Completion Date
January 2025
Status Updated
March, 2024
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 92% completed | |
Block work | A-1=95%,A-2=95%A-3=95%, A-4=95%,A-5=90% ,A-6 =65%,A-7=35%,A-8=0%. | |
Electrical conduit work | A-1=95%,A-2=95%A-3=95%, A-4=95%,A-5=95% ,A-6 =80%,A-7=20%,A-8=20%. | |
Door frame fitting work | A-1=90%,A-2=80%A-3=95%, A-4=95%,A-5=80% ,A-6 =0%,A-7=0%,A-8=0%. | |
Sanitary & plumbing line work | A-1=0%,A-2=0%A-3=0%, A-4=0%,A-5=0% ,A-6 =0%,A-7=0%,A-8=0%. | |
In side Plastering work | A-1=85%,A-2=30%A-3=90%, A-4=90%,A-5=70% ,A-6 =25%,A-7=25%,A-8=0%. | |
Electrical cable wiring work | N/A | |
Wall tiles work | N/A | |
Common sanitary & Plumbing line work | N/A | |
Outside plastering work | N/A | |
Floor tiles/Marble work | N/A | |
L.C.C work | N/A | |
Grill & Railing work | N/A | |
Inside paint & Polishing work | N/A | |
Switch -Socket fitting work | N/A | |
Outside paint work | N/A | |
Door shutter work | N/A | |
Aluminum/Glazing work | N/A | |
Tiles Pointing work & Marble finishing work | N/A | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | N/A | |
Boundary wall /Ground floor development work | N/A | |
Roof top finishing work | N/A | |
Roof top Gardening work | N/A |