The Skyline

Dhanmondi, Dhaka

Expected Completion Date

May 2026

Status Updated

November, 2024

SL. No Name of the work Progress details
01 Shore pile 100%.
  Tie beam 100%
02 Earth cutting 100%
03 Mat casting 100%
04 Supper structure Basement 2 Retaining wall and Roof Slab Casting 100% Complete.

Basement 1 Retaining wall and Roof Slab Casting 100% Complete.

Ground Floor Column and Slab Casting 100% Complete.

1st Floor column and Slab Casting 100% Complete.

2nd Floor Column & Slab casting 100% completed.

3rd Floor Column & Slab casting 100% completed.

4th Floor Column & Slab casting 100% completed.

5th Floor Column & Slab casting 100% completed.

6th Floor Column & Slab casting 100% completed.

7th Floor Column and slab casting 100% completed.

8th floor column & slab casting 100% complete

9th floor column & slab casting 100 % complete.

10th floor Column & slab casting 100% complete.

11th floor slab and column casting 100% complete.

12th floor slab and Column casting 100% complete .

13th floor slab and Column casting  100% complete

14th floor slab  casting  100% complete

 

1st to 13th  floor north & south side fair face wall casting 100% complete.

1st to 11th floor ceiling plaster  100% complete.

1st to 6th  floor block work average 90 % complete.

 

05

 

 

 

Panel work 2nd Panel slab fitting  90 %

3rd    Panel slab fitting 70 %

4th    Panel slab fitting  20 %

06 Electrical conducting work 1st to 10th floor vertical riser pipe 80% complete
07 Door frame fitting work  
08 Sanitary & plumbing line work (Ace drain water line,  Ver – vertical line)  
09 In side Plastering work  
10 Electrical cable wiring work B2, B1, G. FLOOR Average 30% complete
11 Wall tiles work  
12 Common sanitary & Plumbing line work  
13 Outside plastering work  
14 Floor tiles/Marble work  
14 L.C.C work  
15 Grill & Railing work  
16 Inside paint & Polishing work  
17 Switch -Socket fitting work  
18 Outside paint work  
19 Door shutter work  
20 Aluminum/Glazing work  
21 Tiles Pointing work & Marble finishing work  
22 Commode – Basin fitting work and C.P fittings work  

 

23 Lift/Generator /Substation /Solar work  
24 Boundary wall /Ground floor development work  
25 Roof top finishing work  
26 Roof top Gardening work  

16604