The Santorini

Bashundhara R/A, Dhaka

Completion Date

July 2025

Status Updated

September, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work A-2=90%, B-2=90%, A-3=90%, B-3=90%,    A-4=90%, B-4=90%, A-5=90%, B-5=90%, A-6=90%, B-6=90%, A-7=90%, B-7=90%, A-8=90%, B-8=90%, A-9=90%, B-9=90%
  Electrical  conduit work A-2=90%, B-2=90%, A-3=90%, B-3=90%,    A-4=90%, B-4=90%, A-5=90%, B-5=90%, A-6=90%, B-6=90%, A-7=90%, B-7=90%,

A-8=90%, B-8=90%, A-9=90%, B-9=90%,

  Door frame fitting work A-2=90%, B-2=90%, A-3=90%, B-3=90%,    A-4=90%, B-4=90%, A-5=90%, B-5=90%, A-6=90%, B-6=90%, A-7=90%, B-7=90%,

A-8=90%, B-8=90%, A-9=90%, B-9=90%,

  Sanitary & plumbing line  work A-2=70%, B-2=75%, A-3=75%, B-3=75%,    A-4=75%, B-4=75%, A-5=75%, B-5=75%, A-6=75%, B-6=75%, A-7=75%, B-7=75%, A-8=75%, B-8=75%, A-9=05%, B-9=05%
  In side Plastering work A-2=90%, B-2=90%, A-3=90%, B-3=90%,    A-4=90%, B-4=90%, A-5=90%, B-5=90%, A-6=90%, B-6=90%, A-7=90%, B-7=90%,

A-8=90%, B-8=90%, A-9=80%, B-9=70%,

  Electrical cable wiring work A-2=00%, B-2=00%, A-3=90%, B-3=90%,    A-4=90%, B-4=90%, A-5=90%, B-5=90%, A-6=90%, B-6=90%, A-7=90%, B-7=90%, A-8=90%, B-8=90%, A-9=00%, B-9=00%
  Wall tiles  work N/A
  Common sanitary & Plumbing line work N/A
  Outside plastering work 01. North side = 00%,

02. South side = 00%,

03. East Side = 80%,

04. West Side = 80%.

  Floor tiles/Marble work N/A
  L.C.C work N/A
  Grill & Railing work N/A
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Aluminum/Glazing work N/A
  Outside paint work N/A
  Door shutter work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work N/A
  Roof top finishing work N/A
  Roof top Gardening work N/A