The Destination

Dhanmondi, Dhaka

Completion Date

February 2024

Status Updated

March, 2024

SL. No Name of the work Progress details
01 Foundation work 100%
02 Super Structure work G.F- 100%, 1st floor-100%, 2nd floor-100%, 3rd floor 100%,4th-Floor -100% , 5th Floor-100%, 6th floor 100%,7th floor 100%, 8th floor 100%, 9th floor 100%, 10 th floor 100%, 11th floor 100%, Roof top 90%
03 Block Work  1st Floor 85% ,A2-100%, B2-100%, A3-100%, B3-100%, A4-100% ,B4-100%, A5-100%, B5-100%, A6-100%, B6-100%, A7-100%, B7-100%, A8-100%, B8-100%, A9-100%, B9-100%, A10-90%, B10-90%, A11-100%, B11-100%,
04 Electrical  conducting work G.F- 55%, 1st floor-65%, 2nd floor 100%,3rd Floor-100%, 4th Floor 100%, 5th floor 100%, 6th floor 100%, 7th floor 100%, 8th floor 100%, 9th floor 100%, 10th floor 100%, 11th floor100% ,Roof Top 50%

 

05 Door frame fitting work Flat-B2  100%, A2- 100% , B3-100%, A3-100%, B4-100%, A4-100%,  B5-100%, A5-100%, B6-100% , A6-100%, A7-100%, B7-100%, A8-100%,B8-100%,A9-100%,B9-100%,A10-95%,B10-85% ,A11-100% B11-100%Mezzanine Floor 60%
06 Sanitary & plumbing line  work(Ace drain water line, ven- vertical line) 2nd floor 100%, 3rd floor 100%, 4th floor100%, 5th floor 100%, 6th floor 100%, 7th floor 100%, 8th floor 100%, 9th floor 100%, 10th Floor 100% ,11thfloor 100% , Roof Top 35%.
07 In side Plastering work G.F 50% ,1st Floor ceiling plaster 100%, 2nd floor 100%, 3rd floor 100%, 4th floor 100%,5th 100% ,6th floor 100%, 7th floor 100%,8th floor 100%, 9th floor 100%,10th floor 100%, 11th floor 100%

Wall plaster: A2-100%,B2-100%, A3-100%,B3-100%,A4-100%,B4-100%,A5-100%,B5-100%,A6-100%, B6-100%, A7-100%, B7-100%,A8-100%, B8-100%, A9-100%, B9-100%, A10-100%,B10-90%,  A11-100% ,B11-100% , Roof Top 70% .

08 Electrical cable wiring work A2-100%,B2-100%,A3-100%,B3-100%, A4-100%, B4-100%, A5-100%, B5-100%, A6-100%, B6-100%, A7-100%,B7-100%, A8-100%, B8-100%,A9-100%, B9-100%,A10-100% , B10-30%,  A11-100%, B11 -100% ,Roof Top 40% , Mezzanine Floor 40%
09 Wall tiles  work A2-100%,B2-100%,A3-100%, B3-100%, A4-100%, B4-100%, A5-100%, B5-100%,A6 -100% ,B6-100%, A7-100% , B7-100% ,B8-100%, A8-100%,  A9-100%,B9-100%, A11-100% ,B11-100%, A10- 100% ,B10-100%,
10 Common sanitary & Plumbing line work  
11 Outside plastering work South side 100%, North side 100%, West side 100%
12 Floor tiles/Marble work  Flat-A2-100%, B2-100% , A3-100% ,  B3 -100%, A5 -100%, B5 -100%, A6-100%, B6 -100%, A7-100%, B7-100%,A8-100% ,B8-100%,B9-100%,  A9-100% A-10 -100% , B-10 -100% , A11-100%, B11-100%, Roof Top 30%
13 L.C.C work 100%
14 Grill & Railing work 90%
15 Inside paint & Polishing work A11-45% ,B11-45% , A9-45%, B9-43%, A8-43%, B8-47%,A7-40%, B7-42%, A6-41%, B6-44%, A5-45%, B5-47%, A4-45%, B4-45%, A3-30%, B3-30%
16 Switch -Socket fitting work A11-90%,  B11-50%,  A9-70%, B9-70%, A8-60%, B8-65%,A7-60%, B7-60%,A6-65%, A5-70%, B5-60%, A4-60%, B4-60%
17 Outside paint work 20%
18 Door shutter work A11-90%, A9-95%, B9-90% , A8-50%, B8-50%, A7-90%, B7-40%, A6-50%, A4-40%, B4-40%,  A5-90%, B5-90%
19 Aluminum/Glazing work A11-70% , A9-60%, B9-40%, A8-60%, B8- 60%, A7-30%, B7-30%, A6-30%, B6-20%, A5-75%, B5-75% ,A4-40%, B4-40%, A3-30%, B3-30%
20 Tiles Pointing work & Marble finishing work  
21 Commode – Basin fitting work and C.P fittings work  

 

22 Lift/Generator /Substation /Solar work 47%
23 Boundary wall /Ground floor development work 75%
24 Roof top finishing work 47%
25 Roof top Gardening work 25%