Completion Date
January 2025
Status Updated
March, 2024
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 95% completed | |
Block work | A-1=100%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%. | |
Electrical conduit work | A-1=90%,A-2=90%,A-3=90%,A-4=90%,A-5=90%,A-6=90%,A-7=100%,A-8=100%,A-9=90%. | |
Door frame fitting work | A-1=100%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100% | |
Sanitary & plumbing line work | A-1=80%,A-2=80%,A-3=80%,A-4=80%,A-5=80%,A-6=80%,A-7=80%,A-8=80%,A-9=60%. | |
In side Plastering work | A-1=80%,A-2=80%,A-3=80%,A-4=80%,A-5=80%,A-6=80%,A-7=90%,A-8=90%,A-9=80%. | |
Electrical cable wiring work | A-1=20%,A-2=20%,A-3=60%,A-4=70%,A-5=100%,A-6=90%,A-7=100%,A-8=100%,A-9=80%. | |
Wall tiles work | A-1=60%,A-2=60%,A-3=80%,A-4=80%,A-5=80%,A-6=80%,A-7=90%,A-8=90%,A-9=60%. | |
Common sanitary & Plumbing line work | N/A | |
Outside plastering work | 75% | |
Floor tiles/Marble work | 50% | |
L.C.C work | N/A | |
Grill & Railing work | 40% | |
Inside paint & Polishing work | N/A | |
Switch -Socket fitting work | N/A | |
Outside paint work | N/A | |
Door shutter work | N/A | |
Aluminum/Glazing work | N/A | |
Tiles Pointing work & Marble finishing work | N/A | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | N/A | |
Boundary wall /Ground floor development work | N/Asss | |
Roof top finishing work | 50% | |
Roof top Gardening work | 50% |