Welcome Home

Mirpur, Dhaka

Expected Completion Date

November 2026

Status Updated

December, 2025

Name of the work Progress details
Foundation work 100% Completed
Super Structure work 95% completed
Block work A Type =98%

B Type =98%

C Type =95%

D Type =98%

E Type =90%

F Type =98%

G Type =95%

H Type =85%

I Type =85%

J Type =90%

K Type =98%

Conduit Pipe Work A Type =95%

B Type =95%

C Type =80%

D Type =90%

E Type =80%

F Type =90%

G Type =80%

H Type =75%

I Type =75%

J Type =75%

K Type =95%

Door frame fitting work A Type =95%

B Type =95%

C Type =90%

D Type =95%

E Type =85%

F Type =100%

G Type =98%

H Type =65%

I Type =65%

J Type =65%

K Type =95%

Sanitary & plumbing line work A Type =60%

B Type =60%

C Type =60%

D Type =60%

E Type =60%

F Type =60%

G Type =60%

H Type =50%

I Type =50%

J Type =50%

K Type =60%

In side Plastering work Tower1&2, Basement Ceiling=95%

GF Ceiling= 95%,

1st Floor Ceiling= 95%,

2nd Floor Ceiling= 95%

3rd Floor Ceiling=95%,

4th Floor Ceiling=95%,

5th Floor Ceiling=95%,

6th Floor Ceiling=95%,

7th Floor Ceiling=95%,

8th Floor Ceiling=95%,

9th Floor Ceiling=95%,

10th Floor Ceiling=95%,

11th Floor Ceiling=95%,

12th Floor Ceiling=95%,

13th Floor Ceiling=95%,

Inside Wall Plaster:

1st floor 90%,

2nd floor 95%

3rd floor 95%

4th floor 95%

5th floor 95%

6th floor 85%

7th floor 85%

8th floor 70%

9th floor 55%

10th floor 30%

11th floor 10%

12th floor 05%

13th floor 05%

 

Electrical cable wiring work Basement= 95%,

Ground Floor=60%

1st floor 10%,

2nd floor 10%

3rd floor 60%

4th floor 10%

5th floor 10%

6th floor 10%

7th floor 10%

8th floor 10%

9th floor 10%

10th floor 05%

11th floor 05%

Wall tiles work Wall tiles work

1st floor 40%,

2nd floor 80%

3rd floor 80%

4th floor 80%

5th floor 80%

6th floor 80%

7th floor 80%

8th floor 80%

9th floor 60%

10th floor 50%

11th floor 50%

 

 

 

Common sanitary & Plumbing line work 1st Floor = 40%,

2nd Floor = 40%

3rd Floor = 40%,

4th Floor = 40%,

5th Floor = 40%,

6th Floor = 40%,

Outside plastering work Outside Wall Plaster:

13th floor 10%

12th floor 10%

11th floor 10%

10th floor 10%

09th floor 10%

08th floor 10%

07th floor 10%

06th floor 10%

05th floor 10%

04th floor 10%

03th floor 10%

02th floor 10%

01th floor 10%

 

Floor tiles/Marble work Floor tiles work

1st floor 40%,

2nd floor 80%

3rd floor 80%

4th floor 80%

5th floor 80%

6th floor 80%

 

L.C.C work N/A
Grill & Railing work N/A
Inside paint & Polishing work N/A
Switch -Socket fitting work N/A
Outside paint work N/A
Door shutter work N/A
Aluminum/Glazing work N/A
Tiles Pointing work & Marble finishing work N/A
Commode – Basin fitting work and C.P fittings work N/A
Lift/Generator /Substation /Solar work N/A
Boundary wall /Ground floor development work Boundary wall = 60%

 

Roof top finishing work N/A
Roof top Gardening work N/A

 