Valencia

Uttara, Dhaka

Expected Completion Date

October 2026

Status Updated

November, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work Tower-1: Ground floor slab 100%,1st floor slab 100%,2nd floor slab 100%,3rd floor slab 100%,4th floor slab 100%.

5th floor 100%, 5th floor column 100%.

6th floor slab 100%, 7th floor slab 100%.

8th floor column 100%,9th floor slab 100%.

 

Tower-2: 1st floor slab 100%,2nd floor slab 100%, 3rd floor slab 100% ,4th floor slab 100%. 5th floor slab 100%. 6th floor slab 100%, 6th floor column 100%,7th floor slab 100%, 8th floor column 100% 8th floor slab 100% 9th floor column 100%,9th Floor Slab 100%

 

  Block work Tower-1: Ground floor Substation room, Stair wall 90%. 1st floor 70%, 2nd floor 95%, 3rd floor 95%, 4th floor 80%,5th floor 80%, 6th  80%,7th floor 80%

 

Tower-2: 1st floor 90%, 2nd floor 90%,3rd floor 85%, 4th floor 85%, 5th floor 70%,

  Electrical  conduit work Tower-1: 1st floor slab conduiting100%, 2nd floor slab conduiting 100%, 3rd floor slab conduiting 100%,4th floor slab conduiting 100%,5th floor slab conduiting 100%. 6th floor slab 100%,7th floor 100%, 8th floor slab 100%, 9th floor slab 100%

 

Tower-2:1st floor floor slab conduiting100%, 2nd  floor slab conduiting 100%, 3rd floor slab conduiting 100%. 4th floor slab 100%,5th floor 100%,6th floor slab 100%,7th floor slab 100%. 8th floor 100% 9th floor 100%

 

  Door frame fitting work 130
  Sanitary & plumbing line  work N/A
  In side Plastering work Tower-1 Basement ceiling Plaster 100%,

Ground floor ceiling Plaster 90%, 2nd floor celling 100%, 4th floor 100%,5th floor 100%, 6th floor slab 100%,7th floor 100% , 8th floor slab 100%

 

Tower-2 1st floor celling 100%,2nd floor ceiling 100%, 3rd floor 100%, 4th floor 100%, 5th floor 100%,6th floor 100% 7th Floor plaster 70%

  Electrical cable wiring work Basement 60%, Ground floor 50%.
  Wall tiles  work N/A
  Common sanitary & Plumbing line work N/A
  Outside plastering work N/A
  Floor tiles/Marble work N/A
  L.C.C work N/A
  Grill & Railing work N/A
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work 20
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work N/A
  Roof top finishing work N/A
  Roof top Gardening work N/A

 

16604