West Gate

Dhanmondi, Dhaka

Expected Completion Date

April 2026

Status Updated

November, 2025

SL. No Name of the work Progress details
01 Service pile 100%.
02 Grade beam 100%
03 Earth cutting 100%
04 Pile cap casting 100%
05 Supper structure 1.Ground Floor Column and Slab Casting 100% Complete.

2.1st Floor to 9th floor slab and column 100%.

3.Roof top parapet wall 100%

4.Roof top design wall100 %

5.Over head water tank 100%

6.lift machine room 100%

 

 

06

 

 

 

Panel work & Block Work 3rd floor panel work 100%, 4rth floor panel work 100%, 5th  panel work 95%, 6th  panel work 95%,7th floor panel work 95%,8th floor panel work 90%,9th floor panel 80%,

Block work1st floor work 70%, 2nd floor 50%,3rd floor 100%,4rth floor 100%,5th floor 100%,6th floor 100%,7th floor 100%,8th floor 95%,9th floor 95%.

07 Electrical conducting work 1st floor 50%, 2nd Floor 50%, 3rd & 4rth floor vertical wearing 95%, 5th 95%, 6th floor 95%,7th floor 95%,8th floor 95%,9th floor 90%.
08 Door frame fitting work 3rd floor 95%, 4rth floor 95%, 5th floor 95%,6th floor 95%,7th floor 95%,8th floor 95%,9th floor 95%,
09 Sanitary & plumbing line work (Ac drain water line,  vertical line) 2nd floor 20%,3rd floor 40%,4rth floor 40%,5th floor 40%,6th floor 40%,7th floor 40%,8th floor 40%,9th floor 40%,
10 In side Plastering work GF ceiling plaster 60%, 1st fllor 80%,2nd floor 95%,3rd floor 95%,4rth floor95%,5th floor95%,6th floor95%, 7th floor 95%, 8th floor 95%, 9th floor 90%.

1st floor wall plaster 60%, 3rd floor 90%,4rth floor 90%,5th floor 90%,6th 90%,7th 90%,8th 90%,9th floor 90%.

 

 

 

10 Electrical cable wiring work Not Yet Started
11 Wall tiles work 5th floor 40%, 7th floor 40%.
12 Common sanitary & Plumbing line work Not Yet Started
13 Outside plastering work 70%
14 Floor tiles Not Yet Started
14 L.C.C work Not Yet Started
15 Grill & Railing work Not Yet Started
16 Inside paint & Polishing work Not Yet Started
17 Switch -Socket fitting work Not Yet Started
18 Outside paint work Not Yet Started
19 Door shutter work Not Yet Started
20 Aluminum/Glazing work Not Yet Started
21 Tiles Pointing work & Marble finishing work Not Yet Started
22 Commode – Basin fitting work and C.P fittings work Not Yet Started
23 Lift/Generator /Substation /Solar work Not Yet Started
24 Boundary wall /Ground floor development work 10%.
25 Roof top finishing work  20%
26 Roof top Gardening work Not Yet Started