Pine Hurst

Uttara, Dhaka

Completion Date

September 2024

Status Updated

March, 2024

SL. No Name of the work Progress details
1 Foundation work 100% completed.
2 Basement work N/A
3 Super Structure work 98% completed (8th Floor Roof slab casting completed)
4 Block Work 95% completed
5 Electrical conduiting work 95% completed
6 Door frame fitting work 96% completed
7 Sanitary & plumbing line work 80% completed

 

8 Inside Plastering work 85% completed
9 Electrical cable wiring work 30% completed
10 Wall tiles work 20 % Completed
11 Common sanitary & Plumbing line work NYS
12 Outside plastering work 50%
13 Floor tiles/Marble work NYS
14 L.C.C work NYS
15 Grill & Railing work NYS
16 Inside paint & Polishing work NYS
17 Switch -Socket fitting work NYS
18 Outside paint work NYS
19 Door shutter work NYS
20 Aluminum work NYS
21 Tiles Pointing work & Marble finishing work NYS
22 Commode – Basin fitting work and C.P fittings work NYS
23 Lift/Generator /Substation /Solar work NYS
24 Boundary wall /Ground floor development work NYS
25 Roof top finishing work NYS
26 Roof top Gardening work G.F Garden work NYS
27 Land escape /Logo work NYS