Wood Green

Uttara, Dhaka

Completion Date

June 2025

Status Updated

September, 2024

SL. No Name of the work Progress details
1 Foundation work 100% completed
2 Basement work N/A
3 Super Structure work 98% completed. (Roof slab casting completed).
4 Block Work A1-92%, A2-92%, A3-92%, A4-92%, A5-92%, A6-92%, A7-92% Completed A8-NYS.
5 Electrical conduiting work A1-90%, A2-90%, A3-90%, A4-90%, A5-90%, A6-90%, A7-90% Completed A8-NYS.
6 Door frame fitting work A1-100%, A2-100%, A3-100%, A4-100%, A5-100%, A6-72%, A7-72% Completed A8-NYS.
7 Sanitary & plumbing line work NYS
8 Inside Plastering work A1-85%, A2-85%, A3-85%, A4-85%, A5-85%, A6-85%, A7-80% Completed A8-NYS.
9 Electrical cable wiring work NYS
10 Wall tiles work NYS
11 Common sanitary & Plumbing line work NYS
12 Outside plastering work  
13 Floor tiles/Marble work  
14 L.C.C work  
15 Grill & Railing work  
16 Inside paint & Polishing work  
17 Switch -Socket fitting work  
18 Outside paint work  
19 Door shutter work  
20 Aluminum work  
21 Tiles Pointing work & Marble finishing work  
22 Commode – Basin fitting work and C.P fittings work  
23 Lift/Generator /Substation /Solar work  
24 Boundary wall /Ground floor development work  
25 Roof top finishing work  
26 Roof top Gardening work G.F Garden work  
27 Land escape /Logo work  