The Skyline

Dhanmondi, Dhaka

Completion Date

May 2026

Status Updated

March, 2024

SL. No Name of the work Progress details
01 Shore pile 100%.
02 Tie beam 100%
03 Earth cutting 100%
04 Mat casting 100%
05 Sub-Structure 100%
06 Supper structure Ground Floor Column and Slab Casting 100% Complete.

1st Floor Roof Slab Casting Complete.

2nd Floor Roof Slab Casting Complete.

3rd Floor Roof Slab Casting Complete.

4th Floor Roof Slab Casting Complete.

5th Floor Roof Slab Casting Complete.

6th Floor Roof Slab Casting Complete.

07 Electrical conducting work  
08 Door frame fitting work  
09 Sanitary & plumbing line work (Ace drain water line, Ver- vertical line)  
10 In side Plastering work  
11 Electrical cable wiring work  
12 Wall tiles work  
13 Common sanitary & Plumbing line work  
14 Outside plastering work  
15 Floor tiles/Marble work  
16 L.C.C work  
17 Grill & Railing work  
18 Inside paint & Polishing work  
19 Switch -Socket fitting work  
20 Outside paint work  
21 Door shutter work  
22 Aluminum/Glazing work  
23 Tiles Pointing work & Marble finishing work  
24 Commode – Basin fitting work and C.P fittings work  

 

25 Lift/Generator /Substation /Solar work  
26 Boundary wall /Ground floor development work  
27 Roof top finishing work  
28 Roof top Gardening work  