Expected Completion Date
May 2026
Status Updated
November, 2024
SL. No | Name of the work | Progress details |
01 | Shore pile | 100%. |
Tie beam | 100% | |
02 | Earth cutting | 100% |
03 | Mat casting | 100% |
04 | Supper structure | Basement 2 Retaining wall and Roof Slab Casting 100% Complete.
Basement 1 Retaining wall and Roof Slab Casting 100% Complete. Ground Floor Column and Slab Casting 100% Complete. 1st Floor column and Slab Casting 100% Complete. 2nd Floor Column & Slab casting 100% completed. 3rd Floor Column & Slab casting 100% completed. 4th Floor Column & Slab casting 100% completed. 5th Floor Column & Slab casting 100% completed. 6th Floor Column & Slab casting 100% completed. 7th Floor Column and slab casting 100% completed. 8th floor column & slab casting 100% complete 9th floor column & slab casting 100 % complete. 10th floor Column & slab casting 100% complete. 11th floor slab and column casting 100% complete. 12th floor slab and Column casting 100% complete . 13th floor slab and Column casting 100% complete 14th floor slab casting 100% complete
1st to 13th floor north & south side fair face wall casting 100% complete. 1st to 11th floor ceiling plaster 100% complete. 1st to 6th floor block work average 90 % complete.
|
05
|
Panel work | 2nd Panel slab fitting 90 %
3rd Panel slab fitting 70 % 4th Panel slab fitting 20 % |
06 | Electrical conducting work | 1st to 10th floor vertical riser pipe 80% complete |
07 | Door frame fitting work | |
08 | Sanitary & plumbing line work (Ace drain water line, Ver – vertical line) | |
09 | In side Plastering work | |
10 | Electrical cable wiring work | B2, B1, G. FLOOR Average 30% complete |
11 | Wall tiles work | |
12 | Common sanitary & Plumbing line work | |
13 | Outside plastering work | |
14 | Floor tiles/Marble work | |
14 | L.C.C work | |
15 | Grill & Railing work | |
16 | Inside paint & Polishing work | |
17 | Switch -Socket fitting work | |
18 | Outside paint work | |
19 | Door shutter work | |
20 | Aluminum/Glazing work | |
21 | Tiles Pointing work & Marble finishing work | |
22 | Commode – Basin fitting work and C.P fittings work |
|
23 | Lift/Generator /Substation /Solar work | |
24 | Boundary wall /Ground floor development work | |
25 | Roof top finishing work | |
26 | Roof top Gardening work |