Finesse

Bashundhara R/A, Dhaka

Completion Date

June 2024

Status Updated

August, 2024

SL. No Name of the work Progress details
01 Foundation work 100% completed.
02 Super Structure work 100% completed.
03 Block Work 95% completed.
04 Electrical conducting work 80 % completed.
05 Door frame fitting work 90% completed.
06 Sanitary & plumbing line work 70 % completed.
07 In side Plastering work 90 % completed.
08 Electrical cable wiring work 40 % completed.
09 Wall tiles work 80 % completed.
10 Common sanitary & Plumbing line work 0 % completed.
11 Outside plastering work 40% completed.
12 Floor tiles/Marble work 70 % completed
13 L.C.C work 0% completed
14 Grill & Railing work 0% completed
15 Inside paint & Polishing work 0% completed
16 Switch -Socket fitting work N/A
17 Outside paint work 0% completed
18 Door shutter work 0% completed
19 Aluminum work 0% completed
20 Tiles Pointing work & Marble finishing work 0% completed
21 Commode – Basin fitting work and C.P fittings work 0% completed
22 Lift/Generator /Substation /Solar work 0% completed
23 Boundary wall /Ground floor development work 0% completed.
24 Roof top finishing work 0% completed.
25 Roof top Gardening work G.F Garden work 0% completed.

 

16604