West Gate

Dhanmondi, Dhaka

Expected Completion Date

April 2026

Status Updated

January, 2026

SL. No Name of the work Progress details
01 Service pile 100%.
02 Grade beam 100%
03 Earth cutting 100%
04 Pile cap casting 100%
05 Supper structure 1.Ground Floor Column and Slab Casting 100% Complete.

2.1st Floor to 9th floor slab and column 100%.

3.Roof top parapet wall 100%

4.Roof top design wall100 %

5.Over head water tank 100%

6.lift machine room 100%

 

 

06

 

 

 

Panel work & Block Work 1st floor panel work 100%, 2nd floor panel work 85%, 3rd floor panel work 100%, 4rth floor panel work 100%, 5th  panel work 100%, 6th  panel work 100%,7th floor panel work 100%,8th floor panel work 100%,9th floor panel 100%,

Block work1st floor work 98%, 2nd floor 70%,3rd floor 100%,4rth floor 100%,5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%.

07 Electrical conducting work 1st floor 80%, 2nd Floor 60%, 3rd & 4rth floor vertical wearing 95%, 5th 95%, 6th floor 95%,7th floor 95%,8th floor 95%,9th floor 95%.
08 Door frame fitting work 2nd floor 70%,3rd floor 100%, 4rth floor 100%, 5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%,
09 Sanitary & plumbing line work (Ac drain water line,  vertical line) 2nd floor 50%,3rd floor 60%,4rth floor 70%,5th floor 70%,6th floor 70%,7th floor 70%,8th floor 70%,9th floor 70%,
10 In side Plastering work GF ceiling plaster 90%, 1st fllor 90%,2nd floor 95%,3rd floor 95%,4rth floor100%,5th floor100%,6th floor100%, 7th floor 100%, 8th floor 100%, 9th floor 100%.

1st floor wall plaster 70%,2nd floor 60%, 3rd floor 95%,4rth floor 95%,5th floor 95%,6th 90%,7th 95%,8th 95%,9th floor 95%.

 

 

 

10 Electrical cable wiring work N/A
11 Wall tiles work B4 70%,A5 60%, B5 60%, B6 60%, A7 60%, B7 60%, B8 70%,  A9 60%, B9 60%,
12 Common sanitary & Plumbing line work N/A
13 Outside plastering work 95%
14 Floor tiles A4 70%, B4 70%, A5 70%, B5 70%, A7 70%, B7 70%, A8 70%, B8 70%, A9 70%, B9 70%.
14 L.C.C work 100%
15 Grill & Railing work 20%
16 Inside paint & Polishing work N/A
17 Switch -Socket fitting work N/A
18 Outside paint work N/A
19 Door shutter work N/A
20 Aluminum/Glazing work N/A
21 Tiles Pointing work & Marble finishing work N/A
22 Commode – Basin fitting work and C.P fittings work N/A
23 Lift/Generator /Substation /Solar work N/A
24 Boundary wall /Ground floor development work 40%.
25 Roof top finishing work  60%
26 Roof top Gardening work 40%

16604