Wood Green

Uttara, Dhaka

Expected Completion Date

June 2025

Status Updated

January, 2025

SL. No Name of the work Progress details
1 Foundation work 100% completed
2 Basement work N/A
3 Super Structure work 100% completed
4 Block Work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-92%, A7-92%, A8-92% Completed.
5 Electrical conduiting work A1-100%, A2-90%, A3-100%, A4-100%, A5-100%, A6-100%, A7-90%, A8-90% Completed.
6 Door frame fitting work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100%, A8-50% Completed.
7 Sanitary & plumbing line work 50% Completed.
8 Inside Plastering work A1-85%, A2-85%, A3-85%, A4-85%, A5-85%, A6-85%, A7-85%, A8-50% Completed.
9 Electrical cable wiring work 60% Completed.
10 Wall tiles work A1-60% Completed.
11 Common sanitary & Plumbing line work NYS
12 Outside plastering work 80% Completed
13 Floor tiles/Marble work  
14 L.C.C work  
15 Grill & Railing work 05% Completed.
16 Inside paint & Polishing work  
17 Switch -Socket fitting work  
18 Outside paint work  
19 Door shutter work  
20 Aluminum work  
21 Tiles Pointing work & Marble finishing work  
22 Commode – Basin fitting work and C.P fittings work  
23 Lift/Generator /Substation /Solar work  
24 Boundary wall /Ground floor development work  
25 Roof top finishing work  
26 Roof top Gardening work G.F Garden work  
27 Land escape /Logo work  