The Boulevard

Bashundhara R/A, Dhaka

Completion Date

January 2025

Status Updated

March, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 92% completed
  Block work A-1=95%,A-2=95%A-3=95%, A-4=95%,A-5=90% ,A-6 =65%,A-7=35%,A-8=0%.
  Electrical  conduit work A-1=95%,A-2=95%A-3=95%, A-4=95%,A-5=95% ,A-6 =80%,A-7=20%,A-8=20%.
  Door frame fitting work A-1=90%,A-2=80%A-3=95%, A-4=95%,A-5=80% ,A-6 =0%,A-7=0%,A-8=0%.
  Sanitary & plumbing line  work A-1=0%,A-2=0%A-3=0%, A-4=0%,A-5=0% ,A-6 =0%,A-7=0%,A-8=0%.
  In side Plastering work A-1=85%,A-2=30%A-3=90%, A-4=90%,A-5=70% ,A-6 =25%,A-7=25%,A-8=0%.
  Electrical cable wiring work N/A
  Wall tiles  work N/A
  Common sanitary & Plumbing line work N/A
  Outside plastering work N/A
  Floor tiles/Marble work N/A
  L.C.C work N/A
  Grill & Railing work N/A
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work N/A
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work N/A
  Roof top finishing work N/A
  Roof top Gardening work N/A