Wood Green

Uttara, Dhaka

Expected Completion Date

June 2025

Status Updated

March, 2025

SL. No Name of the work Progress details
1 Foundation work 100% completed
2 Basement work N/A
3 Super Structure work 100% completed
4 Block Work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed.
5 Electrical conduiting work A1-100%, A2-90%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed.
6 Door frame fitting work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed.
7 Sanitary & plumbing line work 70% Completed.
8 Inside Plastering work A1-85%, A2-85%, A3-85%, A4-85%, A5-85%, A6-85%, A7-85%, A8-85% Completed.
9 Electrical cable wiring work 80% Completed.
10 Wall tiles work A1-60%, A3-80%, A4-80%, A5-80%, A6-80%, A7-80%, A8-50% Completed.
11 Common sanitary & Plumbing line work NYS
12 Outside plastering work 90% Completed
13 Floor tiles/Marble work A1-30%, A3-50%, A4-50%, A5-50%, A6-50%, A7-50% Completed.
14 L.C.C work  
15 Grill & Railing work 50% Completed.
16 Inside paint & Polishing work Not Yet Started.
17 Switch -Socket fitting work Not Yet Started.
18 Outside paint work Not Yet Started.
19 Door shutter work Not Yet Started.
20 Aluminum work Not Yet Started.
21 Tiles Pointing work & Marble finishing work Not Yet Started.
22 Commode – Basin fitting work and C.P fittings work Not Yet Started.
23 Lift/Generator /Substation /Solar work Not Yet Started.
24 Boundary wall /Ground floor development work Not Yet Started.
25 Roof top finishing work Not Yet Started.
26 Roof top Gardening work G.F Garden work Not Yet Started.
27 Land escape /Logo work Not Yet Started.