The Millennial

Bhatara, Dhaka

Completion Date

October 2025

Status Updated

March, 2024

SL. No Name of the work Progress details
1 Foundation work 100% completed
2 Basement work 100 % completed
3 Super Structure work 95 % completed (Tower-1, 8th floor roof completed, Tower-2, Roof casting completed and tower-3, Roof casting completed.)
4 Block Work Tower -01,

A-1 =100%, A-2= 100%, A-3= 95%, A-4=100, A-5=95%, A-6=90%, A-7=100%, A-8 =100%,

Tower -02,

B-1=40%, B-2=100%, B-3 =100%, B-4=100%, B-5= 100%, B-6= 100%,  B-7= 100%, B-8= 100%,B-9= 100%, B-10= 90%, B-11= 100%, B-12= 100, B-13=70% , C-1= 100%,  C-2=100%, C-3 =100% , C-4= 100%, C-5=100% ,C-6= 100%, C-7= 100%, C-8= 100% , C-9= 100% ,C-10= 90%,  C-11= 90% , C-12= 100, C-13=70%   , D-2=100% , D-3=100% , D-4=100% , D-5=100%. D-6= 100%, D-7= 100%, D-8= 100% , D-9= 100%, D-10= 90%, D-11= 90%, D-12= 100, D-13=70% ,E-1= 100%,   E-2 = 100%, E-3=100% , E-4=100%, E-5=80% , E-6= 100%, E-7= 100%, E-8= 100% , E-9= 100%, E-10= 100%, E-11= 100% , E-12= 100, E-13=70%

Tower -03 ,F-2= 100%, F-3= 100%, F-4=100%, F-5=100%, F-6=100%,  F-7=100%, F-8 = 80% , F-9 = 70% F-10= 70% F-11 = 70% F-12 = 70%   G-1=100%, G-2=100%, G-4=100%, G-5= 100%, G-6= 100%, G-7=100%, G-8= 100%,  G-9 = 70% ,G-10= 70% ,G-11 = 70%, G-12 = 70%,  H-1=100%, H-2=100%, H-3 =100% , H-4= 100%, H-5=90% , H-6 =100% , H-7= 100%, H-8=100% , H-9 = 70% ,H-10= 70% ,H-11 = 70%, H-12 = 70%,  I-1=100% I-2=100% , I-3=100% , I-4=100% , I-5=100%.  I-6 =100%, I-7=100% , I-8=100%,

I-9=70% , I-10=70%,

5 Electrical conduiting work Over all 75% completed
6 Door frame fitting work Over all 35% completed
7 Sanitary & plumbing line work NYS
8 Inside Plastering work Overall 50%
9 Electrical cable wiring work NYS
10 Wall tiles work Tower -1, 10%
11 Common sanitary & Plumbing line work NYS
12 Outside plastering work Tower -1 completed
13 Floor tiles/Marble work NYS
14 L.C.C work NYS
15 Grill & Railing work NYS
16 Inside paint & Polishing work NYS
17 Switch -Socket fitting work NYS
18 Outside paint work NYS
19 Door shutter work NYS
20 Aluminum work NYS
21 Tiles Pointing work & Marble finishing work NYS
22 Commode – Basin fitting work and C.P fittings work NYS
23 Lift/Generator /Substation /Solar work NYS
24 Boundary wall /Ground floor development work 25% completed (Boundary wall 70% completed)
25 Roof top finishing work 30%
26 Roof top Gardening work G.F Garden work NYS
27 Land escape /Logo work NYS