Expected Completion Date
November 2026
Status Updated
July, 2025
Name of the work | Progress details |
Foundation work | 100% Completed |
Super Structure work | 93% completed |
Block work | A Type =75%
B Type =75% C Type =70% D Type =75% E Type =75% F Type =80% G Type =65% H Type =70% I Type =70% J Type =50% K Type =65%
|
Conduit Pipe Work | A Type =70%
B Type =70% C Type =65% D Type =70% E Type =70% F Type =75% G Type =60% H Type =65% I Type =65% J Type =45% K Type =60%
|
Door frame fitting work | A Type =40%
B Type =40% C Type =40% D Type =55% E Type =40% F Type =55% G Type =55% H Type =25% I Type =25% J Type =05% K Type =30%
|
Sanitary & plumbing line work | N/A |
In side Plastering work | Tower1&2, Basement Ceiling=95%
GF Ceiling= 95%, 1st Floor Ceiling= 95%, 2nd Floor Ceiling= 95% 3rd Floor Ceiling=95%, 4th Floor Ceiling=95%, 5th Floor Ceiling=95%, 6th Floor Ceiling=95%, 7th Floor Ceiling=95%, 8th Floor Ceiling=95%, 9th Floor Ceiling=95%, 10th Floor Ceiling=95%, 11th Floor Ceiling=95%, 12th Floor Ceiling=10%,
Inside Wall Plaster: 1st floor 60%, 2nd floor 90% 3rd floor 70% 4th floor 60%
|
Electrical cable wiring work | Basement= 95%, Ground Floor=60% |
Wall tiles work | N/A |
Common sanitary & Plumbing line work | 1st Floor = 40%,
2nd Floor = 40% 3rd Floor = 40%, 4th Floor = 40%, 5th Floor = 40%, 6th Floor = 40%,
|
Outside plastering work | N/A |
Floor tiles/Marble work | N/A |
L.C.C work | N/A |
Grill & Railing work | N/A |
Inside paint & Polishing work | N/A |
Switch -Socket fitting work | N/A |
Outside paint work | N/A |
Door shutter work | N/A |
Aluminum/Glazing work | N/A |
Tiles Pointing work & Marble finishing work | N/A |
Commode – Basin fitting work and C.P fittings work | N/A |
Lift/Generator /Substation /Solar work | N/A |
Boundary wall /Ground floor development work | Boundary wall = 40%
|
Roof top finishing work | N/A |
Roof top Gardening work | N/A |