Welcome Home

Mirpur, Dhaka

Expected Completion Date

November 2026

Status Updated

May, 2025

Name of the work Progress details
Foundation work 99% Completed
Super Structure work 92% completed
Block work A Type =70%

B Type =70%

C Type =65%

D Type =70%

E Type =70%

F Type =70%

G Type =60%

H Type =60%

I Type =60%

J Type =50%

K Type =55%

 

Conduit Pipe Work A Type =65%

B Type =65%

C Type =60%

D Type =65%

E Type =65%

F Type =65%

G Type =55%

H Type =55%

I Type =55%

J Type =45%

K Type =50%

 

Door frame fitting work A Type =25%

B Type =25%

C Type =25%

D Type =30%

E Type =30%

F Type =30%

G Type =30%

H Type =25%

I Type =25%

J Type =00%

K Type =25%

 

Sanitary & plumbing line work N/A
In side Plastering work Tower1&2, Basement Ceiling=95%

GF Ceiling= 95%,

1st Floor Ceiling= 95%,

2nd Floor Ceiling= 95%

3rd Floor Ceiling=95%,

4th Floor Ceiling=95%,

5th Floor Ceiling=95%,

6th Floor Ceiling=95%,

7th Floor Ceiling=95%,

8th Floor Ceiling=95%,

9th Floor Ceiling=95%,

10th Floor Ceiling=95%,

11th Floor Ceiling=95%,

 

Inside Wall Plaster:

1st floor 50%,

2nd floor 85%

3rd floor50%

 

Electrical cable wiring work Basement= 95%, Ground Floor=60%
Wall tiles work N/A
Common sanitary & Plumbing line work N/A
Outside plastering work N/A
Floor tiles/Marble work N/A
L.C.C work N/A
Grill & Railing work N/A
Inside paint & Polishing work N/A
Switch -Socket fitting work N/A
Outside paint work N/A
Door shutter work N/A
Aluminum/Glazing work N/A
Tiles Pointing work & Marble finishing work N/A
Commode – Basin fitting work and C.P fittings work N/A
Lift/Generator /Substation /Solar work N/A
Boundary wall /Ground floor development work N/A
Roof top finishing work N/A
Roof top Gardening work N/A