West Gate

Dhanmondi, Dhaka

Expected Completion Date

April 2026

Status Updated

February, 2026

SL. No Name of the work Progress details
01 Service pile 100%.
02 Grade beam 100%
03 Earth cutting 100%
04 Pile cap casting 100%
05 Supper structure 1.Ground Floor Column and Slab Casting 100% Complete.

2.1st Floor to 9th floor slab and column 100%.

3.Roof top parapet wall 100%

4.Roof top design wall100 %

5.Over head water tank 100%

6.lift machine room 100%

 

 

06

 

 

 

Panel work & Block Work 1st floor panel work 100%, 2nd floor panel work 85%, 3rd floor panel work 100%, 4rth floor panel work 100%, 5th  panel work 100%, 6th  panel work 100%,7th floor panel work 100%,8th floor panel work 100%,9th floor panel 100%,

Block work1st floor work 98%, 2nd floor 70%,3rd floor 100%,4rth floor 100%,5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%.

07 Electrical conducting work 1st floor 90%, 2nd Floor 80%, 3rd & 4rth floor vertical wearing 95%, 5th 95%, 6th floor 95%,7th floor 95%,8th floor 95%,9th floor 95%.
08 Door frame fitting work 2nd floor 80%,3rd floor 100%, 4rth floor 100%, 5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%,
09 Sanitary & plumbing line work (Ac drain water line,  vertical line) 2nd floor 70%,3rd floor 80%,4rth floor 80%,5th floor 80%,6th floor 80%,7th floor 90%,8th floor 90%,9th floor 90%,
10 In side Plastering work GF ceiling plaster 90%, 1st fllor 90%,2nd floor 95%,3rd floor 95%,4rth floor100%,5th floor100%,6th floor100%, 7th floor 100%, 8th floor 100%, 9th floor 100%.

1st floor wall plaster 80%,2nd floor 90%, 3rd floor 95%,4rth floor 95%,5th floor 95%,6th 90%,7th 95%,8th 95%,9th floor 95%.

 

 

 

10 Electrical cable wiring work Not Yet Started
11 Wall tiles work B4 80%,A5 80%, B5 80%, B6 80%, A7 90%, B7 90%, B8 80%,  A9 80%, B9 80%,
12 Common sanitary & Plumbing line work 20 % Completed
13 Outside plastering work 95% Completed
14 Floor tiles A4 80%, B4 80%, A5 90%, B5 90%, A7 80%, B7 80%, A8 80%, B8 80%, A9 80%, B9 80%.
14 L.C.C work 100%
15 Grill & Railing work 40%
16 Inside paint & Polishing work Not Yet Started
17 Switch -Socket fitting work Not Yet Started
18 Outside paint work Not Yet Started
19 Door shutter work Not Yet Started
20 Aluminum/Glazing work Not Yet Started
21 Tiles Pointing work & Marble finishing work Not Yet Started
22 Commode – Basin fitting work and C.P fittings work Not Yet Started
23 Lift/Generator /Substation /Solar work Not Yet Started
24 Boundary wall /Ground floor development work 50% Completed
25 Roof top finishing work  70% Completed
26 Roof top Gardening work 40% Completed

 