Pine Hurst

Uttara, Dhaka

Completion Date

October 2024

Status Updated

September, 2024

SL. No Name of the work Progress details
1 Foundation work 100% completed.
2 Basement work N/A
3 Super Structure work 100% completed (8th Floor Roof slab casting completed)
4 Block Work 100% completed
5 Electrical conduiting work 98% completed
6 Door frame fitting work 100% completed
7 Sanitary & plumbing line work 98% completed

 

8 Inside Plastering work 100% completed
9 Electrical cable wiring work 95% completed
10 Wall tiles work 90% Completed
11 Common sanitary & Plumbing line work 30%
12 Outside plastering work 95% Completed
13 Floor tiles/Marble work 95% Completed
14 L.C.C work NYS
15 Grill & Railing work 85%
16 Inside paint & Polishing work 40%
17 Switch -Socket fitting work 40%
18 Outside paint work NYS
19 Door shutter work 60%
20 Aluminum work 30%
21 Tiles Pointing work & Marble finishing work 20%
22 Commode – Basin fitting work and C.P fittings work NYS
23 Lift/Generator /Substation /Solar work 20%
24 Boundary wall /Ground floor development work NYS
25 Roof top finishing work 65%
26 Roof top Gardening work G.F Garden work 50%
27 Landscape /Logo work NYS

 