West Gate

Dhanmondi, Dhaka

Expected Completion Date

April 2026

Status Updated

December, 2025

SL. No Name of the work Progress details
01 Service pile 100%.
02 Grade beam 100%
03 Earth cutting 100%
04 Pile cap casting 100%
05 Supper structure 1.Ground Floor Column and Slab Casting 100% Complete.

2.1st Floor to 9th floor slab and column 100%.

3.Roof top parapet wall 100%

4.Roof top design wall100 %

5.Over head water tank 100%

6.lift machine room 100%

 

 

06

 

 

 

Panel work & Block Work 3rd floor panel work 100%, 4rth floor panel work 100%, 5th  panel work 95%, 6th  panel work 95%,7th floor panel work 95%,8th floor panel work 95%,9th floor panel 95%,

Block work1st floor work 90%, 2nd floor 60%,3rd floor 100%,4rth floor 100%,5th floor 100%,6th floor 100%,7th floor 100%,8th floor 95%,9th floor 95%.

07 Electrical conducting work 1st floor 80%, 2nd Floor 60%, 3rd & 4rth floor vertical wearing 95%, 5th 95%, 6th floor 95%,7th floor 95%,8th floor 95%,9th floor 95%.
08 Door frame fitting work 2nd floor 50%,3rd floor 100%, 4rth floor 100%, 5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%,
09 Sanitary & plumbing line work (Ac drain water line,  vertical line) 2nd floor 30%,3rd floor 50%,4rth floor 60%,5th floor 60%,6th floor 60%,7th floor 60%,8th floor 60%,9th floor 60%,
10 In side Plastering work GF ceiling plaster 80%, 1st fllor 90%,2nd floor 95%,3rd floor 95%,4rth floor95%,5th floor95%,6th floor95%, 7th floor 95%, 8th floor 95%, 9th floor 95%.

1st floor wall plaster 60%,2nd floor 50%, 3rd floor 95%,4rth floor 95%,5th floor 95%,6th 90%,7th 95%,8th 95%,9th floor 95%.

 

 

 

10 Electrical cable wiring work Not Yet Started.
11 Wall tiles work A5 40%, B5 40%, B6 40%, A7 40%, B7 40%, A9 40%, B9 50%
12 Common sanitary & Plumbing line work Not Yet Started.
13 Outside plastering work 90%
14 Floor tiles Not Yet Started.
14 L.C.C work Not Yet Started.
15 Grill & Railing work Not Yet Started.
16 Inside paint & Polishing work Not Yet Started.
17 Switch -Socket fitting work Not Yet Started.
18 Outside paint work Not Yet Started.
19 Door shutter work Not Yet Started.
20 Aluminum/Glazing work Not Yet Started.
21 Tiles Pointing work & Marble finishing work Not Yet Started.
22 Commode – Basin fitting work and C.P fittings work Not Yet Started.
23 Lift/Generator /Substation /Solar work Not Yet Started.
24 Boundary wall /Ground floor development work 30%.
25 Roof top finishing work  40%
26 Roof top Gardening work 30%

 