West Gate

Dhanmondi, Dhaka

Expected Completion Date

April 2026

Status Updated

October, 2025

SL. No Name of the work Progress details
01 Service pile 100%.
02 Grade beam 100%
03 Earth cutting 100%
04 Pile cap casting 100%
05 Supper structure 1.Ground Floor Column and Slab Casting 100% Complete.

2.1st Floor to 9th floor slab and column 100%.

3.Roof top parapet wall 100%

4.Roof top design wall 97%

5.Overhead water tank 100%

6.lift machine room 100%

 

 

06

 

 

 

Panel work & Block Work 3rd floor panel work 100%, 4th floor panel work 100%, 5th floor   panel work 95%, 6th floor  panel work 95%,7th floor panel work 95%, 8th floor panel work 95%, 9th floor panel 90%,

Block work1st floor work 60%, 2nd floor 45%,3rd floor 100%,4rth floor 100%,5th floor 100%,6th floor 100%,7th floor 100%,8th floor 90%,9th floor 95%.

07 Electrical conducting work 1st floor 60%, 3rd & 4rth floor vertical wearing 95%, 5th 95%, 6th floor 95%,7th floor 95%,8th floor 95%,9th floor 95%.
08 Door frame fitting work 3rd floor 90%,4rth 90%.5th 90%,6th 90%,7th 90%,8th 90%,

9th 90%,

09 Sanitary & plumbing line work (Ace drain water line,  vertical line) 2nd floor 20%,3rd floor 50%,4rth floor 50%,5th floor 60%,6th floor 50%,7th floor 50%,8th floor 50%,9th Floor 50%,
10 In side Plastering work GF ceiling plaster 60%, 1st fllor 80%,2nd floor 90%,3rd floor 100%,4rth floor100%,5th floor100%,6th floor100%, 7th floor 100%, 8th floor 90%, 9th floor 90%.

1st floor wall plaster 60%, 3rd floor 90%,4rth floor 95%,5th floor 90%,6th Floor 90%, 7th Floor 90%, 8th Floor 20%,

 

 

 

10 Electrical cable wiring work N/A
11 Wall tiles work 5th floor 15%,7th floor 10%,
12 Common sanitary & Plumbing line work N/A
13 Outside plastering work 50%
14 Floor tiles N/A
14 L.C.C work N/A
15 Grill & Railing work N/A
16 Inside paint & Polishing work N/A
17 Switch -Socket fitting work N/A
18 Outside paint work N/A
19 Door shutter work N/A
20 Aluminum/Glazing work N/A
21 Tiles Pointing work & Marble finishing work N/A
22 Commode – Basin fitting work and C.P fittings work N/A
23 Lift/Generator /Substation /Solar work N/A
24 Boundary wall /Ground floor development work N/A
25 Roof top finishing work  N/A
26 Roof top Gardening work N/A

 