West Gate

Dhanmondi, Dhaka

Expected Completion Date

April 2026

Status Updated

September, 2025

SL. No Name of the work Progress details
01 Service pile 100%.
02 Grade beam 100%
03 Earth cutting 100%
04 Pile cap casting 100%
05 Supper structure 1.Ground Floor Column and Slab Casting 100% Complete.

2.1st Floor to 9th floor slab and column 100%.

3.Roof top parapet wall 100%

4.Roof top design wall 95%

5.Overhead water tank 100%

6.lift machine room 100%

 

 

06

 

 

 

Panel work & Block Work 1st floor 80% completed, 2nd floor 5% completed, 3rd floor panel work 100%, 4th floor panel work 100%, 5th  floor panel work 100%, 6th  panel work 100%,7th floor panel work 100%,8th floor panel work 100%,9th floor panel 80%,

Block work1st floor work 70%, 2nd floor 30%,3rd floor 100%,4rth floor 100%,5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%.

07 Electrical conducting work 1st floor 70%, 3rd & 4rth floor vertical wearing 90%, 5th 90%, 6th floor 70%,7th floor 70%,8th floor 65%,9th floor 55%.
08 Door frame fitting work 3rd floor 90%, 4th floor 90%, 5th floor 90%, 6th floor 90% completed, 7th floor 90% completed.
09 Sanitary & plumbing line work (Ace drain water line,  vertical line) 2nd floor 15%,3rd floor 15%,4th floor 15%,5th floor 15%,6th floor 15%,7th floor 15%,8th floor 15%
10 In side Plastering work GF ceiling plaster 70%, 1st fllor 80%,2nd floor 95%,3rd floor 95%,4rth floor95%,5th floor95%,6th floor95%, 7th floor 95%, 8th floor 95%, 9th floor 90%.

1st floor wall plaster 50%, 3rd floor 90%,4th floor 90%,5th floor 90%, 6th floor 70% completed

 

 

 

10 Electrical cable wiring work N/A
11 Wall tiles work N/A
12 Common sanitary & Plumbing line work 10% completed
13 Outside plastering work 30%
14 Floor tiles N/A
14 L.C.C work N/A
15 Grill & Railing work N/A
16 Inside paint & Polishing work N/A
17 Switch -Socket fitting work N/A
18 Outside paint work N/A
19 Door shutter work N/A
20 Aluminum/Glazing work N/A
21 Tiles Pointing work & Marble finishing work N/A
22 Commode – Basin fitting work and C.P fittings work N/A
23 Lift/Generator /Substation /Solar work N/A
24 Boundary wall /Ground floor development work N/A
25 Roof top finishing work N/A
26 Roof top Gardening work N/A