The Skyline

Dhanmondi, Dhaka
Expected Completion Date May 2026
Status Updated April, 2026
Back to all projects
The Skyline

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Shore pile 100%.
  Tie beam 100%
02 Earth cutting 100%
03 Mat casting 100%
04 Supper structure Basement 2 Retaining wall and Roof Slab Casting 100% Complete.

Basement 1 Retaining wall and Roof Slab Casting 100% Complete.

Ground Floor Column and Slab Casting 100% Complete.

1. 1st Floor to 15th floor slab & Column casting  100% complete

2. 1st to 14th  floor north & south side fair face wall casting 100%     complete.

3. 1st to 15th floor ceiling plaster  100% complete.

4. 1st to 14th  floor block work average 100 % complete.

5. 1st to 14th floor stair  Ceiling plaster100 % complete   .

6. 1st to 14th floor False slab  & lintel casting average 100% complete

7. 14th,15th floor Up stand & planter box casting 100% complete

8. 1st to 14th floor SDB wall casting 100% complete

 

 

05

 

 

 

Panel work 1st floor to 13 th floor panel casting & fitting 100% completed
06 Electrical conduiting 1st to 14th floor vertical riser pipe 100% complete

1st to 14th floor internal 100% complete

07 Door frame fitting work 1st to 13th floor 100% complete
08 Sanitary & plumbing line work (Ac drain  line,  vertical line) G.floor to 13th Average 100% complete

 

09 In side Plastering work Basement -01, Basement-02 Retaining wall plaster100% complete

Typical floor ( 1st To 14th ) wall plaster 100%  complete

 

10 Electrical cable wiring work B2, B1, 1st   to 6th floor 100 %complete

7th to 14th floor 97% complete

11 Wall tiles work Kitchen  100% complete. Bath room 98% complete
12 Common sanitary & Plumbing line work 1st   to 14th floor  Internal wiring average 98% complete
13 Outside plastering work 100% work done
14 Floor tiles A1,A2 ,, A3,,A4,A5,A6,A7,A8,A9, A10,A11,A12,A13,B1, B2,B3,B4,B5,B6,B7,B8,B9,B10,B11,B12,B13Typical floor ( 1st To 14th ) total  100% complete.
15 Grill & Railing work( stair ) Stair railing fitting 98% complete
16 Inside paint & Polishing work 1st to 13th floor (1st coat) 100% complete.

1st to 13th floor (2nd coat) 98% complete

17 Switch -Socket fitting work 1st to 7th floor 97% complete
18 Outside paint work 1st to 14th floor 1st coat 100% complete
19 Door shutter work  
20 Aluminum/Glazing work Front side framing & Glass Fixing100 % complete And other side frame & glass fixing =96% complete.
21 Tiles Pointing work & Marble finishing work 1st & 13th floor 95 % complete
22 Commode – Basin fitting work and C.P fittings work 2nd to 13th floor kitchen sink fitting  100% complete
23 Lift/Generator /Substation /Solar work Lift work 85% complete. Generator work  75% complete
24 Boundary wall /Ground floor development work Grade beam & column casting 100% complete.

Boundary brick wall 100% complete, plaster work 100% complete.

25 Roof top finishing work  Water tank tiles work 100% finishing complete
26 Roof top Gardening work  R.C.C work 100% complete.

 