West Gate

Dhanmondi, Dhaka

Expected Completion Date

April 2026

Status Updated

March, 2026

SL. No Name of the work Progress details
01 Service pile 100%.
02 Grade beam 100%
03 Earth cutting 100%
04 Pile cap casting 100%
05 Supper structure 1.Ground Floor Column and Slab Casting 100% Complete.

2.1st Floor to 9th floor slab and column 100%.

3.Roof top parapet wall 100%

4.Roof top design wall100 %

5.Over head water tank 100%

6.lift machine room 100%

7. Boundary wall 60%

 

06

 

 

 

Panel work & Block Work 1st floor panel work 100%, 2nd floor panel work 100%, 3rd floor panel work 100%, 4rth floor panel work 100%, 5th   panel work 100%, 6th  panel work 100%,7th floor panel work 100%,8th floor panel work 100%,9th floor panel 100%,

Block work1st floor work 98%, 2nd floor 100%,3rd floor 100%,4rth floor 100%,5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%.

07 Electrical conducting work 1st floor 85%, 2nd Floor 95%, 3rd & 4rth floor vertical wearing 95%, 5th 95%, 6th floor 95%,7th floor 95%,8th floor 95%,9th floor 95%.
08 Door frame fitting work 2nd floor 100%,3rd floor 100%, 4rth floor 100%, 5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%,
09 Sanitary & plumbing line work (Ac drain water line,  vertical line) 2nd floor 70%,3rd floor 75%,4rth floor 85%,5th floor 85%,6th floor 85%,7th floor 85%,8th floor 85%,9th floor 85%,
10 In side Plastering work GF ceiling plaster 95%, 1st fllor 95%,2nd floor 100%,3rd floor 100%,4rth floor100%,5th floor100%,6th floor100%, 7th floor 100%, 8th floor 100%, 9th floor 100%.

1st floor wall plaster 90%,2nd floor 90%, 3rd floor 98%,4rth floor 98%,5th floor 98%,6th 97%,7th 98%,8th 98%,9th floor 98%.

 

 

 

10 Electrical cable wiring work  
11 Wall tiles work B3 75%, A4 75%, B4 80%, A5 85%, B5 85%, B6 60%, A7 85%, B7 85%, A8 75%, B8 85%,  A9 85%, B9 85%, & OHWT 100%
12 Common sanitary & Plumbing line work 25%
13 Outside plastering work 98%
14 Floor tiles A3 85%,B3 85%,A4 90%, B4 90%, A5 90%,A6 85%, B5 90%, A7 90%, B7 90%, A8 90%, B8 90%, A9 90%, B9 90%. Mazanine 90%, OHWT 100%, & Stair 80%
14 L.C.C work 100%
15 Grill & Railing work 60%
16 Inside paint & Polishing work N/A
17 Switch -Socket fitting work N/A
18 Outside paint work N/A
19 Door shutter work N/A
20 Aluminum/Glazing work N/A
21 Tiles Pointing work & Marble finishing work N/A
22 Commode – Basin fitting work and C.P fittings work N/A
23 Lift/Generator /Substation /Solar work N/A
24 Boundary wall /Ground floor development work 60%.
25 Roof top finishing work  75%
26 Roof top Gardening work 60%