Valencia

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work Tower-1: Ground floor slab 100%,1st floor slab 100%,2nd floor slab 100%,3rd floor slab 100%,4th floor slab 100%.

5th floor 100%, 5th floor column 100%.

6th floor slab 100%, 7th floor slab 100%.

8th floor column 100%,8th floor slab 100%.

 

Tower-2: 1st floor slab 100%,2nd floor slab 100%, 3rd floor slab 100% ,4th floor slab 100%. 5th floor slab 100%. 6th floor slab 100%, 6th floor column 100%,7th floor slab 100%, 8th floor column 100% 8th floor slab 100% 9th floor column 100%,9th Floor Slab 90%

 

  Block work Tower-1: Ground floor Substation room, Stair wall 95%. 1st floor 95%, 2nd floor 100%, 3rd floor 100%, 4th floor 100%,5th floor 100%, 6th floor 100%,7th floor 100% 8TH Floor100 %

 

Tower-2: 1st floor 100%, 2nd floor 100%,3rd floor 100%, 4th floor 100%, 5th floor 100%,6th Floor 100% 7th Floor 100% 8th Floor 100% 9th Floor 85%

  Electrical  conduit work Tower-1: 1st floor slab conduiting100%, 2nd floor slab conduiting 100%, 3rd floor slab conduiting 100%,4th floor slab conduiting 100%,5th floor slab conduiting 100%. 6th floor slab 100%,7th floor 100%, 8th floor slab 100%, 9th floor slab 100%

 

Tower-2:1st floor floor slab conduiting100%, 2nd  floor slab conduiting 100%, 3rd floor slab conduiting 100%. 4th floor slab 100%,5th floor 100%,6th floor slab 100%,7th floor slab 100%. 8th floor slab 100% 9th floor slab100%

  Door frame fitting work 440
  Sanitary & plumbing line  work 86%
  In side Ceiling Plaster & Wall Plaster work Tower-1 Basement ceiling Plaster 100%,

Ground floor ceiling Plaster 100%, 2nd floor celling 100%, 4th floor 100%,5th floor 100%, 6th floor slab 100%,7th floor 100%, 8th floor ceiling plaster 100%. Basement wall Plaster 95%,2nd floor wall Plaster 100%,3rd Floor wall plaster100% 4th Floor wall plaster 100%,5th Floor wall Plaster 100%, 6th floor wall plaster 100%, 7th floor wall plaster 100%,8th floor wall plaster 100%

 

Tower-2 1st floor celling 100%,2nd floor ceiling 100%, 3rd floor 100%, 4th floor 100%, 5th floor 100%,6th floor 100% 7th Floor plaster 100% ,8th floor ceiling plaster 100%,9th Floor ceiling plaster 80%….1st floor wall Plaster 100%,2nd floor Wall plaster 100%,3rd floor wall plaster 100%,4th floor wall plaster 100%, 5th Floor wall plaster 100%,6th floor wall plaster 90%,7th floor wall plaster 85% 8th floor wall plaster 80% 9th floor wall plaster 20%

  Electrical cable wiring work Basement 80%, Ground floor 75%.
  Wall tiles  work 85%
  Common sanitary & Plumbing line work 60%
  Outside plastering work 80%
  Floor tiles/Marble work 70%
  L.C.C work 50%
  Grill & Railing work 80%
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work N/A
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work 70%
  Roof top finishing work 90%
  Roof top Gardening work N/A