The Destination

Dhanmondi, Dhaka

Completion Date

September 2024

Status Updated

September, 2024

SL. No Name of the work Progress details
01 Foundation work 100%
02 Super Structure work G.F- 100%, 1st floor-100%, 2nd floor-100%, 3rd floor 100%,4th-Floor -100% , 5th Floor-100%, 6th floor 100%,7th floor 100%, 8th floor 100%, 9th floor 100%, 10 th floor 100%, 11th floor 100%, Roof top 100%%
03 Block Work  1st Floor100% ,A2-100%, B2-100%, A3-100%, B3-100%, A4-100% ,B4-100%, A5-100%, B5-100%, A6-100%, B6-100%, A7-100%, B7-100%, A8-100%, B8-100%, A9-100%, B9-100%, A10-100%, B10-100%, A11-100%, B11-100%,
04 Electrical  conducting work G.F- 70%, 1st floor-70%, 2nd floor 100%,3rd Floor-100%, 4th Floor 100%, 5th floor 100%, 6th floor 100%, 7th floor 100%, 8th floor 100%, 9th floor 100%, 10th floor 100%, 11th floor100% ,Roof Top 70%
05 Door frame fitting work Flat-B2  100%, A2- 100% , B3-100%, A3-100%, B4-100%, A4-100%,  B5-100%, A5-100%, B6-100% , A6-100%, A7-100%, B7-100%, A8-100%,B8-100%,A9-100%,B9-100%,A10-100%B10-100% ,A11-100% B11-100%Mezzanine Floor 100%
06 Sanitary & plumbing line  work(Ace drain water line, ven- vertical line) 2nd floor 100%, 3rd floor 100%, 4th floor100%, 5th floor 100%, 6th floor 100%, 7th floor 100%, 8th floor 100%, 9th floor 100%, 10th Floor 100% ,11thfloor 100% , Roof Top 60%.
07 In side Plastering work G.F 90% ,1st Floor ceiling plaster 100%, 2nd floor 100%, 3rd floor 100%, 4th floor 100%,5th 100% ,6th floor 100%, 7th floor 100%,8th floor 100%, 9th floor 100%,10th floor 100%, 11th floor 100%

Wall plaster: A2-100%,B2-100%, A3-100%,B3-100%,A4-100%,B4-100%,A5-100%,B5-100%,A6-100%, B6-100%, A7-100%, B7-100%,A8-100%, B8-100%, A9-100%, B9-100%, A10-100%,B10-100%,  A11-100% ,B11-100% , Roof Top 80% .

08 Electrical cable wiring work G.F-60% , 1st Floor-60% , A2-100%,B2-100%,A3-100%,B3-100%, A4-100%, B4-100%, A5-100%, B5-100%, A6-100%, B6-100%, A7-100%,B7-100%, A8-100%, B8-100%,A9-100%, B9-100%,A10-100% , B10-100%,  A11-100%, B11 -100% ,Roof Top60% .
09 Wall tiles  work G.F-90% , 1st Floor-90%, A2-100%,B2-100%,A3-100%, B3-100%, A4-100%, B4-100%, A5-100%, B5-100%,A6 -100% ,B6-100%, A7-100% , B7-100% ,B8-100%, A8-100%,  A9-100%,B9-100%, A10- 100% ,B10-100%,  A11-100% ,B11-100%, Roof Top-60%
10 Common sanitary & Plumbing line work G.F-60% ,1st Floor-60% , Roof Top-40%.
11 Outside plastering work South side 100%, North side 100%, West side 100%
12 Floor tiles/Marble work  G.F-85%, 1st Floor-85%, Flat-A2-100%, B2-100% , A3-100% ,  B3 -100%, A5 -100%, B5 -100%, A6-100%, B6 -100%, A7-100%, B7-100%,A8-100% ,B8-100%,B9-100%,  A9-100% A-10 -100% , B-10 -100% , A11-100%, B11-100%, Roof Top 70%
13 L.C.C work 100%
14 Grill & Railing work 100%
15 Inside paint & Polishing work A11-100% ,B11-90% , A9-100%, B9-100%, A8-100%, B8-100%,A7-100%, B7-100%, A6-90%, B6-100%, A5-90%, B5-60%, A4-70%, B4-70%, A3-95%, B3-95%,A2-60%,  B2-90%
16 Switch -Socket fitting work A11-100%,  B11-100%, A10-70%,B10-70%,  A9-100%, B9-100%, A8-100%, B8-100%,A7-100%, B7-100%,A6-100%, B6-100%, A5-100%, B5-100%, A4-100%, B4-100%,A3-100%, B3-100%, A2-100%, B2-100%
17 Outside paint work 40%
18 Door shutter work A11-100%, A9-100%, B9-100% , A8-90%, B8-50%, A7-90%, B7-90%, A6-80%, A4-50%, B4-50%,  A5-90%, B5-90%, A3-60%,  B3-60% ,A2-60%, B2-60%
19 Aluminum/Glazing work A11-100% , A9-100%, B9-100%, A8-90%, B8- 90%, A7-100%, B7-100%, A6-90%, B6-90%, A5-80%, B5-80% ,A4-90%, B4-40%, A3-90%, B3-90%, A2-70%, B2-90%
20 Tiles Pointing work & Marble finishing work A11-100%, A9-100%, B9-100%, A8-70%,A7-100%, B7-100%, B8-50%, A6-60%, B6-90%, A3-95%, B3-95%, B2-95%,
21 Commode – Basin fitting work and C.P fittings work A11-100%,B11-50% A10-40% B10-40% A9-100%, B9- 100%,A8- 90%B8-100%,A7-100%, B7-100%,A6-90% B6-100%, A5-100%, B5-90%, A4-85%B4-40%, A3-100%,B3-100%A2-90%, B2-100%.

 

22 Lift/Generator /Substation /Solar work 80%
23 Boundary wall /Ground floor development work 85%
24 Roof top finishing work 70%
25 Roof top Gardening work 40%