Cosmopolis

Mirpur, Dhaka

Completion Date

September 2026

Status Updated

September, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 91% completed
  Block work T-1,2,3&4,A-Type=58%,B-Type=58% C-Type=58%,D-Type=58%,
  Electrical  conduit work T-3&4,A-Type=40%,B-Type=40%,C-Type=40%,D-Type=40%,

T-1,2 Type (A)= 20%, B-Type= 20%,

C-Type=20%,

  Door frame fitting work 22%
  Sanitary & plumbing line  work 22%
  In side Plastering work 15%
  Electrical cable wiring work N/A
  Wall tiles  work N/A
  Common Area sanitary & Plumbing line work N/A
  Outside plastering work N/A
  Floor tiles/Marble work N/A
  L.C.C work N/A
  Grill & Railing work N/A
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work N/A
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work N/A
  Roof top finishing work N/A
  Roof top Gardening work N/A

 