Shopnoneer

Uttarkhan, Dhaka

Completion Date

September 2024

Status Updated

March, 2024

SL. No Name of the work Progress details
1 Foundation work 100% completed.
2 Basement work 100% completed
3 Super Structure work 100% completed
4 Block Work 100% completed
5 Electrical conduiting work 100% completed
6 Door frame fitting work 100% completed
7 Sanitary & plumbing line work 98% completed
8 Inside Plastering work 97% completed
9 Electrical cable wiring work 100% completed
10 Wall tiles work 95% completed
11 Common sanitary & Plumbing line work 70% completed
12 Outside plastering work 98% completed
13 Floor tiles/Marble work 98% completed
14 L.C.C work 95% completed
15 Grill & Railing work 95% completed
16 Inside paint & Polishing work 70% completed
17 Switch -Socket fitting work NYS
18 Outside paint work 65 % completed
19 Door shutter work 75 % completed
20 Aluminum work 50% completed.
21 Tiles Pointing work & Marble finishing work NYS
22 Commode – Basin fitting work and C.P fittings work NYS
23 Lift/Generator /Substation /Solar work NYS
24 Boundary wall /Ground floor development work 90% completed
25 Roof top finishing work NYS
26 Roof top Gardening work G.F Garden work NYS
27 Land escape /Logo work NYS