Expected Completion Date
November 2026
Status Updated
December, 2025
| Name of the work | Progress details |
| Foundation work | 100% Completed |
| Super Structure work | 95% completed |
| Block work | A Type =98%
B Type =98% C Type =95% D Type =98% E Type =90% F Type =98% G Type =95% H Type =85% I Type =85% J Type =90% K Type =98% |
| Conduit Pipe Work | A Type =95%
B Type =95% C Type =80% D Type =90% E Type =80% F Type =90% G Type =80% H Type =75% I Type =75% J Type =75% K Type =95% |
| Door frame fitting work | A Type =95%
B Type =95% C Type =90% D Type =95% E Type =85% F Type =100% G Type =98% H Type =65% I Type =65% J Type =65% K Type =95% |
| Sanitary & plumbing line work | A Type =60%
B Type =60% C Type =60% D Type =60% E Type =60% F Type =60% G Type =60% H Type =50% I Type =50% J Type =50% K Type =60% |
| In side Plastering work | Tower1&2, Basement Ceiling=95%
GF Ceiling= 95%, 1st Floor Ceiling= 95%, 2nd Floor Ceiling= 95% 3rd Floor Ceiling=95%, 4th Floor Ceiling=95%, 5th Floor Ceiling=95%, 6th Floor Ceiling=95%, 7th Floor Ceiling=95%, 8th Floor Ceiling=95%, 9th Floor Ceiling=95%, 10th Floor Ceiling=95%, 11th Floor Ceiling=95%, 12th Floor Ceiling=95%, 13th Floor Ceiling=95%, Inside Wall Plaster: 1st floor 90%, 2nd floor 95% 3rd floor 95% 4th floor 95% 5th floor 95% 6th floor 85% 7th floor 85% 8th floor 70% 9th floor 55% 10th floor 30% 11th floor 10% 12th floor 05% 13th floor 05%
|
| Electrical cable wiring work | Basement= 95%,
Ground Floor=60% 1st floor 10%, 2nd floor 10% 3rd floor 60% 4th floor 10% 5th floor 10% 6th floor 10% 7th floor 10% 8th floor 10% 9th floor 10% 10th floor 05% 11th floor 05% |
| Wall tiles work | Wall tiles work
1st floor 40%, 2nd floor 80% 3rd floor 80% 4th floor 80% 5th floor 80% 6th floor 80% 7th floor 80% 8th floor 80% 9th floor 60% 10th floor 50% 11th floor 50%
|
| Common sanitary & Plumbing line work | 1st Floor = 40%,
2nd Floor = 40% 3rd Floor = 40%, 4th Floor = 40%, 5th Floor = 40%, 6th Floor = 40%, |
| Outside plastering work | Outside Wall Plaster:
13th floor 10% 12th floor 10% 11th floor 10% 10th floor 10% 09th floor 10% 08th floor 10% 07th floor 10% 06th floor 10% 05th floor 10% 04th floor 10% 03th floor 10% 02th floor 10% 01th floor 10%
|
| Floor tiles/Marble work | Floor tiles work
1st floor 40%, 2nd floor 80% 3rd floor 80% 4th floor 80% 5th floor 80% 6th floor 80%
|
| L.C.C work | N/A |
| Grill & Railing work | N/A |
| Inside paint & Polishing work | N/A |
| Switch -Socket fitting work | N/A |
| Outside paint work | N/A |
| Door shutter work | N/A |
| Aluminum/Glazing work | N/A |
| Tiles Pointing work & Marble finishing work | N/A |
| Commode – Basin fitting work and C.P fittings work | N/A |
| Lift/Generator /Substation /Solar work | N/A |
| Boundary wall /Ground floor development work | Boundary wall = 60%
|
| Roof top finishing work | N/A |
| Roof top Gardening work | N/A |