Welcome Home

Mirpur, Dhaka

Expected Completion Date

November 2026

Status Updated

February, 2026

Name of the work Progress details
Foundation work 100% Completed
Super Structure work 95% completed
Block work A Type =100%

B Type =98%

C Type =95%

D Type =100%

E Type =98%

F Type =100%

G Type =100%

H Type =95%

I Type =100%

J Type =95%

K Type =100%

Conduit Pipe Work A Type =100%

B Type =100%

C Type =100%

D Type =100%

E Type =100%

F Type =100%

G Type =100%

H Type =90%

I Type =100%

J Type =100%

K Type =100%

Door frame fitting work A Type =100%

B Type =99%

C Type =95%

D Type =100%

E Type =90%

F Type =100%

G Type =100%

H Type =98%

I Type =98%

J Type =70%

K Type =100%

Sanitary & plumbing line work A Type =90%

B Type =90%

C Type =80%

D Type =90%

E Type =60%

F Type =100%

G Type =100%

H Type =80%

I Type =80%

J Type =50%

K Type =90%

In side Plastering work Tower1&2, Basement Ceiling=95%

GF Ceiling= 95%,

1st Floor Ceiling= 95%,

2nd Floor Ceiling= 95%

3rd Floor Ceiling=95%,

4th Floor Ceiling=95%,

5th Floor Ceiling=95%,

6th Floor Ceiling=95%,

7th Floor Ceiling=95%,

8th Floor Ceiling=95%,

9th Floor Ceiling=95%,

10th Floor Ceiling=95%,

11th Floor Ceiling=95%,

12th Floor Ceiling=95%,

13th Floor Ceiling=95%,

Inside Wall Plaster:

1st floor 90%,

2nd floor 95%

3rd floor 95%

4th floor 95%

5th floor 95%

6th floor 90%

7th floor 90%

8th floor 90%

9th floor 90%

10th floor 60%

11th floor 50%

12th floor 40%

13th floor 40%

 

Electrical cable wiring work Basement= 95%,

Ground Floor=60%

1st floor 10%,

2nd floor 10%

3rd floor 80%

4th floor 80%

5th floor 10%

6th floor 10%

7th floor 10%

8th floor 10%

9th floor 10%

10th floor 10%

11th floor 10%

12th floor 05%

13th floor 05%

 

Wall tiles work Wall tiles work

1st floor 40%,

2nd floor 90%

3rd floor 90%

4th floor 90%

5th floor 90%

6th floor 90%

7th floor 90%

8th floor 90%

9th floor 90%

10th floor 90%

11th floor 90%

12th floor 60%

13th floor 60%

 

Common sanitary & Plumbing line work 1st Floor = 40%,

2nd Floor = 40%

3rd Floor = 40%,

4th Floor = 40%,

5th Floor = 40%,

6th Floor = 40%,

7th floor 20%

8th floor 20%

9th floor 20%

10th floor 20%

11th floor 15%

12th floor 10%

13th floor 10%

 

 

Outside plastering work Outside Wall Plaster:

13th floor 40%

12th floor 50%

11th floor 35%

10th floor 35%

09th floor 35%

08th floor 35%

07th floor 35%

06th floor 35%

05th floor 20%

04th floor 20%

03th floor 20%

02th floor 20%

01th floor 20%

 

Floor tiles/Marble work/Granait work Floor tiles work:

1st floor 7%,

2nd floor 7%

3rd floor 7%

4th floor 7%

5th floor 7%

6th floor 7%

7th floor 7%

8th floor 10%

9th floor 15%

10th floor 10%

11th floor 10%

12th floor 20%

13th floor 20%

 

Granait work:

1st floor 4%,

2nd floor 4%

3rd floor 4%

4th floor 4%

5th floor 4%

6th floor 4%

 

 

L.C.C work N/A
Grill & Railing work 1st floor 0%,

2nd floor 5%

3rd floor 5%

4th floor 5%

5th floor 5%

6th floor 5%

7th floor 5%

8th floor 5%

9th floor 5%

10th floor 5%

11th floor 5%

12th floor 5%

13th floor 5%

 

 

Inside paint & Polishing work N/A
Switch -Socket fitting work N/A
Outside paint work N/A
Door shutter work N/A
Aluminum/Glazing work N/A
Tiles Pointing work & Marble finishing work N/A
Commode – Basin fitting work and C.P fittings work N/A
Lift/Generator /Substation /Solar work N/A
Boundary wall /Ground floor development work Boundary wall = 62%

 

Roof top finishing work N/A
Roof top Gardening work N/A

16604