Completion Date
May 2026
Status Updated
February, 2024
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | Tower-1: Ground floor slab 100%,1st floor slab 100%,2nd floor slab 100%,3rd floor slab 100%,4th floor slab 100%.
5th floor 100%, 5th floor column 100%. Tower-2: 1st floor slab 100%,2nd floor slab 100%, 3rd floor slab 100% |
|
Block work | Tower-1: Ground floor Substation room, Stair wall 90%. 2nd floor 15%. | |
Electrical conduit work | Tower-1: 1st floor slab conduiting100%, 2nd floor slab conduiting 100%, 3rd floor slab conduiting 100%,4th floor slab conduiting 100%,5th floor slab conduiting 100%.
Tower-2:1st floor floor slab conduiting100%, 2nd floor slab conduiting 100%, 3rd floor slab conduiting 100%.
|
|
Door frame fitting work | N/A | |
Sanitary & plumbing line work | N/A | |
In side Plastering work | Tower-1 Basement ceiling Plaster 100%,
Ground floor ceiling Plaster 20%, 2nd floor celling 50%. Tower-2 1st floor celling 100%. |
|
Electrical cable wiring work | Basement 30%, Ground floor 50%. | |
Wall tiles work | N/A | |
Common sanitary & Plumbing line work | N/A | |
Outside plastering work | N/A | |
Floor tiles/Marble work | N/A | |
L.C.C work | N/A | |
Grill & Railing work | N/A | |
Inside paint & Polishing work | N/A | |
Switch -Socket fitting work | N/A | |
Outside paint work | N/A | |
Door shutter work | N/A | |
Aluminum/Glazing work | N/A | |
Tiles Pointing work & Marble finishing work | N/A | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | N/A | |
Boundary wall /Ground floor development work | N/A | |
Roof top finishing work | N/A | |
Roof top Gardening work | N/A |