Expected Completion Date
June 2025
Status Updated
December, 2024
SL. No | Name of the work | Progress details |
1 | Foundation work | 100% completed |
2 | Basement work | N/A |
3 | Super Structure work | 100% completed |
4 | Block Work | A1-94%, A2-94%, A3-94%, A4-94%, A5-92%, A6-92%, A7-92%, A8-92% Completed. |
5 | Electrical conduiting work | A1-90%, A2-90%, A3-100%, A4-100%, A5-100%, A6-100%, A7-90%, A8-80% Completed. |
6 | Door frame fitting work | A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-100%, A7-100% Completed A8-NYS. |
7 | Sanitary & plumbing line work | 30% Completed. |
8 | Inside Plastering work | A1-85%, A2-85%, A3-85%, A4-85%, A5-85%, A6-85%, A7-85% Completed A8-NYS. |
9 | Electrical cable wiring work | 50% Completed. |
10 | Wall tiles work | NYS |
11 | Common sanitary & Plumbing line work | NYS |
12 | Outside plastering work | 60% Completed |
13 | Floor tiles/Marble work | |
14 | L.C.C work | |
15 | Grill & Railing work | |
16 | Inside paint & Polishing work | |
17 | Switch -Socket fitting work | |
18 | Outside paint work | |
19 | Door shutter work | |
20 | Aluminum work | |
21 | Tiles Pointing work & Marble finishing work | |
22 | Commode – Basin fitting work and C.P fittings work | |
23 | Lift/Generator /Substation /Solar work | |
24 | Boundary wall /Ground floor development work | |
25 | Roof top finishing work | |
26 | Roof top Gardening work G.F Garden work | |
27 | Land escape /Logo work |