Completion Date
November 2024
Status Updated
March, 2024
SL. No | Name of the work | Progress details |
1 | Supper structure | 13th floor roof slab 100%. Roof top- OHWT 100%, Parapet 100%, swimming pool 100%. |
2 | Ceiling plaster | 2nd floor 100%, 3rd floor 100%, 4th floor 100%, 5th floor 100%, 6th floor 100%, 7th floor 100%. 8th floor 100 %. 9th floor 100%. 10th floor 100%. 11 th floor 100%, 12 th floor 100%, 13 th floor 30%. |
3 | Block work | A2- 100%,B-2 100 %,C2-100%, A3-100%.B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-100%. A8 100%, B8 100% C8 100%. A9 100%,B9 100%,C9 100%.A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100% C13- 100%. |
Internal Wall plaster | A2 90%, B2- 90%, C2-90%, A3- 90%, B3-90%, C3-90%, A4-90%, B4-90%, C4-90%, A5-90%. B5 90%, C5 90%. A6-90%, B6-90%, C6-90%, A7-90%, B7- 90 %, C7-90%, A8-90%, B8-90%, C8-90%, A9 -95%, B9 95%, C9 – 95%, A10 – 95%, B10 – 95%, C 10 95%, A11 – 95%, B-11 – 95%, C-11 – 95%, A-12 – 70%, B-12 – 70%, C-12 – 90%. | |
4 | Electrical conducting work | A2- 90%,B-2 90 %,C2-100%, A3-90%, B3- 90%, C3-90%, A4- 90%, B4- 90%, C4- 90%, C4-90%,A5-90%. B5 90%, C5 90%. A6-90%, B6-90%, C6-90%, A7-90%, B7- 90 %, C7-90%, A8-70%, B8-70%, C8-70%, A9 -95%, B9 95%, C9 – 95%, A10 – 95%, B10 – 95%, C 10 95%, A11 – 95%, B-11 – 95%, C-11 – 95%, A-12 – 70%, B-12 – 70%, C-12 – 90%. |
5 | Door frame fitting work | C2-80%, A3-80%.B3- 80%, C3-80%, A4- 70%, B4- 7%, C4- 70%, C4-70%, A5-70%. B5 70%, C5 70%. A6-90%< B6-90%, C6-90%, A7-90%, B7- 90 %, C7-90%, A8-70%, B8-70%, C8-70%, A8 80%, B8 80%, C8 80%, A9 80%, B9 80%, C9 80%, A10 80%, B10 80 %, C10- 80%, A11 – 80%, B-11 – 80%, C-11 – 80%, A-12 – 80%, B-12 – 80%, C-12 – 80%. |
6 | Sanitary & plumbing line work (AC drain water line, ver – vertical line) | 30% |
8 | Electrical cable wiring work | A4- 90%, B4- 90%, C4- 90%, C6-90%, C-8 – 90% |
9 | Wall tiles work | B3- 50%, C3-50%, A-7 – 50%, A-9 – 50%, B-9 – 50%, C-9 – 50% |
10 | Common sanitary & Plumbing line work | 30% |
Outside plastering work | 80% | |
Floor tiles/Marble work | ||
L.C.C work | ||
Grill & Railing work | ||
Inside paint & Polishing work | ||
Switch -Socket fitting work | ||
Outside paint work | ||
Door shutter work | ||
Aluminum/Glazing work | ||
Tiles Pointing work & Marble finishing work | ||
Commode – Basin fitting work and C.P fittings work |
|
|
Lift/Generator /Substation /Solar work | ||
Boundary wall /Ground floor development work | ||
Roof top finishing work | ||
Roof top Gardening work |
16604