Welcome Home

Mirpur, Dhaka

Expected Completion Date

November 2026

Status Updated

July, 2025

Name of the work Progress details
Foundation work 100% Completed
Super Structure work 93% completed
Block work A Type =75%

B Type =75%

C Type =70%

D Type =75%

E Type =75%

F Type =80%

G Type =65%

H Type =70%

I Type =70%

J Type =50%

K Type =65%

 

Conduit Pipe Work A Type =70%

B Type =70%

C Type =65%

D Type =70%

E Type =70%

F Type =75%

G Type =60%

H Type =65%

I Type =65%

J Type =45%

K Type =60%

 

Door frame fitting work A Type =40%

B Type =40%

C Type =40%

D Type =55%

E Type =40%

F Type =55%

G Type =55%

H Type =25%

I Type =25%

J Type =05%

K Type =30%

 

Sanitary & plumbing line work N/A
In side Plastering work Tower1&2, Basement Ceiling=95%

GF Ceiling= 95%,

1st Floor Ceiling= 95%,

2nd Floor Ceiling= 95%

3rd Floor Ceiling=95%,

4th Floor Ceiling=95%,

5th Floor Ceiling=95%,

6th Floor Ceiling=95%,

7th Floor Ceiling=95%,

8th Floor Ceiling=95%,

9th Floor Ceiling=95%,

10th Floor Ceiling=95%,

11th Floor Ceiling=95%,

12th Floor Ceiling=10%,

 

 

 

Inside Wall Plaster:

1st floor 60%,

2nd floor 90%

3rd floor 70%

4th floor 60%

 

Electrical cable wiring work Basement= 95%, Ground Floor=60%
Wall tiles work N/A
Common sanitary & Plumbing line work 1st Floor = 40%,

2nd Floor = 40%

3rd Floor = 40%,

4th Floor = 40%,

5th Floor = 40%,

6th Floor = 40%,

 

Outside plastering work N/A
Floor tiles/Marble work N/A
L.C.C work N/A
Grill & Railing work N/A
Inside paint & Polishing work N/A
Switch -Socket fitting work N/A
Outside paint work N/A
Door shutter work N/A
Aluminum/Glazing work N/A
Tiles Pointing work & Marble finishing work N/A
Commode – Basin fitting work and C.P fittings work N/A
Lift/Generator /Substation /Solar work N/A
Boundary wall /Ground floor development work Boundary wall = 40%

 

Roof top finishing work N/A
Roof top Gardening work N/A