Expected Completion Date
April 2026
Status Updated
March, 2025
SL. No | Name of the work | Progress details |
01 | Foundation work | 100% |
02 | Super Structure work | G.F 100%, 1st Floor (Roof Slab) -100%, 2nd Floor Roof Slab -100%, 3rd Floor Roof Slab -100%, 4th Floor Roof Slab -100% completed, 5th Floor Roof Slab -100% completed. 6th floor roof slab – 100% completed. 7th floor roof slab 100% completed. 8th floor roof slab 100% completed. 9th floor roof slab 100% completed. |
03 | Block Work | 2nd Floor -60%, 3rd Floor -70%, 4th Floor Roof Slab -50% completed. |
04 | Electrical conduiting work | 10% Completed.
|
05 | Door frame fitting work | Not Yet Started. |
06 | Sanitary & plumbing line work (Ace drain water line, ven- vertical line) | Not Yet Started. |
07 | In side Plastering work | 10% Completed. |
08 | Electrical cable wiring work | Not Yet Started. |
09 | Wall tiles work | Not Yet Started. |
10 | Common sanitary & Plumbing line work | Not Yet Started. |
11 | Outside plastering work | Not Yet Started. |
12 | Floor tiles/Marble work | Not Yet Started. |
13 | L.C.C work | Not Yet Started. |
14 | Grill & Railing work | Not Yet Started. |
15 | Inside paint & Polishing work | Not Yet Started. |
16 | Switch -Socket fitting work | Not Yet Started. |
17 | Outside paint work | Not Yet Started. |
18 | Door shutter work | Not Yet Started. |
19 | Aluminum/Glazing work | Not Yet Started. |
20 | Tiles Pointing work & Marble finishing work | Not Yet Started. |
21 | Commode – Basin fitting work and C.P fittings work | Not Yet Started. |
22 | Lift/Generator /Substation /Solar work | Not Yet Started. |
23 | Boundary wall /Ground floor development work | Not Yet Started. |
24 | Roof top finishing work | Not Yet Started. |
25 | Roof top Gardening work | Not Yet Started. |
16604