Expected Completion Date
April 2026
Status Updated
June, 2025
SL. No | Name of the work | Progress details |
01 | Service pile | 100%. |
02 | Grade beam | 100% |
03 | Earth cutting | 100% |
04 | Pile cap casting | 100% |
05 | Supper structure | 1.Ground Floor Column and Slab Casting 100% Complete.
2.1st Floor to 9th floor slab and column 100%. 3.Roof top parapet wall 85% 4.Roof top design wall 70% 5.Over head water tank 100% 6.lift machine room 70%
|
06
|
Panel work & Block Work | 3rd floor panel work 85%, 4rth floor panel work 85%, 5th panel work 70%, 6th panel work 30%,
Block work 3rd floor 85%,4rth floor 85%,5th floor 85%,6th floor 85%,7th floor 85%,8th floor 85%,9th floor 85%. |
07 | Electrical conducting work | 3rd & 4rth floor vertical wearing 65%, 5th 50%, 6th floor 40%,7th floor 40%,8th floor 35%,9th floor 30%. |
08 | Door frame fitting work | N/A |
09 | Sanitary & plumbing line work (Ace drain water line, vertical line) | N/A |
10 | In side Plastering work | GF ceiling plaster 60%, 2nd floor 80%,3rd floor 80%,4rth floor80%,5th floor80%,6th floor80%, 7th floor 80%, 8th floor 80%, 9th floor 80%.
|
10 | Electrical cable wiring work | N/A |
11 | Wall tiles work | N/A |
12 | Common sanitary & Plumbing line work | N/A |
13 | Outside plastering work | N/A |
14 | Floor tiles | N/A |
14 | L.C.C work | N/A |
15 | Grill & Railing work | N/A |
16 | Inside paint & Polishing work | N/A |
17 | Switch -Socket fitting work | N/A |
18 | Outside paint work | N/A |
19 | Door shutter work | N/A |
20 | Aluminum/Glazing work | N/A |
21 | Tiles Pointing work & Marble finishing work | N/A |
22 | Commode – Basin fitting work and C.P fittings work | N/A |
23 | Lift/Generator /Substation /Solar work | N/A |
24 | Boundary wall /Ground floor development work | N/A |
25 | Roof top finishing work | N/A |
26 | Roof top Gardening work | N/A |