New Horizon

Purana Paltan, Dhaka

Completion Date

December 2024

Status Updated

September, 2024

SL. No Name of the work Progress details

(September’24)

        Remarks
01 Foundation work 100% completed.  
02 Super Structure work 100% completed.  
03 Block Work Basement=100%

G. F.=60%

A1= 100%, A2= 100%,

A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%,

Roof= 100%

 
04 Electrical Conducting work Basement=60%

G. F=50%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%,

Roof = 100%

 
05 Door frame fitting work Basement=100%

G. F=100%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%

 
06 Sanitary & plumbing line work Basement=20%

G. F=30%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=70%, B5=70%,

A6=75%, B6=70%,

A7=70%, B7=70%,

A8=70%, B8=70%,

 

 
07 In side Plastering work Basement=80%

G. F=20%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=90%, B5=90%,

A6=90%, B6=90%,

A7=90%, B7=90%,

A8=90%, B8=90%,

 
08  

 

Electrical cable wiring work

Basement=60%

G, F=30%

A1= 25%, A2= 25%, A3= 25%, A4= 25%,

A5=60%, B5=60%,

A6=60%, B6=60%,

A7=0%, B7=0%,

A8=0%, B8=0%,

 
09 Wall Tiles work Basement=0%

GF=0%

A1= 80%, A2= 80%, A3= 80%, A4= 80%,

A5=60%, B5=60%,

A6=50%, B6=50%,

A7=0%, B7=50%,

A8=50%, B8=10%,

 
10 Common sanitary & Plumbing line work Basement=20%

G, F=30%

A1= 80%, A2= 80%, A3= 80%, A4= 80%,

A5=60%, B5=60%,

A6=60%, B6=60%,

A7=60%, B7=60%,

A8=60%, B8=60%,

 
11 Outside plastering work 95% Completed  
12 Floor tiles/Marble work Basement=0%

GF=0%

A1= 90%, A2= 90%, A3= 90%, A4= 90%,

A5=80%, B5=50%,

A6=80%, B6=80%,

A7=80%, B7=80%,

A8=80%, B8=80%,

 
13 L.C.C work 5% Completed  
14 Grill & Railing work 90 % Completed  
15 Inside paint & Polishing work 35 % Completed  
16 Switch -Socket fitting work 5 % Completed  
17 Outside paint work    
18 Door shutter work    
19 Aluminum work 20 % Completeds  
20 Tiles Pointing work & Marble finishing work    
21 Commode – Basin fitting work and C.P fittings work    
22 Lift/Generator /Substation /Solar work 75% Completed  
23 Boundary wall /Ground floor development work 65% Completed  
24 Roof top finishing work 80% Completed  
25 Roof top Gardening work G.F Garden work 25% Completed  