Expected Completion Date
May 2026
Status Updated
September, 2025
SL. No | Name of the work | Progress details |
01 | Shore pile | 100%. |
Tie beam | 100% | |
02 | Earth excavation | 100% |
03 | Mat casting | 100% |
04 | Super structure | Basement 2 Retaining wall and Roof Slab Casting 100% Complete.
Basement 1 Retaining wall and Roof Slab Casting 100% Complete. Ground Floor Column and Slab Casting 100% Complete. 1. 1st Floor to 15th floor slab & Column casting 100% complete 2. 1st to 14th floor north & south side fair face wall casting 100% complete. 3. 1st to 15th floor ceiling plaster 100% complete. 4. 1st to 14th floor block work average 98 % complete. 5. 1st to 14th floor stair Ceiling plaster100 % complete. 6. 1st to 14th floor False slab & lintel casting average 100% complete. 7. 14th,15th floor Up stand & planter box casting 100% complete 8. 1st to 14th floor SDB wall casting 100% complete
|
05
|
Panel work | 1st floor to 13 th floor panel casting & fitting 100% completed |
06 | Electrical conduiting | 1st to 14th floor vertical riser pipe 100% complete
1st to 14th floor internal 95% complete |
07 | Door frame fitting work | 1st to 13th floor 95% complete |
08 | Sanitary & plumbing line work (Ac drain line, vertical line) | 1st to 13th Average 95% complete
|
09 | In side Plastering work | Basement -01, Basement-02 Retaining wall plaster100% complete
Typical floor ( 1st To 14th ) wall plaster 95% complete
|
10 | Electrical cable wiring work | B2, B1, G. Floor & 1st to 13th floor Average 92 %complete |
11 | Wall tiles work | 70% completed. |
12 | Common sanitary & Plumbing line work | 4th to 11th floor Internal wiring average 60% complete |
13 | Outside plastering work | 98% work done |
14 | Floor tiles | A1,A2,A3,A4,A5,A6,A7,A8,A9,A10,A11,A12,A13,B2,B3,B4,B5,B6, B7,B8,B9,B10,B11,B12,B13Typical floor ( 1st To 14th ) total 85% completed. |
15 | Grill & Railing work (stair) | Stair railing fitting 65% complete |
16 | Inside paint & Polishing work | |
17 | Switch -Socket fitting work | |
18 | Outside paint work | |
19 | Door shutter work | |
20 | Aluminum/Glazing work | |
21 | Tiles Pointing work & Marble finishing work | |
22 | Commode – Basin fitting work and C.P fittings work |
|
23 | Lift/Generator /Substation /Solar work | |
24 | Boundary wall /Ground floor development work | Grade beam & column casting 95% complete
Boundary brick wall 95% complete, plaster work 95% complete |
25 | Roof top finishing work | Water tank top floor 30% finishing complete |
26 | Roof top Gardening work |