Welcome Home

Mirpur, Dhaka

Expected Completion Date

November 2026

Status Updated

September, 2025

Name of the work Progress details
Foundation work 100% Completed
Super Structure work 93% completed
Block work A Type =90%

B Type =90%

C Type =75%

D Type =90%

E Type =80%

F Type =85%

G Type =80%

H Type =80%

I Type =80%

J Type =70%

K Type =75%

 

Conduit Pipe Work A Type =90%

B Type =90%

C Type =75%

D Type =80%

E Type =75%

F Type =75%

G Type =70%

H Type =70%

I Type =70%

J Type =60%

K Type =65%

 

Door frame fitting work A Type =60%

B Type =60%

C Type =55%

D Type =70%

E Type =70%

F Type =70%

G Type =70%

H Type =40%

I Type =40%

J Type =15%

K Type =40%

 

Sanitary & plumbing line work A Type =50%

B Type =50%

C Type =50%

D Type =50%

E Type =50%

F Type =50%

G Type =50%

H Type =50%

I Type =50%

J Type =50%

K Type =50%

 

In side Plastering work Tower1&2, Basement Ceiling=95%

GF Ceiling= 95%,

1st Floor Ceiling= 95%,

2nd Floor Ceiling= 95%

3rd Floor Ceiling=95%,

4th Floor Ceiling=95%,

5th Floor Ceiling=95%,

6th Floor Ceiling=95%,

7th Floor Ceiling=95%,

8th Floor Ceiling=95%,

9th Floor Ceiling=95%,

10th Floor Ceiling=95%,

11th Floor Ceiling=95%,

12th Floor Ceiling=95%,

13th Floor Ceiling=20%,

 

Inside Wall Plaster:

1st floor 80%,

2nd floor 95%

3rd floor 95%

4th floor 85%

5th floor 70%

6th floor 40%

7th floor 40%

 

 

Electrical cable wiring work Basement= 95%,

Ground Floor=60%

1st floor 10%,

2nd floor 10%

3rd floor 10%

4th floor 10%

5th floor 10%

6th floor 10%

 

 

Wall tiles work Wall tiles work

1st floor 30%,

2nd floor 50%

3rd floor 50%

4th floor 40%

5th floor 30%

 

Common sanitary & Plumbing line work 1st Floor = 40%,

2nd Floor = 40%

3rd Floor = 40%,

4th Floor = 40%,

5th Floor = 40%,

6th Floor = 40%,

 

Outside plastering work N/A
Floor tiles/Marble work N/A
L.C.C work N/A
Grill & Railing work N/A
Inside paint & Polishing work N/A
Switch -Socket fitting work N/A
Outside paint work N/A
Door shutter work N/A
Aluminum/Glazing work N/A
Tiles Pointing work & Marble finishing work N/A
Commode – Basin fitting work and C.P fittings work N/A
Lift/Generator /Substation /Solar work N/A
Boundary wall /Ground floor development work Boundary wall = 40%

 

Roof top finishing work N/A
Roof top Gardening work N/A