Expected Completion Date
April 2026
Status Updated
October, 2025
| SL. No | Name of the work | Progress details |
| 01 | Service pile | 100%. |
| 02 | Grade beam | 100% |
| 03 | Earth cutting | 100% |
| 04 | Pile cap casting | 100% |
| 05 | Supper structure | 1.Ground Floor Column and Slab Casting 100% Complete.
2.1st Floor to 9th floor slab and column 100%. 3.Roof top parapet wall 100% 4.Roof top design wall 97% 5.Overhead water tank 100% 6.lift machine room 100%
|
| 06
|
Panel work & Block Work | 3rd floor panel work 100%, 4th floor panel work 100%, 5th floor panel work 95%, 6th floor panel work 95%,7th floor panel work 95%, 8th floor panel work 95%, 9th floor panel 90%,
Block work1st floor work 60%, 2nd floor 45%,3rd floor 100%,4rth floor 100%,5th floor 100%,6th floor 100%,7th floor 100%,8th floor 90%,9th floor 95%. |
| 07 | Electrical conducting work | 1st floor 60%, 3rd & 4rth floor vertical wearing 95%, 5th 95%, 6th floor 95%,7th floor 95%,8th floor 95%,9th floor 95%. |
| 08 | Door frame fitting work | 3rd floor 90%,4rth 90%.5th 90%,6th 90%,7th 90%,8th 90%,
9th 90%, |
| 09 | Sanitary & plumbing line work (Ace drain water line, vertical line) | 2nd floor 20%,3rd floor 50%,4rth floor 50%,5th floor 60%,6th floor 50%,7th floor 50%,8th floor 50%,9th Floor 50%, |
| 10 | In side Plastering work | GF ceiling plaster 60%, 1st fllor 80%,2nd floor 90%,3rd floor 100%,4rth floor100%,5th floor100%,6th floor100%, 7th floor 100%, 8th floor 90%, 9th floor 90%.
1st floor wall plaster 60%, 3rd floor 90%,4rth floor 95%,5th floor 90%,6th Floor 90%, 7th Floor 90%, 8th Floor 20%,
|
| 10 | Electrical cable wiring work | N/A |
| 11 | Wall tiles work | 5th floor 15%,7th floor 10%, |
| 12 | Common sanitary & Plumbing line work | N/A |
| 13 | Outside plastering work | 50% |
| 14 | Floor tiles | N/A |
| 14 | L.C.C work | N/A |
| 15 | Grill & Railing work | N/A |
| 16 | Inside paint & Polishing work | N/A |
| 17 | Switch -Socket fitting work | N/A |
| 18 | Outside paint work | N/A |
| 19 | Door shutter work | N/A |
| 20 | Aluminum/Glazing work | N/A |
| 21 | Tiles Pointing work & Marble finishing work | N/A |
| 22 | Commode – Basin fitting work and C.P fittings work | N/A |
| 23 | Lift/Generator /Substation /Solar work | N/A |
| 24 | Boundary wall /Ground floor development work | N/A |
| 25 | Roof top finishing work | N/A |
| 26 | Roof top Gardening work | N/A |
16604