Expected Completion Date
September 2025
Status Updated
July, 2025
SL. No | Name of the work | Progress details |
1 | Foundation work | 100% completed |
2 | Basement work | N/A |
3 | Super Structure work | 100% completed |
4 | Block Work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
5 | Electrical conduiting work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
6 | Door frame fitting work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
7 | Sanitary & plumbing line work | 95% Completed. |
8 | Inside Plastering work | A1-95%, A2-95%, A3-95%, A4-95%, A5-95%, A6-95%, A7-95%, A8-95% Completed. |
9 | Electrical cable wiring work | 95% Completed. |
10 | Wall tiles work | A1-95%, A2-70%, A3-95%, A4-95%, A5-95%, A6-95%, A7-95%, A8-95% Completed. |
11 | Common sanitary & Plumbing line work | 50% Completed |
12 | Outside plastering work | 100% Completed |
13 | Floor tiles/Marble work | A1-90%, A2-70%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
14 | L.C.C work | 85% completed. |
15 | Grill & Railing work | 90% Completed. |
16 | Inside paint & Polishing work | |
17 | Switch -Socket fitting work | |
18 | Outside paint work | |
19 | Door shutter work | |
20 | Aluminum work | 15% completed. |
21 | Tiles Pointing work & Marble finishing work | |
22 | Commode – Basin fitting work and C.P fittings work | |
23 | Lift/Generator /Substation /Solar work | 20% completed. |
24 | Boundary wall /Ground floor development work | 10% completed |
25 | Roof top finishing work | 24% completed |
26 | Roof top Gardening work G.F Garden work | |
27 | Land escape /Logo work |