Expected Completion Date
September 2025
Status Updated
September, 2025
| SL. No | Name of the work | Progress details |
| 1 | Foundation work | 100% completed |
| 2 | Basement work | N/A |
| 3 | Super Structure work | 100% completed |
| 4 | Block Work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
| 5 | Electrical conduiting work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
| 6 | Door frame fitting work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
| 7 | Sanitary & plumbing line work | 95% Completed. |
| 8 | Inside Plastering work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
| 9 | Electrical cable wiring work | 98% Completed. |
| 10 | Wall tiles work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
| 11 | Common sanitary & Plumbing line work | 80% Completed |
| 12 | Outside plastering work | 100% Completed |
| 13 | Floor tiles/Marble work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
| 14 | L.C.C work | 100% Completed |
| 15 | Grill & Railing work | 98% Completed. |
| 16 | Inside paint & Polishing work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
| 17 | Switch -Socket fitting work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
| 18 | Outside paint work | 10% completed |
| 19 | Door shutter work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
| 20 | Aluminum work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
| 21 | Tiles Pointing work & Marble finishing work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
| 22 | Commode – Basin fitting work and C.P fittings work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed. |
| 23 | Lift/Generator /Substation /Solar work | 65% completed |
| 24 | Boundary wall /Ground floor development work | 70% Completed |
| 25 | Roof top finishing work | 70% Completed |
| 26 | Roof top Gardening work G.F Garden work | Not Yet Started |
| 27 | Land escape /Logo work | Not Yet Started |