Expected Completion Date
November 2026
Status Updated
September, 2025
| Name of the work | Progress details |
| Foundation work | 100% Completed |
| Super Structure work | 93% completed |
| Block work | A Type =90%
B Type =90% C Type =75% D Type =90% E Type =80% F Type =85% G Type =80% H Type =80% I Type =80% J Type =70% K Type =75%
|
| Conduit Pipe Work | A Type =90%
B Type =90% C Type =75% D Type =80% E Type =75% F Type =75% G Type =70% H Type =70% I Type =70% J Type =60% K Type =65%
|
| Door frame fitting work | A Type =60%
B Type =60% C Type =55% D Type =70% E Type =70% F Type =70% G Type =70% H Type =40% I Type =40% J Type =15% K Type =40%
|
| Sanitary & plumbing line work | A Type =50%
B Type =50% C Type =50% D Type =50% E Type =50% F Type =50% G Type =50% H Type =50% I Type =50% J Type =50% K Type =50%
|
| In side Plastering work | Tower1&2, Basement Ceiling=95%
GF Ceiling= 95%, 1st Floor Ceiling= 95%, 2nd Floor Ceiling= 95% 3rd Floor Ceiling=95%, 4th Floor Ceiling=95%, 5th Floor Ceiling=95%, 6th Floor Ceiling=95%, 7th Floor Ceiling=95%, 8th Floor Ceiling=95%, 9th Floor Ceiling=95%, 10th Floor Ceiling=95%, 11th Floor Ceiling=95%, 12th Floor Ceiling=95%, 13th Floor Ceiling=20%,
Inside Wall Plaster: 1st floor 80%, 2nd floor 95% 3rd floor 95% 4th floor 85% 5th floor 70% 6th floor 40% 7th floor 40%
|
| Electrical cable wiring work | Basement= 95%,
Ground Floor=60% 1st floor 10%, 2nd floor 10% 3rd floor 10% 4th floor 10% 5th floor 10% 6th floor 10%
|
| Wall tiles work | Wall tiles work
1st floor 30%, 2nd floor 50% 3rd floor 50% 4th floor 40% 5th floor 30%
|
| Common sanitary & Plumbing line work | 1st Floor = 40%,
2nd Floor = 40% 3rd Floor = 40%, 4th Floor = 40%, 5th Floor = 40%, 6th Floor = 40%,
|
| Outside plastering work | N/A |
| Floor tiles/Marble work | N/A |
| L.C.C work | N/A |
| Grill & Railing work | N/A |
| Inside paint & Polishing work | N/A |
| Switch -Socket fitting work | N/A |
| Outside paint work | N/A |
| Door shutter work | N/A |
| Aluminum/Glazing work | N/A |
| Tiles Pointing work & Marble finishing work | N/A |
| Commode – Basin fitting work and C.P fittings work | N/A |
| Lift/Generator /Substation /Solar work | N/A |
| Boundary wall /Ground floor development work | Boundary wall = 40%
|
| Roof top finishing work | N/A |
| Roof top Gardening work | N/A |