Expected Completion Date
October 2026
Status Updated
September, 2025
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | Tower-1: Ground floor slab 100%,1st floor slab 100%,2nd floor slab 100%,3rd floor slab 100%,4th floor slab 100%.
5th floor 100%, 5th floor column 100%. 6th floor slab 100%, 7th floor slab 100%. 8th floor column 100%,8th floor slab 100%.
Tower-2: 1st floor slab 100%,2nd floor slab 100%, 3rd floor slab 100% ,4th floor slab 100%. 5th floor slab 100%. 6th floor slab 100%, 6th floor column 100%,7th floor slab 100%, 8th floor column 100% 8th floor slab 100% 9th floor column 100%,9th Floor Slab 100%
|
|
Block work | Tower-1: Ground floor Substation room, Stair wall 90%. 1st floor 70%, 2nd floor 100%, 3rd floor 100%, 4th floor 100%,5th floor 100%, 6th 100%,7th floor 97% 8TH Floor96 %
Tower-2: 1st floor 100%, 2nd floor 100%,3rd floor 97%, 4th floor 96%, 5th floor 90%,6th Floor 85% 7th Floor 80% 8th Floor 70% 9th Floor 25% |
|
Electrical conduit work | Tower-1: 1st floor slab conduiting100%, 2nd floor slab conduiting 100%, 3rd floor slab conduiting 100%,4th floor slab conduiting 100%,5th floor slab conduiting 100%. 6th floor slab 100%,7th floor 100%, 8th floor slab 100%, 9th floor slab 100%
Tower-2:1st floor floor slab conduiting100%, 2nd floor slab conduiting 100%, 3rd floor slab conduiting 100%. 4th floor slab 100%,5th floor 100%,6th floor slab 100%,7th floor slab 100%. 8th floor 100% 9th floor 100% 10th Floor 80% |
|
Door frame fitting work | 440 | |
Sanitary & plumbing line work | 78% | |
In side Ceiling Plaster & Wall Plaster work | Tower-1 Basement ceiling Plaster 100%,
Ground floor ceiling Plaster 100%, 2nd floor celling 100%, 4th floor 100%,5th floor 100%, 6th floor slab 100%,7th floor 100% , 8th floor slab 100%. Basement wall Plaster 95%,2nd floor wall Plaster 98%,3rd Floor wall plaster98% 4th Floor 98%,5th Floor wall Plaster 97%, 6th floor 96%, 7th floor 90%,8th floor wall plaster 80%
Tower-2 1st floor celling 100%,2nd floor ceiling 100%, 3rd floor 100%, 4th floor 100%, 5th floor 100%,6th floor 100% 7th Floor plaster 95% ,8th floor celing plaster 90%,9th Floor celing plaster 80%.1st floor wall Plaster 85%,2nd floor Wall plaster 85%,3rd floor wall plaster 80%,4th floor wall plaster 80%, 5th Floor wall plaster 70% |
|
Electrical cable wiring work | Basement 80%, Ground floor 70%. | |
Wall tiles work | 55% | |
Common sanitary & Plumbing line work | 50% | |
Outside plastering work | 30% | |
Floor tiles/Marble work | 10% | |
L.C.C work | N/A | |
Grill & Railing work | N/A | |
Inside paint & Polishing work | N/A | |
Switch -Socket fitting work | N/A | |
Outside paint work | N/A | |
Door shutter work | N/A | |
Aluminum/Glazing work | N/A | |
Tiles Pointing work & Marble finishing work | N/A | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | N/A | |
Boundary wall /Ground floor development work | N/A | |
Roof top finishing work | 60% | |
Roof top Gardening work | N/A |
16604