Wood Green

Uttara, Dhaka

Expected Completion Date

September 2025

Status Updated

October, 2025

SL. No Name of the work Progress details
1 Foundation work 100% completed
2 Basement work N/A
3 Super Structure work 100% completed
4 Block Work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed.
5 Electrical conduiting work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed.
6 Door frame fitting work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed.
7 Sanitary & plumbing line work 100% Completed.
8 Inside Plastering work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed.
9 Electrical cable wiring work 100% Completed.
10 Wall tiles work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed.
11 Common sanitary & Plumbing line work 100% Completed
12 Outside plastering work 100% Completed
13 Floor tiles/Marble work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed.
14 L.C.C work 100% Completed
15 Grill & Railing work 100% Completed.
16 Inside paint & Polishing work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed.
17 Switch -Socket fitting work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed.
18 Outside paint work 90% completed
19 Door shutter work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed.
20 Aluminum work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed.
21 Tiles Pointing work & Marble finishing work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed.
22 Commode – Basin fitting work and C.P fittings work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-100% Completed.
23 Lift/Generator /Substation /Solar work 95% completed
24 Boundary wall /Ground floor development work 98% Completed
25 Roof top finishing work 98% Completed
26 Roof top Gardening work G.F Garden work 80% Completed
27 Land escape /Logo work 80% Completed