bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

Shopnoneer

Uttarkhan, Dhaka
Expected Completion Date February 2025
Status Updated May, 2025
Back to all projects
Shopnoneer

Construction progress details

The progress table comes directly from the WordPress post content.

SL NO Name of Work Progress details
1 Foundation work Completed
2 Super Structure Work Completed
3 Brick work/ Block work Tower-1, 2, 3, &4 – Block work 100% complected
4 Electrical conduiting work Tower-1, 2, 3, &4 – Ele work 100% complected
5 Door frame fitting work Door fame fitting 100% completed.
6 Sanitary & Plumbing line work Tower 1, 2, 3 &4 bath room ppr work 100% completed
7 In side plastering work Tower-1, 2, 3 &4 – In side Plaster work 100% complected
8 Electrical cable wiring work Tower-1, 2,3 &4 – 13th floor cable Wiring 100% complected
9 wall tiles work Bath Room wall 100% completed
10 Common Sanitary & Plumbing line work Tower – 1,2,3&4 sanitary & plumbing line 100%
11 Outside plastering work Tower-3, outside plaster 100% & tower -4, Outside plaster 100 % & tower-2 Outside plaster 100% tower -1 Outside plaster 100%
12 Floor tiles/ Marble work Main Floor Tiles work 100%
13 L.C.C work Tower-4 (100%) Tower-1 (100%) Tower-2 (100%)
14 Grill & Railing work Tower – 1,2,3&4 Grill Work 100 %
15 In side paint & Polishing work Tower – 1, 2 ,3 & 4 In side paint 100%
16 Switch – Socket fitting work 100%
17 Outside Paint work Tower – 1,2,3 & 4 Outside 100% completed
18 Door Shutter work 100%
19 Aluminum work 100%
20 Tiles pointing work &Marble finishing work 100%
21 Commode – Basin fitting work & C. P fitting work 100% 
22 Lift / Generator/Substation/ Solar work Tower – 1,2,3&4 Lift installation completed. Generator installation completed.
23 Boundary wall/ Ground Floor development work Boundary wall 100%
24 Roof top finishing work Tower – 1,2,3 & 4 Roof top 100 % completed
25 Roof top Gardening work G.F. Garden work 100% completed