Dulce Domi

Uttara, Dhaka

Completion Date

July 2025

Status Updated

September, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 98% completed
  Block work A-1=100%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%.
  Electrical  conduit work A-1=100%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%.
  Door frame fitting work A-1=100%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%
  Sanitary & plumbing line  work A-1=80%,A-2=80%,A-3=80%,A-4=80%,A-5=80%,A-6=80%,A-7=80%,A-8=80%,A-9=80%.
  In side Plastering work A-1=80%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%.
  Electrical cable wiring work A-1=100%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%.
  Wall tiles  work A-1=90%,A-2=90%,A-3=90%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%.
  Common sanitary & Plumbing line work 15%
  Outside plastering work 95%
  Floor tiles/Marble work 90%
  L.C.C work 100%
  Grill & Railing work 90%
  Inside paint & Polishing work 40%
  Switch -Socket fitting work N/A
  Outside paint work 10%
  Door shutter work 60%
  Aluminum/Glazing work 60%
  Tiles Pointing work & Marble finishing work 15%
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work 80%
  Boundary wall /Ground floor development work 80%
  Roof top finishing work 90%
  Roof top Gardening work 80%