Completion Date
July 2025
Status Updated
September, 2024
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 98% completed | |
Block work | A-1=100%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%. | |
Electrical conduit work | A-1=100%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%. | |
Door frame fitting work | A-1=100%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100% | |
Sanitary & plumbing line work | A-1=80%,A-2=80%,A-3=80%,A-4=80%,A-5=80%,A-6=80%,A-7=80%,A-8=80%,A-9=80%. | |
In side Plastering work | A-1=80%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%. | |
Electrical cable wiring work | A-1=100%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%. | |
Wall tiles work | A-1=90%,A-2=90%,A-3=90%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%. | |
Common sanitary & Plumbing line work | 15% | |
Outside plastering work | 95% | |
Floor tiles/Marble work | 90% | |
L.C.C work | 100% | |
Grill & Railing work | 90% | |
Inside paint & Polishing work | 40% | |
Switch -Socket fitting work | N/A | |
Outside paint work | 10% | |
Door shutter work | 60% | |
Aluminum/Glazing work | 60% | |
Tiles Pointing work & Marble finishing work | 15% | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | 80% | |
Boundary wall /Ground floor development work | 80% | |
Roof top finishing work | 90% | |
Roof top Gardening work | 80% |