Welcome Home

Mirpur, Dhaka

Expected Completion Date

November 2026

Status Updated

March, 2025

Name of the work Progress details
Foundation work 99% Completed
Super Structure work 92% completed
Block work A Type =55%

B Type =55%

C Type =55%

D Type =50%

E Type =50%

F Type =50%

G Type =50%

H Type =50%

I Type =50%

J Type =50%

K Type =50%

 

Conduit Pipe Work A Type =50%

B Type =50%

C Type =50%

D Type =45%

E Type =45%

F Type =45%

G Type =45%

H Type =45%

I Type =45%

J Type =45%

K Type =45%

 

Door frame fitting work A Type =25%

B Type =17%

C Type =17%

D Type =08%

E Type =17%

F Type =08%

G Type =08%

H Type =17%

I Type =17%

J Type =00%

K Type =17%

 

 

 

Sanitary & plumbing line work N/A
In side Plastering work Tower1&2, Basement Ceiling=95%

GF Ceiling= 95%,

1st Floor Ceiling= 95%,

2nd Floor Ceiling= 95%

3rd Floor Ceiling=95%,

4th Floor Ceiling=95%,

5th Floor Ceiling=95%,

6th Floor Ceiling=95%,

7th Floor Ceiling=95%,

8th Floor Ceiling=95%,

9th Floor Ceiling=95%,

10th Floor Ceiling=60%,

 

Inside Wall Plaster:

1st floor 50%,

2nd floor 65%

Electrical cable wiring work Basement= 95%, Ground Floor=60%
Wall tiles work N/A
Common sanitary & Plumbing line work N/A
Outside plastering work N/A
Floor tiles/Marble work N/A
L.C.C work N/A
Grill & Railing work N/A
Inside paint & Polishing work N/A
Switch -Socket fitting work N/A
Outside paint work N/A
Door shutter work N/A
Aluminum/Glazing work N/A
Tiles Pointing work & Marble finishing work N/A
Commode – Basin fitting work and C.P fittings work N/A
Lift/Generator /Substation /Solar work N/A
Boundary wall /Ground floor development work N/A
Roof top finishing work N/A
Roof top Gardening work N/A

 