The Skyline

Dhanmondi, Dhaka

Expected Completion Date

May 2026

Status Updated

September, 2025

SL. No Name of the work Progress details
01 Shore pile 100%.
  Tie beam 100%
02 Earth excavation 100%
03 Mat casting 100%
04 Super structure Basement 2 Retaining wall and Roof Slab Casting 100% Complete.

Basement 1 Retaining wall and Roof Slab Casting 100% Complete.

Ground Floor Column and Slab Casting 100% Complete.

1. 1st Floor to 15th floor slab & Column casting 100% complete

2. 1st to 14th floor north & south side fair face wall casting 100%     complete.

3. 1st to 15th floor ceiling plaster 100% complete.

4. 1st to 14th floor block work average 98 % complete.

5. 1st to 14th floor stair Ceiling plaster100 % complete.

6. 1st to 14th floor False slab & lintel casting average 100% complete.

7. 14th,15th floor Up stand & planter box casting 100% complete

8. 1st to 14th floor SDB wall casting 100% complete

 

 

05

 

 

 

Panel work 1st floor to 13 th floor panel casting & fitting 100% completed
06 Electrical conduiting 1st to 14th floor vertical riser pipe 100% complete

1st to 14th floor internal 95% complete

07 Door frame fitting work 1st to 13th floor 95% complete
08 Sanitary & plumbing line work (Ac drain  line,  vertical line) 1st  to 13th Average 95% complete

 

09 In side Plastering work Basement -01, Basement-02 Retaining wall plaster100% complete

Typical floor ( 1st To 14th ) wall plaster 95%  complete

 

10 Electrical cable wiring work B2, B1, G. Floor & 1st   to 13th floor Average 92 %complete
11 Wall tiles work 70% completed.
12 Common sanitary & Plumbing line work 4th to 11th floor Internal wiring average 60% complete
13 Outside plastering work 98% work done
14 Floor tiles A1,A2,A3,A4,A5,A6,A7,A8,A9,A10,A11,A12,A13,B2,B3,B4,B5,B6, B7,B8,B9,B10,B11,B12,B13Typical floor ( 1st To 14th ) total  85% completed.
15 Grill & Railing work (stair) Stair railing fitting 65% complete
16 Inside paint & Polishing work  
17 Switch -Socket fitting work  
18 Outside paint work  
19 Door shutter work  
20 Aluminum/Glazing work  
21 Tiles Pointing work & Marble finishing work  
22 Commode – Basin fitting work and C.P fittings work  

 

23 Lift/Generator /Substation /Solar work  
24 Boundary wall /Ground floor development work Grade beam & column casting 95% complete

Boundary brick wall 95% complete, plaster work 95% complete

25 Roof top finishing work  Water tank top floor 30% finishing complete
26 Roof top Gardening work  