Completion Date
April 2025
Status Updated
September, 2024
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 96% completed | |
Block work | A-1=98%,A-2=98%A-3=98%, A-4=98%,A-5=98% ,A-6 =98%,A-7=98%,A-8=95%. | |
Electrical conduit work | A-1=95%,A-2=95%A-3=95%, A-4=95%,A-5=95% ,A-6 =95%,A-7=95%,A-8=95%. | |
Door frame fitting work | A-1=97%,A-2=97%A-3=97%, A-4=97%,A-5=99% ,A-6 =99%,A-7=99%,A-8=99%. | |
Sanitary & plumbing line work | A-1=60%,A-2=95%A-3=600%, A-4=60%,A-5=35% ,A-6 =35%,A-7=35%,A-8=35%. | |
In side Plastering work | A-1=95%,A-2=95%A-3=95%, A-4=95%,A-5=95% ,A-6 =93%,A-7=90%,A-8=90%. | |
Electrical cable wiring work | A-1=15%,A-2=15%A-3=15%, A-4=15%,A-5=0% ,A-6 =0%,A-7=0%,A-8=0%. | |
Wall tiles work | N/A | |
Common sanitary & Plumbing line work | N/A | |
Outside plastering work | 55% | |
Floor tiles/Marble work | A-1=0%,A-2=25%A-3=0%, A-4=0%, A-5=0% ,A-6 =0%,A-7=0%,A-8=0%. | |
L.C.C work | N/A | |
Grill & Railing work | N/A | |
Inside paint & Polishing work | N/A | |
Switch -Socket fitting work | N/A | |
Outside paint work | N/A | |
Door shutter work | N/A | |
Aluminum/Glazing work | N/A | |
Tiles Pointing work & Marble finishing work | N/A | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | N/A | |
Boundary wall /Ground floor development work | N/A | |
Roof top finishing work | N/A | |
Roof top Gardening work | N/A |