Winsome Home

Bashundhara R/A, Dhaka

Completion Date

December 2024

Status Updated

September, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work A-1=100%,B-1=100%A-2=100%,B-2=100%,A-3=100%, B-3=100%,A-4=100%,B-4=100%A-5=100%,B-5=100%A-6=100%,     B-6=100%,A-7=100%, B-7=100%,G.F=98%,Roof=100%
  Electrical  conduit work A-1=100%,B-1=100%A-2=100%,B-2=100%, A-3=100%, B-3=100%,A-4=100%, B-4=100%A-5=100%,B-5=100%A-6=100%, B-6=100%,A-7=100%, B-7=100%,%,G.F=98%,Roof=95%
  Door frame fitting work A-1=100%,B-1=100%A-2=100%,              B-2=100%,A-3=100%, B-3=100%,                   A-4=100%,B-4=100%A-5=100%,                        B-5=100%A-6=100%,B-6=100%,                           A-7=100%, B-7=100%,%,G.F=100%,Roof=100%
  Sanitary & plumbing line  work A-1=98%,B-1=98%A-2=97%,                               B-2=98%,A-3=97%, B-3=98%,                   A-4=98%,B-4=98%A-5=98%,                        B-5=98%A-6=98%,B-6=98%,                           A-7=98%, B-7=98%,%,G.F=96%,Roof=100%
  In side Plastering work A-1=98%,B-1=98%A-2=98%,B-2=98%,    A-3=98%, B-3=98%,A-4=98%                   B-4=98%A-5=98%,B-5=98%A-6=98%,     B-6=98%,A-7=98%, B-7=98%,%,G.F=98%,Roof=99%
  Electrical cable wiring work A-1=99%,B-1=99%,B-2=99%, A-3=99%, B-3=99%,A-4=99%,B-4=99%A-5=99%,              B-5=99%,A-6=99%, B-6=99%, A-7=99%, B-7=99%,
  Wall tiles  work A-1=99%,B-1=99%A-2=99%,B-2=99%,    A-3=99%, B-3=99%,A-4=99%                   B-4=99%A-5=99%,B-5=99%A-6=99%,     B-6=99%,A-7=99%, B-7=99%,%,G.F=97%,Roof=99%
  Common sanitary & Plumbing line work 100%
  Outside plastering work 95%
  Floor tiles/Marble work A-1=99%, B-1=99%, B-2=99%, A-3=99%, B-3=99%,A-4=99%,B-4=99%A-5=99%,             B-5=99%A-6=99%,B-6=99%,A-7=99%,   B-7=99%,
  L.C.C work 100%
  Grill & Railing work A-1=100%,B-1=100%A-2=100%,              B-2=100%,A-3=100%, B-3=100%,                   A-4=100%,B-4=100%A-5=100%,                        B-5=100%A-6=100%,B-6=100%,                           A-7=100%, B-7=100%,%,G.F=96%,Roof=100%
  Inside paint & Polishing work 30%
  Switch -Socket fitting work 90%
  Outside paint work 75%
  Door shutter work 99%
  Aluminum/Glazing work 85%
  Tiles Pointing work & Marble finishing work 75%
  Commode – Basin fitting work and C.P fittings work 10%
  Lift/Generator /Substation /Solar work 85%
  Boundary wall /Ground floor development work 96%
  Roof top finishing work 65%
  Roof top Gardening work 82%