Twinkle

Block D, Bashundhara R/A

Expected Completion Date

January 2026

Status Updated

February, 2026

SL. No Name of the work Progress details
01 Foundation work Foundation 100% completed
02 Super Structure work 100%
03 Block Work A-1 =100%, A-2= 100%, A-3= 100%, A- 4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8=100%, A-9=100%
04 Electrical conducting work 90%
05 Door frame fitting work A-1 =100%, A-2= 100%, A-3= 100%, A- 4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8=100%, A-9=100%
06 Sanitary & plumbing line work N/A
07 In side Plastering work A-2= 100%, A-3= 100%, A- 4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
08 Electrical cable wiring work 100%
09 Wall tiles work 100%
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work 100%
12 Floor tiles/Marble work 100%
13 L.C.C work 100%
14 Grill & Railing work 95%
15 Inside paint & Polishing work 80%
16 Switch -Socket fitting work 80%
17 Outside paint work 70%
18 Door shutter work 90%
19 Aluminum work 90%
20 Tiles Pointing work & Marble finishing work 40%
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work 90%
24 Roof top finishing work

 

90%
25 Roof top Gardening work G.F Garden work N/A

 