New Horizon

Purana Paltan, Dhaka

Expected Completion Date

May 2025

Status Updated

June, 2025

SL. No Name of the work Progress details Remark
01 Foundation work 100% completed.  
02 Super Structure work 100% completed.  
03  

 

Block Work

Basement=100%

G. F.=60%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%,

Roof= 100%

 
04  

 

Electrical Conducting work

Basement=60%

G. F=50%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%,

Roof = 100%

 
05  

 

Door frame fitting work

Basement=100%

G. F=100%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%

 
06  

 

Sanitary & plumbing line work

Basement=100%

G. F=100%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%,

 

 
07  

 

In side Plastering work

Basement=100%

G. F=100%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%,

 
08  

 

Electrical cable wiring work

Basement=100%

G. F=100%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%

 
09  

 

Wall Tiles work

Basement=100%

G. F=100%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%

 
10  

 

Common sanitary & Plumbing line work

Basement=100%

G, F=100%

A1= 1000%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%,

 
11 Outside plastering work 100% Completed  
12  

 

Floor tiles/Marble work

Basement=100%

G, F=100%

A1= 100%, A2= 100%, A3= 90%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%,

 
13 L.C.C work 100% Completed  
14 Grill & Railing work

 

100% Completed  
15 Inside paint &

Polishing work

100% Completed  
16 Switch -Socket fitting work 100% Completed  
17 Outside paint work 100 % Completed  
18 Door shutter work 100 % Completed  
19 Aluminum work 100 % Completed  
20 Tiles Pointing work & Marble finishing work 100 % Completed  
21 Commode – Basin fitting work and C.P fittings work 100 % Completed  
22 Lift/Generator /Substation /Solar work 100% Completed  
23 Boundary wall /Ground floor development work 100% Completed  
24 Roof top finishing work 100% Completed  
25 Roof top Gardening work G.F Garden work 100% Completed  

 