The Sunlight

Bashundhara R/A, Dhaka

Completion Date

November 2024

Status Updated

March, 2024

SL. No Name of the work Progress details
01 Foundation work 100%
02 Super Structure work 100%
03 Block Work A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5 =100%, A-6= 100%, A-7= 100%, A-8= 100%, A-8= 90%,
04 Electrical conducting work A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5 =100%, A-6= 100%, A-7= 100%, A-8= 80%, A-9= 50%,
05 Door frame fitting work A-1 =100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5 =100%, A-6 =100%, A-7 =100%, A-8 =100%,
06 Sanitary & plumbing line work A-1 =50%, A-2= 50%, A-3= 50%, A-4= 50%
07 In side Plastering work A-1 =100%, A-2= 100%, A-3=100%, A-4=80%, A-5=100%, A-6=100%, A-7=100%, A-8=20%, A-9=10%,
08 Electrical cable wiring work N/A
09 Wall tiles work A-1 =00%, A-2= 40%, A-3= 50%, A-4= 60%, A-5 =70%,
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work 25%
12 Floor tiles/Marble work N/A
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work 20%
25 Roof top Gardening work G.F Garden work N/A

16604