The Sunlight

Bashundhara R/A, Dhaka

Expected Completion Date

March 2025

Status Updated

November, 2024

SL. No Name of the work Progress details
01 Foundation work 100%
02 Super Structure work 100%
03 Block Work A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5 =100%, A-6= 100%, A-7= 100%, A-8= 100%, A-8= 90%,
04 Electrical conducting work A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5 =100%, A-6= 100%, A-7= 100%, A-8= 80%, A-9= 50%,
05 Door frame fitting work A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5 =100%, A-6 =100%, A-7 =100%, A-8 =100%,
06 Sanitary & plumbing line work A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100% A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100% ,A-9= 100%
07 In side Plastering work A-1 =100%, A-2= 100%, A-3=100%, A-4=100%, A-5=100%, A-6=100%, A-7=100%, A-8=100%, A-9=100%,
08 Electrical cable wiring work A-1 =100%, A-2= 100%, A-3=100%, A-4=100%, A-5=100%, A-6=100%, A-7=100%, A-8=100%, A-9=100%,
09 Wall tiles work A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5 =100%, A-6= 100%, A-7=100%, A-6= 100%, A-7=100%, A-8=100%, A-9=100%,
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work 100%
12 Floor tiles/Marble work A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5 =100%, A-6= 100%, A-7=100%, A-8=100%, A-9=100%,
13 L.C.C work 100%
14 Grill & Railing work A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5 =100%, A-6= 100%, A-7=100%, A-8=100%, A-9=100%,
15 Inside paint & Polishing work A-1 =0%, A-2= 20%, A-3= 20%, A-4= 20%, A-5 =20%, A-6= 20%, A-7=30%,  A-8=10%, A-9=10%,
16 Switch -Socket fitting work N/A
17 Outside paint work 20%
18 Door shutter work 60%
19 Aluminum work 30%
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work 20%
23 Boundary wall /Ground floor development work 50%
24 Roof top finishing work 80%
25 Roof top Gardening work G.F Garden work N/A

 

 

16604