Expected Completion Date
April 2026
Status Updated
January, 2026
| SL. No | Name of the work | Progress details |
| 01 | Service pile | 100%. |
| 02 | Grade beam | 100% |
| 03 | Earth cutting | 100% |
| 04 | Pile cap casting | 100% |
| 05 | Supper structure | 1.Ground Floor Column and Slab Casting 100% Complete.
2.1st Floor to 9th floor slab and column 100%. 3.Roof top parapet wall 100% 4.Roof top design wall100 % 5.Over head water tank 100% 6.lift machine room 100%
|
| 06
|
Panel work & Block Work | 1st floor panel work 100%, 2nd floor panel work 85%, 3rd floor panel work 100%, 4rth floor panel work 100%, 5th panel work 100%, 6th panel work 100%,7th floor panel work 100%,8th floor panel work 100%,9th floor panel 100%,
Block work1st floor work 98%, 2nd floor 70%,3rd floor 100%,4rth floor 100%,5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%. |
| 07 | Electrical conducting work | 1st floor 80%, 2nd Floor 60%, 3rd & 4rth floor vertical wearing 95%, 5th 95%, 6th floor 95%,7th floor 95%,8th floor 95%,9th floor 95%. |
| 08 | Door frame fitting work | 2nd floor 70%,3rd floor 100%, 4rth floor 100%, 5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%, |
| 09 | Sanitary & plumbing line work (Ac drain water line, vertical line) | 2nd floor 50%,3rd floor 60%,4rth floor 70%,5th floor 70%,6th floor 70%,7th floor 70%,8th floor 70%,9th floor 70%, |
| 10 | In side Plastering work | GF ceiling plaster 90%, 1st fllor 90%,2nd floor 95%,3rd floor 95%,4rth floor100%,5th floor100%,6th floor100%, 7th floor 100%, 8th floor 100%, 9th floor 100%.
1st floor wall plaster 70%,2nd floor 60%, 3rd floor 95%,4rth floor 95%,5th floor 95%,6th 90%,7th 95%,8th 95%,9th floor 95%.
|
| 10 | Electrical cable wiring work | N/A |
| 11 | Wall tiles work | B4 70%,A5 60%, B5 60%, B6 60%, A7 60%, B7 60%, B8 70%, A9 60%, B9 60%, |
| 12 | Common sanitary & Plumbing line work | N/A |
| 13 | Outside plastering work | 95% |
| 14 | Floor tiles | A4 70%, B4 70%, A5 70%, B5 70%, A7 70%, B7 70%, A8 70%, B8 70%, A9 70%, B9 70%. |
| 14 | L.C.C work | 100% |
| 15 | Grill & Railing work | 20% |
| 16 | Inside paint & Polishing work | N/A |
| 17 | Switch -Socket fitting work | N/A |
| 18 | Outside paint work | N/A |
| 19 | Door shutter work | N/A |
| 20 | Aluminum/Glazing work | N/A |
| 21 | Tiles Pointing work & Marble finishing work | N/A |
| 22 | Commode – Basin fitting work and C.P fittings work | N/A |
| 23 | Lift/Generator /Substation /Solar work | N/A |
| 24 | Boundary wall /Ground floor development work | 40%. |
| 25 | Roof top finishing work | 60% |
| 26 | Roof top Gardening work | 40% |