The Skyline

Dhanmondi, Dhaka

Expected Completion Date

May 2026

Status Updated

February, 2025

SL. No Name of the work Progress details
01 Shore pile 100%.
  Tie beam 100%
02 Earth cutting 100%
03 Mat casting 100%
04 Supper structure Basement 2 Retaining wall and Roof Slab Casting 100% Complete.

Basement 1 Retaining wall and Roof Slab Casting 100% Complete.

Ground Floor Column and Slab Casting 100% Complete.

1. 1st Floor to 14th floor slab & Column casting  100% complete

2. 15th floor slab  casting  98% complete

3. 1st to 13th  floor north & south side fair face wall casting 100%     complete.

4. 1st to 14th floor ceiling plaster  100% complete.

5. 1st to 14th  floor block work averag100 % complete.

6. 1st to 14th floor stair  Ceiling plaster100 % complete   .

7. 1st to 14th floor False slab  & lintel casting average 95% complete

8. 14th,15th floor Up stain & planter box casting 100% complete

9. 1st to 10th floor SDB wall casting 95% complete

 

 

05

 

 

 

Panel work  2nd to 8th floor panel casting & fitting 90% complete
06 Electrical conducting work 1st to 14th floor vertical riser pipe 100% complete

1st to 7th floor average 80% complete

07 Door frame fitting work  
08 Sanitary & plumbing line work (Ace drain water line,  Ver – vertical line) 2nd to 13th Average 50% complete
09 In side Plastering work Basement -01, Basement-02 Retaining wall plaster100% complete
10 Electrical cable wiring work B2, B1, G. FLOOR Average 80 %complete
11 Wall tiles work  
12 Common sanitary & Plumbing line work  
13 Outside plastering work 10% work done
14 Floor tiles/Marble work  
14 L.C.C work  
15 Grill & Railing work  
16 Inside paint & Polishing work  
17 Switch -Socket fitting work  
18 Outside paint work  
19 Door shutter work  
20 Aluminum/Glazing work  
21 Tiles Pointing work & Marble finishing work  
22 Commode – Basin fitting work and C.P fittings work  

 

23 Lift/Generator /Substation /Solar work  
24 Boundary wall /Ground floor development work Grade beam & column casting 80% complete

Boundary brick wall 80% complete

25 Roof top finishing work  
26 Roof top Gardening work  

 