West Gate

Dhanmondi, Dhaka
Expected Completion Date July 2026
Status Updated April, 2026
Back to all projects
West Gate

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Service pile 100%.
02 Grade beam 100%
03 Earth cutting 100%
04 Pile cap casting 100%
05 Supper structure 1.Ground Floor Column and Slab Casting 100% Complete.

2.1st Floor to 9th floor slab and column 100%.

3.Roof top parapet wall 100%

4.Roof top design wall100 %

5.Over head water tank 100%

6.lift machine room 100%

7. Boundary wall 70%

 

06

 

 

 

Panel work & Block Work 1st floor panel work 100%, 2nd floor panel work 100%, 3rd floor panel work 100%, 4rth floor panel work 100%, 5th   panel work 100%, 6th  panel work 100%,7th floor panel work 100%,8th floor panel work 100%,9th floor panel 100%,

Block work1st floor work 100%, 2nd floor 100%,3rd floor 100%,4rth floor 100%,5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%.

07 Electrical conducting work 1st floor 85%, 2nd Floor 95%, 3rd & 4rth floor vertical wearing 95%, 5th 95%, 6th floor 95%,7th floor 95%,8th floor 95%,9th floor 95%.
08 Door frame fitting work 2nd floor 100%,3rd floor 100%, 4rth floor 100%, 5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%,
09 Sanitary & plumbing line work (Ac drain water line,  vertical line) 2nd floor 80%,3rd floor 85%,4rth floor 85%,5th floor 85%,6th floor 85%,7th floor 85%,8th floor 85%,9th floor 85%,
10 In side Plastering work GF ceiling plaster 95%, 1st fllor 95%,2nd floor 100%,3rd floor 100%,4rth floor100%,5th floor100%,6th floor100%, 7th floor 100%, 8th floor 100%, 9th floor 100%.

1st floor wall plaster 90%,2nd floor 90%, 3rd floor 98%,4rth floor 98%,5th floor 98%,6th 97%,7th 98%,8th 98%,9th floor 98%.

 

 

 

10 Electrical cable wiring work  
11 Wall tiles work B3 85%, A4 85%, B4 90%, A5 95%, B5 85%, B6 60%, A7 85%, B7 85%, A8 95%, B8 85%,  A9 85%, B9 85%, & OHWT 100%
12 Common sanitary & Plumbing line work 35%
13 Outside plastering work 98%
14 Floor tiles A3 85%,B3 85%,A4 90%, B4 90%, A5 90%,A6 85%, B5 90%, A7 90%, B7 90%, A8 90%, B8 90%, A9 90%, B9 90%. Mazanine 90%, OHWT 100%, & Stair 80%
14 L.C.C work 100%
15 Grill & Railing work 80%
16 Inside paint & Polishing work N/A
17 Switch -Socket fitting work N/A
18 Outside paint work N/A
19 Door shutter work N/A
20 Aluminum/Glazing work N/A
21 Tiles Pointing work & Marble finishing work N/A
22 Commode – Basin fitting work and C.P fittings work N/A
23 Lift/Generator /Substation /Solar work N/A
24 Boundary wall /Ground floor development work 70%.
25 Roof top finishing work  75%
26 Roof top Gardening work 60%