The Millennial

Bhatara, Dhaka
Expected Completion Date June 2026
Status Updated April, 2026
Back to all projects
The Millennial

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
1 Foundation work 100% completed
2 Basement work 100 % completed
3 Super Structure work 100 % completed (Tower-1, Tower-2, Tower-3)
4 Block Work Tower -01, All apartments of tower: 1 (A1 to A8) total 08 apartments no’s are 100% completed.

Tower -02, All apartments of tower: 2 total 55 no’s apartments are 100% completed.

 

Tower -03, All apartments of tower: 3 total 51 nos apartments are 100% completed

 

5 Electrical conduiting work Over all apartments 100 % completed. Common Area 90 % Completed
6 Door frame fitting work Over all 100 % completed
7 Sanitary & plumbing line work Internal wiring 100% completed.
8 Inside Plastering work Overall 100%
9 Electrical cable wiring work 100 % apartments completed.
10 Wall tiles work Wall tile: Tower -1, 100% T-2: 100%. T-3: 98% complete.
11 Common sanitary & Plumbing line work Overall, 90% completed.
12 Outside plastering work Tower -1 completed. Tower-2= 100% T-3 =

100%

13 Floor tiles/Marble work Tower- 1, 100 % Completed. Tower-2, = 100% completed. Tower: 3, 95% completed.
14 L.C.C work Tower- 1 Completed, Tower -2, 100% Completed, Tower -3, 100% Completed.
15 Grill & Railing work Apartments of Tower- 1 = 100 % completed, Tower-2 = 100% completed, Tower-3 = 100% completed.
16 Inside paint & Polishing work Tower-1, 1st and 2nd code work =100% complete. Tower-2, 1st code 100% completed. Tower-3, 1st code 10 apartments completed.
17 Switch -Socket fitting work Tower-1 completed. Tower-2, 100% completed.
18 Outside paint work Tower-1 1st coat Completed. Tower-2, 90% completed.
19 Door shutter work Tower -1 completed. Tower: 2, completed.
20 Aluminum work Tower-1: 100 % completed, Tower: 2, 100% completed. Tower: 3 70% completed
21 Tiles Pointing work & Marble finishing work Tower-1, Wall –  100% completed. Tower: 2, 90% completed.
22 Commode – Basin fitting work and C.P fittings work 90%
23 Lift/Generator /Substation /Solar work 90%
24 Boundary wall /Ground floor development work 90 % completed (Boundary wall 90% completed, Plaster 90% completed.)
25 Roof top finishing work Tower: 1 tile work: 100% competed. Tower-2:  90 % completed. Tower: 3, 90% completed.
26 Roof top Gardening work G.F Garden work NYS
27 Land escape /Logo work 80%