Completion Date
May 2026
Status Updated
March, 2024
SL. No | Name of the work | Progress details |
01 | Shore pile | 100%. |
02 | Tie beam | 100% |
03 | Earth cutting | 100% |
04 | Mat casting | 100% |
05 | Sub-Structure | 100% |
06 | Supper structure | Ground Floor Column and Slab Casting 100% Complete.
1st Floor Roof Slab Casting Complete. 2nd Floor Roof Slab Casting Complete. 3rd Floor Roof Slab Casting Complete. 4th Floor Roof Slab Casting Complete. 5th Floor Roof Slab Casting Complete. 6th Floor Roof Slab Casting Complete. |
07 | Electrical conducting work | |
08 | Door frame fitting work | |
09 | Sanitary & plumbing line work (Ace drain water line, Ver- vertical line) | |
10 | In side Plastering work | |
11 | Electrical cable wiring work | |
12 | Wall tiles work | |
13 | Common sanitary & Plumbing line work | |
14 | Outside plastering work | |
15 | Floor tiles/Marble work | |
16 | L.C.C work | |
17 | Grill & Railing work | |
18 | Inside paint & Polishing work | |
19 | Switch -Socket fitting work | |
20 | Outside paint work | |
21 | Door shutter work | |
22 | Aluminum/Glazing work | |
23 | Tiles Pointing work & Marble finishing work | |
24 | Commode – Basin fitting work and C.P fittings work |
|
25 | Lift/Generator /Substation /Solar work | |
26 | Boundary wall /Ground floor development work | |
27 | Roof top finishing work | |
28 | Roof top Gardening work |