Blue Sky Homes

Bashundhara R/A, Dhaka

Completion Date

June 2024

Status Updated

March, 2024

SL. No Name of the work Progress details
01 Foundation work 100% completed.
02 Super Structure work 100% Completed
03 Block Work A-1 to A-9 = 100 %, completed
04 Electrical conducting work A-1 to A-9 = 100 %, completed
05 Door frame fitting work A-1 to A-9 = 100 %, completed
06 Sanitary & plumbing line work A-1 to A-9 = 100 %, completed
07 In side Plastering work A-1 to A-9 = 100 %, completed
08 Electrical cable wiring work A-1 to A-9 = 100 %, completed
09 Wall tiles work A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
10 Common sanitary & Plumbing line work 80 % completed.
11 Outside plastering work 100% completed.
12 Floor tiles/Marble work A-1 = 100% , A-2= 95%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
13 L.C.C work 100% completed
14 Grill & Railing work A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
15 Inside paint & Polishing work 50% completed
16 Switch -Socket fitting work N/A
17 Outside paint work 50% completed
18 Door shutter work 50% completed
19 Aluminum work 60% completed
20 Tiles Pointing work & Marble finishing work 0% completed
21 Commode – Basin fitting work and C.P fittings work 0% completed
22 Lift/Generator /Substation /Solar work 20% completed
23 Boundary wall /Ground floor development work 80% completed.
24 Roof top finishing work 70% completed.
25 Roof top Gardening work G.F Garden work 50% completed.

16604