Shopnoneer

Uttarkhan, Dhaka

Completion Date

January 2025

Status Updated

July, 2022

SL. No Name of the work Progress details
01 Foundation work 100% completed.
02 Super Structure work Tower -1 , 12th  floor  Roof casting completed , tower -2, 9th  floor Roof casting completed , Tower -3, 8th  floor roof casting Completed and Tower -4,  12th floor roof casting completed .

 

03 Block Work Tower-1, 2, 3, &4 – Block work 40% completed

 

04 Electrical conduting work 25% completed
05 Door frame fitting work 15% completed
06 Sanitary & plumbing line  work  
07 In side Plastering work 10% completed
08 Electrical cable wiring work  
09 Wall tiles  work  
10 Common sanitary & Plumbing line work  
11 Outside plastering work  
12 Floor tiles/Marble work  
13 L.C.C work  
14 Grill & Railing work  
15 Inside paint & Polishing work  
16 Switch -Socket fitting work  
17 Outside paint work  
18 Door shutter work  
19 Aluminum work  
20 Tiles Pointing work & Marble finishing work  
21 Commode – Basin fitting work and C.P fittings work  
22 Lift/Generator /Substation /Solar work  
23 Boundary wall /Ground floor development work  
24 Roof top finishing work  
25 Roof top Gardening work G.F Garden work  