New Horizon

Purana Paltan, Dhaka

Completion Date

July 2024

Status Updated

March, 2024

SL. No Name of the work Progress details

 

01 Foundation work  
02 Super Structure work  
03  

 

Block Work

Basement=100%

G. F.=60%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,   A6=100%, B6=100%,

A7=100%, B7=100%,   A8=100%, B8=100%,

Roof= 100%

04  

 

Electrical Conducting work

Basement=60%

G. F=50%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,     A6=100%, B6=100%,

A7=100%, B7=100%,     A8=100%, B8=100%,

Roof = 100%

05  

 

Door frame fitting work

Basement=100% ,   G. F=100%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,   A6=100%, B6=100%,

A7=100%, B7=100%,   A8=100%, B8=100%

06  

 

Sanitary & plumbing line work

Basement=20% , G. F=30%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=70%, B5=70%,  A6=75%, B6=70%,

A7=70%, B7=70%,  A8=70%, B8=70%,

07  

 

In side Plastering work

Basement=80% ,  G. F=20%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=90%, B5=90%,   A6=20%, B6=50%,

A7=80%, B7=80%,  A8=80%, B8=80%,

08  

 

Electrical cable wiring work

Basement=60% , G, F=30%

A1= 25%, A2= 25%, A3= 25%, A4= 25%,

A5=10%, B5=10%,

09  

 

Wall Tiles work

A1= 80%, A2= 80%, A3= 80%, A4= 80%,

A5=30%, B5=10%,  A8=30%, B8=10%,

10  

 

Common sanitary & Plumbing line work

Basement=20% , G, F=30%

A1= 80%, A2= 80%, A3= 80%, A4= 80%,

A5=40%, B5=40%, A6=40%, B6=40%,

A7=40%, B7=40%, A8=40%, B8=40%,

11 Outside plastering work  
12 Floor tiles/Marble work A1= 90%, A2= 90%, A3= 90%, A4= 90%,

A5=80%, B5=50%,  A8=80%,

13 L.C.C work  
14 Grill & Railing work 60 % Completed
15 Inside paint & Polishing work  
16 Switch -Socket fitting work  
17 Outside paint work  
18 Door shutter work  
19 Aluminum work  
20 Tiles Pointing work & Marble finishing work  
21 Commode – Basin fitting work and C.P fittings work  
22 Lift/Generator /Substation /Solar work 30% Completed
23 Boundary wall /Ground floor development work 65% Completed
24 Roof top finishing work 60% Completed
25 Roof top Gardening work G.F Garden work 25% Completed