Completion Date
March 2025
Status Updated
March, 2024
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 100% completed | |
Block work | A-2=90%, B-2=90%, A-3=90%, B-3=90%, A-4=90%, B-4=90%, A-5=90%, B-5=90%, A-6=90%, B-6=90%, A-7=90%, B-7=90%, A-8=90%, B-8=90%, A-9=50%, B-9=300% | |
Electrical conduit work | A-2=90%, B-2=90%, A-3=90%, B-3=90%, A-4=90%, B-4=90%, A-5=90%, B-5=90%, A-6=90%, B-6=90%, A-7=90%, B-7=90%,
A-8=90%, B-8=90%, A-9=70%, B-9=30%, |
|
Door frame fitting work | A-2=90%, B-2=90%, A-3=90%, B-3=90%, A-4=90%, B-4=90%, A-5=90%, B-5=90%, A-6=90%, B-6=90%, A-7=90%, B-7=90%,
A-8=90%, B-8=90%, A-9=00%, B-9=00%, |
|
Sanitary & plumbing line work | A-2=05%, B-2=05%, A-3=05%, B-3=05%, A-4=05%, B-4=05%, A-5=05%, B-5=05%, A-6=05%, B-6=05%, A-7=05%, B-7=05%, A-8=05%, B-8=05%, A-9=05%, B-9=05% | |
In side Plastering work | A-2=90%, B-2=90%, A-3=90%, B-3=90%, A-4=00%, B-4=00%, A-5=00%, B-5=00%, A-6=50%, B-6=90%, A-7=90%, B-7=90%, A-8=90%, B-8=90%, A-9=00%, B-9=00% | |
Electrical cable wiring work | N/A | |
Wall tiles work | N/A | |
Common sanitary & Plumbing line work | N/A | |
Outside plastering work | N/A | |
Floor tiles/Marble work | N/A | |
L.C.C work | N/A | |
Grill & Railing work | N/A | |
Inside paint & Polishing work | N/A | |
Switch -Socket fitting work | N/A | |
Aluminum/Glazing work | N/A | |
Outside paint work | N/A | |
Door shutter work | N/A | |
Tiles Pointing work & Marble finishing work | N/A | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | N/A | |
Boundary wall /Ground floor development work | N/A | |
Roof top finishing work | N/A | |
Roof top Gardening work | N/A |