Expected Completion Date
April 2026
Status Updated
September, 2025
SL. No | Name of the work | Progress details |
01 | Service pile | 100%. |
02 | Grade beam | 100% |
03 | Earth cutting | 100% |
04 | Pile cap casting | 100% |
05 | Supper structure | 1.Ground Floor Column and Slab Casting 100% Complete.
2.1st Floor to 9th floor slab and column 100%. 3.Roof top parapet wall 100% 4.Roof top design wall 95% 5.Overhead water tank 100% 6.lift machine room 100%
|
06
|
Panel work & Block Work | 1st floor 80% completed, 2nd floor 5% completed, 3rd floor panel work 100%, 4th floor panel work 100%, 5th floor panel work 100%, 6th panel work 100%,7th floor panel work 100%,8th floor panel work 100%,9th floor panel 80%,
Block work1st floor work 70%, 2nd floor 30%,3rd floor 100%,4rth floor 100%,5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%. |
07 | Electrical conducting work | 1st floor 70%, 3rd & 4rth floor vertical wearing 90%, 5th 90%, 6th floor 70%,7th floor 70%,8th floor 65%,9th floor 55%. |
08 | Door frame fitting work | 3rd floor 90%, 4th floor 90%, 5th floor 90%, 6th floor 90% completed, 7th floor 90% completed. |
09 | Sanitary & plumbing line work (Ace drain water line, vertical line) | 2nd floor 15%,3rd floor 15%,4th floor 15%,5th floor 15%,6th floor 15%,7th floor 15%,8th floor 15% |
10 | In side Plastering work | GF ceiling plaster 70%, 1st fllor 80%,2nd floor 95%,3rd floor 95%,4rth floor95%,5th floor95%,6th floor95%, 7th floor 95%, 8th floor 95%, 9th floor 90%.
1st floor wall plaster 50%, 3rd floor 90%,4th floor 90%,5th floor 90%, 6th floor 70% completed
|
10 | Electrical cable wiring work | N/A |
11 | Wall tiles work | N/A |
12 | Common sanitary & Plumbing line work | 10% completed |
13 | Outside plastering work | 30% |
14 | Floor tiles | N/A |
14 | L.C.C work | N/A |
15 | Grill & Railing work | N/A |
16 | Inside paint & Polishing work | N/A |
17 | Switch -Socket fitting work | N/A |
18 | Outside paint work | N/A |
19 | Door shutter work | N/A |
20 | Aluminum/Glazing work | N/A |
21 | Tiles Pointing work & Marble finishing work | N/A |
22 | Commode – Basin fitting work and C.P fittings work | N/A |
23 | Lift/Generator /Substation /Solar work | N/A |
24 | Boundary wall /Ground floor development work | N/A |
25 | Roof top finishing work | N/A |
26 | Roof top Gardening work | N/A |
16604