Expected Completion Date
October 2026
Status Updated
November, 2024
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | Tower-1: Ground floor slab 100%,1st floor slab 100%,2nd floor slab 100%,3rd floor slab 100%,4th floor slab 100%.
5th floor 100%, 5th floor column 100%. 6th floor slab 100%, 7th floor slab 100%. 8th floor column 100%,9th floor slab 100%.
Tower-2: 1st floor slab 100%,2nd floor slab 100%, 3rd floor slab 100% ,4th floor slab 100%. 5th floor slab 100%. 6th floor slab 100%, 6th floor column 100%,7th floor slab 100%, 8th floor column 100% 8th floor slab 100% 9th floor column 100%,9th Floor Slab 100%
|
|
Block work | Tower-1: Ground floor Substation room, Stair wall 90%. 1st floor 70%, 2nd floor 95%, 3rd floor 95%, 4th floor 80%,5th floor 80%, 6th 80%,7th floor 80%
Tower-2: 1st floor 90%, 2nd floor 90%,3rd floor 85%, 4th floor 85%, 5th floor 70%, |
|
Electrical conduit work | Tower-1: 1st floor slab conduiting100%, 2nd floor slab conduiting 100%, 3rd floor slab conduiting 100%,4th floor slab conduiting 100%,5th floor slab conduiting 100%. 6th floor slab 100%,7th floor 100%, 8th floor slab 100%, 9th floor slab 100%
Tower-2:1st floor floor slab conduiting100%, 2nd floor slab conduiting 100%, 3rd floor slab conduiting 100%. 4th floor slab 100%,5th floor 100%,6th floor slab 100%,7th floor slab 100%. 8th floor 100% 9th floor 100%
|
|
Door frame fitting work | 130 | |
Sanitary & plumbing line work | N/A | |
In side Plastering work | Tower-1 Basement ceiling Plaster 100%,
Ground floor ceiling Plaster 90%, 2nd floor celling 100%, 4th floor 100%,5th floor 100%, 6th floor slab 100%,7th floor 100% , 8th floor slab 100%
Tower-2 1st floor celling 100%,2nd floor ceiling 100%, 3rd floor 100%, 4th floor 100%, 5th floor 100%,6th floor 100% 7th Floor plaster 70% |
|
Electrical cable wiring work | Basement 60%, Ground floor 50%. | |
Wall tiles work | N/A | |
Common sanitary & Plumbing line work | N/A | |
Outside plastering work | N/A | |
Floor tiles/Marble work | N/A | |
L.C.C work | N/A | |
Grill & Railing work | N/A | |
Inside paint & Polishing work | N/A | |
Switch -Socket fitting work | N/A | |
Outside paint work | N/A | |
Door shutter work | 20 | |
Aluminum/Glazing work | N/A | |
Tiles Pointing work & Marble finishing work | N/A | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | N/A | |
Boundary wall /Ground floor development work | N/A | |
Roof top finishing work | N/A | |
Roof top Gardening work | N/A |
16604