The Skyline

Dhanmondi, Dhaka

Expected Completion Date

May 2026

Status Updated

July, 2025

SL. No Name of the work Progress details
01 Shore pile 100%.
  Tie beam 100%
02 Earth cutting 100%
03 Mat casting 100%
04 Supper structure Basement 2 Retaining wall and Roof Slab Casting 100% Complete.

Basement 1 Retaining wall and Roof Slab Casting 100% Complete.

Ground Floor Column and Slab Casting 100% Complete.

1. 1st Floor to 15th floor slab & Column casting  100% complete

2. 1st to 14th  floor north & south side fair face wall casting 100%     complete.

3. 1st to 15th floor ceiling plaster  100% complete.

4. 1st to 14th  floor block work average 97 % complete.

5. 1st to 14th floor stair  Ceiling plaster100 % complete   .

6. 1st to 14th floor False slab  & lintel casting average 98% complete

7. 14th,15th floor Up stand & planter box casting 100% complete

8. 1st to 14th floor SDB wall casting 100% complete

 

 

05

 

 

 

Panel work 1st floor to 13 th floor panel casting & fitting 100% completed
06 Electrical conduiting 1st to 14th floor vertical riser pipe 100% complete

1st to 14th floor average 85% complete

07 Door frame fitting work 3rd  to 11th floor 100% complete
08 Sanitary & plumbing line work (Ac drain  line,  vertical line) 1st  to 13th Average 90% complete
09 In side Plastering work Basement -01, Basement-02 Retaining wall plaster100% complete

Typical floor ( 1st To 14th ) wall plaster 80%  complete

 

 

 

10 Electrical cable wiring work B2, B1, G. Floor & 2nd   to 13th floor Average 95 %complete
11 Wall tiles work  
12 Common sanitary & Plumbing line work  
13 Outside plastering work 90% work done
14 Floor tiles A2 ,, A3,,A4,A5,A6,A7,A8,A9, A10,A11,A12,A13,B2,B3,B4,B5,B6,B7,B8,B9,B10,B11,B12,B13Typical floor ( 1st To 14th ) total  70 % complete.
15 Grill & Railing work  
16 Inside paint & Polishing work  
17 Switch -Socket fitting work  
18 Outside paint work  
19 Door shutter work  
20 Aluminum/Glazing work  
21 Tiles Pointing work & Marble finishing work  
22 Commode – Basin fitting work and C.P fittings work  

 

23 Lift/Generator /Substation /Solar work  
24 Boundary wall /Ground floor development work Grade beam & column casting 95% complete

Boundary brick wall 95% complete, plaster work 30% complete

25 Roof top finishing work  
26 Roof top Gardening work  

 

16604