West Gate

Dhanmondi, Dhaka

Expected Completion Date

April 2026

Status Updated

June, 2025

SL. No Name of the work Progress details
01 Service pile 100%.
02 Grade beam 100%
03 Earth cutting 100%
04 Pile cap casting 100%
05 Supper structure 1.Ground Floor Column and Slab Casting 100% Complete.

2.1st Floor to 9th floor slab and column 100%.

3.Roof top parapet wall 85%

4.Roof top design wall 70%

5.Over head water tank 100%

6.lift machine room 70%

 

 

06

 

 

 

Panel work & Block Work 3rd floor panel work 85%, 4rth floor panel work 85%, 5th  panel work 70%, 6th  panel work 30%,

Block work 3rd floor 85%,4rth floor 85%,5th floor 85%,6th floor 85%,7th floor 85%,8th floor 85%,9th floor 85%.

07 Electrical conducting work 3rd & 4rth floor vertical wearing 65%, 5th 50%, 6th floor 40%,7th floor 40%,8th floor 35%,9th floor 30%.
08 Door frame fitting work N/A
09 Sanitary & plumbing line work (Ace drain water line,  vertical line) N/A
10 In side Plastering work GF ceiling plaster 60%, 2nd floor 80%,3rd floor 80%,4rth floor80%,5th floor80%,6th floor80%, 7th floor 80%, 8th floor 80%, 9th floor 80%.

 

 

 

10 Electrical cable wiring work N/A
11 Wall tiles work N/A
12 Common sanitary & Plumbing line work N/A
13 Outside plastering work N/A
14 Floor tiles N/A
14 L.C.C work N/A
15 Grill & Railing work N/A
16 Inside paint & Polishing work N/A
17 Switch -Socket fitting work N/A
18 Outside paint work N/A
19 Door shutter work N/A
20 Aluminum/Glazing work N/A
21 Tiles Pointing work & Marble finishing work N/A
22 Commode – Basin fitting work and C.P fittings work N/A
23 Lift/Generator /Substation /Solar work N/A
24 Boundary wall /Ground floor development work N/A
25 Roof top finishing work  N/A
26 Roof top Gardening work N/A

 