Finesse

Bashundhara R/A, Dhaka

Completion Date

May 2024

Status Updated

March, 2024

SL. No Name of the work Progress details
01 Foundation work 100% completed.
02 Super Structure work 100% completed.
03 Block Work A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
04 Electrical conducting work A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
05 Door frame fitting work A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
06 Sanitary & plumbing line work A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
07 In side Plastering work A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
08 Electrical cable wiring work A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
09 Wall tiles work A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
10 Common sanitary & Plumbing line work 80 % completed.
11 Outside plastering work 100% completed.
12 Floor tiles/Marble work A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
13 L.C.C work 100% completed
14 Grill & Railing work A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
15 Inside paint & Polishing work A-2= 50%, A3 = 50%, A-4 = 50%, A5 = 50%, A-6 = 50%, A-7= 50%, A-8= 50%, A-9= 50%,
16 Switch -Socket fitting work N/A
17 Outside paint work 50% completed
18 Door shutter work 30% completed
19 Aluminum work 60% completed
20 Tiles Pointing work & Marble finishing work 0% completed
21 Commode – Basin fitting work and C.P fittings work 0% completed
22 Lift/Generator /Substation /Solar work 30% completed
23 Boundary wall /Ground floor development work 80% completed.
24 Roof top finishing work 80% completed.
25 Roof top Gardening work G.F Garden work 0% completed.