster100% complete

Typical floor (1st To 14th) wall plaster 65%

 

 

 

10 Electrical cable wiring work B2, B1, G. Floor & 3rd   4th ,5th 7th floor Average 95 %complete
11 Wall tiles work  
12 Common sanitary & Plumbing line work  
13 Outside plastering work 90% work done
14 Floor tiles Typical floor ( 1st To 14th ) total  45 % complete
14 L.C.C work  
15 Grill & Railing work  
16 Inside paint & Polishing work  
17 Switch -Socket fitting work  
18 Outside paint work  
19 Door shutter work  
20 Aluminum/Glazing work  
21 Tiles Pointing work & Marble finishing work  
22 Commode – Basin fitting work and C.P fittings work  

 

23 Lift/Generator /Substation /Solar work  
24 Boundary wall /Ground floor development work Grade beam & column casting 95% complete

Boundary brick wall 95% complete

25 Roof top finishing work  
26 Roof top Gardening work  

 