Expected Completion Date
May 2025
Status Updated
June, 2025
SL. No | Name of the work | Progress details | Remark |
01 | Foundation work | 100% completed. | |
02 | Super Structure work | 100% completed. | |
03 |
Block Work |
Basement=100%
G. F.=60% A1= 100%, A2= 100%, A3= 100%, A4= 100%, A5=100%, B5=100%, A6=100%, B6=100%, A7=100%, B7=100%, A8=100%, B8=100%, Roof= 100% |
|
04 |
Electrical Conducting work |
Basement=60%
G. F=50% A1= 100%, A2= 100%, A3= 100%, A4= 100%, A5=100%, B5=100%, A6=100%, B6=100%, A7=100%, B7=100%, A8=100%, B8=100%, Roof = 100% |
|
05 |
Door frame fitting work |
Basement=100%
G. F=100% A1= 100%, A2= 100%, A3= 100%, A4= 100%, A5=100%, B5=100%, A6=100%, B6=100%, A7=100%, B7=100%, A8=100%, B8=100% |
|
06 |
Sanitary & plumbing line work |
Basement=100%
G. F=100% A1= 100%, A2= 100%, A3= 100%, A4= 100%, A5=100%, B5=100%, A6=100%, B6=100%, A7=100%, B7=100%, A8=100%, B8=100%,
|
|
07 |
In side Plastering work |
Basement=100%
G. F=100% A1= 100%, A2= 100%, A3= 100%, A4= 100%, A5=100%, B5=100%, A6=100%, B6=100%, A7=100%, B7=100%, A8=100%, B8=100%, |
|
08 |
Electrical cable wiring work |
Basement=100%
G. F=100% A1= 100%, A2= 100%, A3= 100%, A4= 100%, A5=100%, B5=100%, A6=100%, B6=100%, A7=100%, B7=100%, A8=100%, B8=100% |
|
09 |
Wall Tiles work |
Basement=100%
G. F=100% A1= 100%, A2= 100%, A3= 100%, A4= 100%, A5=100%, B5=100%, A6=100%, B6=100%, A7=100%, B7=100%, A8=100%, B8=100% |
|
10 |
Common sanitary & Plumbing line work |
Basement=100%
G, F=100% A1= 1000%, A2= 100%, A3= 100%, A4= 100%, A5=100%, B5=100%, A6=100%, B6=100%, A7=100%, B7=100%, A8=100%, B8=100%, |
|
11 | Outside plastering work | 100% Completed | |
12 |
Floor tiles/Marble work |
Basement=100%
G, F=100% A1= 100%, A2= 100%, A3= 90%, A4= 100%, A5=100%, B5=100%, A6=100%, B6=100%, A7=100%, B7=100%, A8=100%, B8=100%, |
|
13 | L.C.C work | 100% Completed | |
14 | Grill & Railing work
|
100% Completed | |
15 | Inside paint &
Polishing work |
100% Completed | |
16 | Switch -Socket fitting work | 100% Completed | |
17 | Outside paint work | 100 % Completed | |
18 | Door shutter work | 100 % Completed | |
19 | Aluminum work | 100 % Completed | |
20 | Tiles Pointing work & Marble finishing work | 100 % Completed | |
21 | Commode – Basin fitting work and C.P fittings work | 100 % Completed | |
22 | Lift/Generator /Substation /Solar work | 100% Completed | |
23 | Boundary wall /Ground floor development work | 100% Completed | |
24 | Roof top finishing work | 100% Completed | |
25 | Roof top Gardening work G.F Garden work | 100% Completed |