Expected Completion Date
April 2026
Status Updated
March, 2026
| SL. No | Name of the work | Progress details |
| 01 | Service pile | 100%. |
| 02 | Grade beam | 100% |
| 03 | Earth cutting | 100% |
| 04 | Pile cap casting | 100% |
| 05 | Supper structure | 1.Ground Floor Column and Slab Casting 100% Complete.
2.1st Floor to 9th floor slab and column 100%. 3.Roof top parapet wall 100% 4.Roof top design wall100 % 5.Over head water tank 100% 6.lift machine room 100% 7. Boundary wall 60%
|
| 06
|
Panel work & Block Work | 1st floor panel work 100%, 2nd floor panel work 100%, 3rd floor panel work 100%, 4rth floor panel work 100%, 5th panel work 100%, 6th panel work 100%,7th floor panel work 100%,8th floor panel work 100%,9th floor panel 100%,
Block work1st floor work 98%, 2nd floor 100%,3rd floor 100%,4rth floor 100%,5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%. |
| 07 | Electrical conducting work | 1st floor 85%, 2nd Floor 95%, 3rd & 4rth floor vertical wearing 95%, 5th 95%, 6th floor 95%,7th floor 95%,8th floor 95%,9th floor 95%. |
| 08 | Door frame fitting work | 2nd floor 100%,3rd floor 100%, 4rth floor 100%, 5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%, |
| 09 | Sanitary & plumbing line work (Ac drain water line, vertical line) | 2nd floor 70%,3rd floor 75%,4rth floor 85%,5th floor 85%,6th floor 85%,7th floor 85%,8th floor 85%,9th floor 85%, |
| 10 | In side Plastering work | GF ceiling plaster 95%, 1st fllor 95%,2nd floor 100%,3rd floor 100%,4rth floor100%,5th floor100%,6th floor100%, 7th floor 100%, 8th floor 100%, 9th floor 100%.
1st floor wall plaster 90%,2nd floor 90%, 3rd floor 98%,4rth floor 98%,5th floor 98%,6th 97%,7th 98%,8th 98%,9th floor 98%.
|
| 10 | Electrical cable wiring work | |
| 11 | Wall tiles work | B3 75%, A4 75%, B4 80%, A5 85%, B5 85%, B6 60%, A7 85%, B7 85%, A8 75%, B8 85%, A9 85%, B9 85%, & OHWT 100% |
| 12 | Common sanitary & Plumbing line work | 25% |
| 13 | Outside plastering work | 98% |
| 14 | Floor tiles | A3 85%,B3 85%,A4 90%, B4 90%, A5 90%,A6 85%, B5 90%, A7 90%, B7 90%, A8 90%, B8 90%, A9 90%, B9 90%. Mazanine 90%, OHWT 100%, & Stair 80% |
| 14 | L.C.C work | 100% |
| 15 | Grill & Railing work | 60% |
| 16 | Inside paint & Polishing work | N/A |
| 17 | Switch -Socket fitting work | N/A |
| 18 | Outside paint work | N/A |
| 19 | Door shutter work | N/A |
| 20 | Aluminum/Glazing work | N/A |
| 21 | Tiles Pointing work & Marble finishing work | N/A |
| 22 | Commode – Basin fitting work and C.P fittings work | N/A |
| 23 | Lift/Generator /Substation /Solar work | N/A |
| 24 | Boundary wall /Ground floor development work | 60%. |
| 25 | Roof top finishing work | 75% |
| 26 | Roof top Gardening work | 60% |