Completion Date
March 2025
Status Updated
September, 2024
SL. No | Name of the work | Progress details |
01 | Foundation work | 100% |
02 | Super Structure work | 100% |
03 | Block Work | A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5 =100%, A-6= 100%, A-7= 100%, A-8= 100%, A-8= 90%, |
04 | Electrical conducting work | A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5 =100%, A-6= 100%, A-7= 100%, A-8= 80%, A-9= 50%, |
05 | Door frame fitting work | A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5 =100%, A-6 =100%, A-7 =100%, A-8 =100%, |
06 | Sanitary & plumbing line work | A-1 =50%, A-2= 50%, A-3= 50%, A-4= 50% A-5= 50%, A-6= 50%, A-7= 50%, A-8= 50% ,A-9= 50% |
07 | In side Plastering work | A-1 =100%, A-2= 100%, A-3=100%, A-4=100%, A-5=100%, A-6=100%, A-7=100%, A-8=100%, A-9=100%, |
08 | Electrical cable wiring work | N/A |
09 | Wall tiles work | A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5 =100%, A-6= 100%, A-7=100%, A-6= 100%, A-7=100%, A-8=100%, A-9=100%, |
10 | Common sanitary & Plumbing line work | N/A |
11 | Outside plastering work | 100% |
12 | Floor tiles/Marble work | A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5 =100%, A-6= 100%, A-7=100%, A-8=100%, A-9=100%, |
13 | L.C.C work | 100% |
14 | Grill & Railing work | A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5 =100%, A-6= 100%, A-7=100%, A-8=100%, A-9=100%, |
15 | Inside paint & Polishing work | A-1 =0%, A-2= 20%, A-3= 20%, A-4= 20%, A-5 =20%, A-6= 20%, A-7=30%, A-8=10%, A-9=10%, |
16 | Switch -Socket fitting work | N/A |
17 | Outside paint work | N/A |
18 | Door shutter work | N/A |
19 | Aluminum work | N/A |
20 | Tiles Pointing work & Marble finishing work | N/A |
21 | Commode – Basin fitting work and C.P fittings work | N/A |
22 | Lift/Generator /Substation /Solar work | N/A |
23 | Boundary wall /Ground floor development work | 10% |
24 | Roof top finishing work | 60% |
25 | Roof top Gardening work G.F Garden work | N/A |
16604