Completion Date
January 2025
Status Updated
September, 2024
SL. No | Name of the work | Location | Progress details | Remarks |
01 | Foundation work | 100% completed. | ||
02 | Super Structure work | 99% | ||
03 | Block Work | Apartment =A1.B1
Apartment =A2.B2 Apartment =A3.B3 Apartment =A4.B4 Apartment =A5.B5 Apartment =A6.B6 Apartment =A7.B7 Apartment =A8.B8 Apartment =A9.B9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete |
|
04 | Electrical conduiting work | Apartment =A1.B1
Apartment =A2.B2 Apartment =A3.B3 Apartment =A4.B4 Apartment =A5.B5 Apartment =A6.B6 Apartment =A7.B7 Apartment =A8.B8 Apartment =A9.B9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete
|
|
05 | Door frame fitting work | Apartment =A1.B1
Apartment =A2.B2 Apartment =A3.B3 Apartment =A4.B4 Apartment =A5.B5 Apartment =A6.B6 Apartment =A7.B7 Apartment =A8.B8 Apartment =A9.B9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete |
|
06 | Sanitary & plumbing line work | Apartment =A1.B1
Apartment =A2.B2 Apartment =A3.B3 Apartment =A4.B4 Apartment =A5.B5 Apartment =A6.B6 Apartment =A7.B7 Apartment =A8.B8 Apartment =A9.B9 |
99% Complete
99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete |
|
07 | In side Plastering work | Apartment =A1.B1
Apartment =A2.B2 Apartment =A3.B3 Apartment =A4.B4 Apartment =A5.B5 Apartment =A6.B6 Apartment =A7.B7 Apartment =A8.B8 Apartment =A9.B9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete
|
|
08 | Electrical cable wiring work | Apartment =A1.B1
Apartment =A2.B2 Apartment =A3.B3 Apartment =A4.B4 Apartment =A5.B5 Apartment =A6.B6 Apartment =A7.B7 Apartment =A8.B8 Apartment =A9.B9 |
98% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 98% Complete 98% Complete
|
|
09 | Wall tiles work | Apartment =A1.B1
Apartment =A2.B2 Apartment =A3.B3 Apartment =A4.B4 Apartment =A5.B5 Apartment =A6.B6 Apartment =A7.B7 Apartment =A8.B8 Apartment =A9.B9 |
95% Complete
95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 100% Complete 100% Complete |
|
10 | Common sanitary & Plumbing line work | 80%
|
||
11 | Outside plastering work | 95% Complete | ||
12 | Floor tiles/Marble work | Apartment =C1.D1
Apartment =A2.B2 Apartment =A3.B3 Apartment =A4.B4 Apartment =A5.B5 Apartment =A6.B6 Apartment =A7.B7 Apartment =A8.B8 Apartment =A9.B9 |
90% Complete
95% Complete 95%Complete 95% Complete 95% Complete 95% Complete 95% Complete 100% Complete 100% Complete
|
|
13 | L.C.C work |
|
||
14 | Grill & Railing work | Apartment =A1.B1
Apartment =A2.B2 Apartment =A3.B3 Apartment =A4.B4 Apartment =A5.B5 Apartment =A6.B6 Apartment =A7.B7 Apartment =A8.B8 Apartment =A9.B9 |
85%
85% 85% 85% 85% 85% 85% 85% 85%
|
|
15 | Inside paint & Polishing work | Apartment =A1.B1
Apartment =A2.B2 Apartment =A3.B3 Apartment =A4.B4 Apartment =A5.B5 Apartment =A6.B6 Apartment =A7.B7 Apartment =A8.B8 Apartment =A9.B9 |
10%
50% 50% 50% 50% 50% 50% 50% 20%
|
|
16 | Switch -Socket fitting work | |||
17 | Outside paint work | |||
18 | Door shutter work | |||
19 | Aluminum work | Apartment =A1.B1
Apartment =A2.B2 Apartment =A3.B3 Apartment =A4.B4 Apartment =A5.B5 Apartment =A6.B6 Apartment =A7.B7 Apartment =A8.B8 Apartment =A9.B9 |
20%
20% 2% 20% 20% 20% 20% 20% 20%
|
|
20 | Tiles Pointing work & Marble finishing work | |||
21 | Commode – Basin fitting work and C.P fittings work | |||
22 | Lift/Generator /Substation /Solar work | Lift Installation work ongoing, Generator at site, Sub-station work is on process. | ||
23 | Boundary wall /Ground floor development work | 50% | ||
24 | Roof top finishing work | 80% | ||
25 | Roof top Gardening work G.F Garden work | 50% |