Shopnoneer

Uttarkhan, Dhaka

Completion Date

October 2024

Status Updated

September, 2024

SL NO Name of Work Progress details
1 Foundation work Completed
2 Super Structure Work Completed
3 Brick work/ Block work Tower-1, 2, 3, &4 – Block work 100% complected
4 Electrical conduiting work Tower-1, 2, 3, &4 – Ele work 100% complected
5 Door frame fitting work Door fame fitting 100% completed.
6 Sanitary & Plumbing line work Tower 1, 2, 3 &4 bath room ppr work 100% completed
7 In side plastering work Tower-1, 2, 3 &4 – In side Plaster work 100% complected
8 Electrical cable wiring work Tower-1, 2,3 &4 – 13th floor cable Wiring complected
9 wall tiles work Bath Room wall 100% completed
10 Common Sanitary & Plumbing line work Tower – 1,2,3&4 sanitary & plumbing line 80%
11 Outside plastering work Tower-3, outside plaster 100% & tower -4, Outside plaster 100 % &tower-2 Outside plaster 100% tower -1 Outside plaster 100%
12 Floor tiles/ Marble work Main Floor Tiles work 95%
13 L.C.C work Tower-4 (100%) Tower-1 (100%) Tower-2 (100%)
14 Grill & Railing work Tower – 1,2,3&4 Grill Work 100 %
15 In side paint & Polishing work Tower – 3&4 In side paint 70%
16 Switch – Socket fitting work 85%
17 Outside Paint work Tower – 1,2,3&4Out side   50 %
18 Door Shutter work 95%
19 Aluminum work 90%
20 Tiles pointing work &Marble finishing work 70%
21 Commode – Basin fitting work & C. P fitting work  
22 Lift / Generator/Substation/ Solar work Tower – 2,2,3&4Lift Generator   45 %
23 Boundary wall/ Ground Floor development work Boundary wall 100%
24 Roof top finishing work Tower – 1,2,3&4Roof top   85 %
25 Roof top Gardening work G.F. Garden work 70%

 